Proactive Productivity Management at Job Sites: Understanding Characteristics of Assumptions Made for Construction Processes during Planning Based on Case Studies and Interviews
Publication: Journal of Construction Engineering and Management
Volume 140, Issue 3
Abstract
During planning and execution of construction projects, project planners and managers make various assumptions with respect to execution of construction activities, availability of resources, suitability of construction methods, and status of preceding activities. However, not all of these assumptions are explicitly documented and verified before the construction activities start. Decisions made based on invalid assumptions can negatively impact the outcomes of construction projects, such as rework, activity delays, and extra material cost. To address the problems caused by invalid assumptions, this paper proposed to develop a formal approach to capture and represent assumptions and proactively verify assumptions to reduce the uncertainties associated with construction projects. To develop such a formal approach, an initial step is to identify characteristics of assumptions. The research team conducted two detailed case studies (i.e., a bridge rehabilitation project and a research lab renovation project) and seven interviews with construction professionals who have experience between 12 and 50 years. This paper provides a detailed discussion on the assumptions identified from case studies and interviews. The developed categorization of assumptions and the general characteristics of assumptions can serve as the foundation for a formal representation of assumptions, which helps construction professionals to proactively verify assumptions so as to avoid negative impacts of invalid assumptions on construction planning and execution.
Get full access to this article
View all available purchase options and get full access to this article.
Acknowledgments
This material is based upon work supported by the National Institute of Standards and Technology under Grant 60NANB9D9197. Any opinions, findings, and conclusions or recommendations expressed in this material are those of the authors and do not necessarily reflect the views of the National Institute of Standards and Technology. The authors also wish to thank Dr. Lucio Soibelman for his early efforts on this paper.
References
Akintoye, A. S., and MacLeod, M. J. (1997). “Risk analysis and management in construction.” Int. J. Proj. Manag., 15(1), 31–38.
Al-Bahar, J., and Crandall, K. (1990). “Systematic risk management approach for construction projects.” J. Constr. Eng. Manage., 533–546.
Allmon, E., Haas, C. T., Borcherding, J. D., and Goodrum, P. M. (2000). “U.S. construction labor productivity trends, 1970–1998.” J. Constr. Eng. Manage., 97–104.
Ballard, G. (1999). “Improving work flow reliability.” Proc. 7th International Group for Lean Construction, Conf., International Group for Lean Construction, Blacksburg, VA, 275–286.
Ballard, G. (2000). “The last planner system for production control.” Ph.D. thesis, Univ. of Birmingham, Birmingham, U.K.
Ballard, G., and Howell, G. (1998). “Shielding production: essential step in production control.” J. Constr. Eng. Manage., 11–17.
Ballard, G., and Howell, G. A. (2003). “An update on last planner1.” Proc., 11th Annual Conf., International Group for Lean Construction, Blacksburg, VA.
BuildingSMART. (2012). “IFC2x Edition 3 Technical Corrigendum 1.” 〈http://buildingsmart-tech.org/ifc/IFC2x3/TC1/html/index.htm〉 (Apr. 2012).
Bertelsen, S. (2004). “Lean construction: Where are we and how to proceed.” Lean Constr. J., 1(1), 46–69.
Campbell, D. T., and Fiske, D. W. (1959). “Convergent and discriminant validation by the multitrait-multimethod matrix.” Psychol. Bull., 56(2), 81.
Carbone, T. A., and Tippett, D. D. (2004). “Project risk management using the project risk FMEA.” Eng. Manage. J., 16(4), 28–35.
Chapman, C., and Ward, S. (1996). Project risk management: Processes, techniques and insights, Wiley, NJ.
Darwiche, A., Levitt, R. E., and Hayes-Roth, B. (1988). “OARPLAN: Generating project plans by reasoning about objects, actions and resources.” AI EDAM, 2(3), 169–181.
Dewar, J. A. (2002). Assumption-based planning: A tool for reducing avoidable surprises, Cambridge University Press, Cambridge, U.K.
Goodrum, P. M., and Haas, C. T. (2002). “Partial factor productivity and equipment technology change at activity level in U.S. construction industry.” J. Constr. Eng. Manage., 463–472.
Hendrickson, C., and Au, T. (2008). “Project management for construction: Fundamental concepts for owners, engineers, architects, and builders.” 〈http://ftp.ce.cmu.edu〉 Sep. 2012.
Hopfe, C. J. (2009). Uncertainty and sensitivity analysis in building performance simulation for decision support and design optimization, Technische Universiteit Eindhoven, Eindhoven, Netherlands.
Howell, G., Laufer, A., and Ballard, G. (1993). “Uncertainty and project objectives.” Project Appraisal J., 8(1), 37–43.
Hwang, S., and Liu, L. Y. (2009). “Contemporaneous time series and forecasting methodologies for predicting short-term productivity.” J. Constr. Eng. Manage., 1047–1055.
Kim, Y., and Ballard, G. (2010). “Management thinking in the earned value method system and the last planner system.” J. Manage. Eng., 223–228.
Lago, P., and van Vliet, H. (2005). “Explicit assumptions enrich architectural models.” Proc., 27th Int. Conf. on Software Engineering, ACM, New York, 206–214.
Lewis, G. A., Mahatham, T., and Wrage, L. (2004). “Assumptions management in software development.” Technical Note CMU/SEI-2004-TN-021, Carnegie Mellon Univ., PA.
McKim, R., Hegazy, T., and Attalla, M. (2000). “Project performance control in reconstruction projects.” J. Constr. Eng. Manage., 137–141.
Meyer, C. B. (2001). “A case in case study methodology.” Field Methods, 13(4), 329–352.
Miranskyy, A., Madhavji, N., Davison, M., and Reesor, M. (2005). Modelling assumptions and requirements in the context of project risk, Proc., Requirements Engineering, 2005. Proc. 13th IEEE Int. Conf., 471–472.
National Research Council. (2009). Advancing the Competitiveness and Efficiency of the U.S. Construction Industry, The National Academies Press, GA.
Navon, R., and Sacks, R. (2007). “Assessing research issues in automated project performance control (APPC).” Autom. Constr., 16(4), 474–484.
Ostacchini, I., and Wermelinger, M. (2009). “Managing assumptions during agile development.” Proc., Sharing and Reusing Architectural Knowledge, SHARK’09, ICSE Workshop on IEEE, 9–16.
Park, H.-S. (2006). “Conceptual framework of construction productivity estimation.” KSCE J. Civ. Eng., 10(5), 311–317.
Rowley, J. (2002). “Using case studies in research.” Manage. Res. News, 25(1), 16–27.
Salem, O., Solomon, J., and Minkarah, I. (2006). “Lean construction: From theory to implementation.” J. Manage. Eng., 168–175.
Tellis, W. (1997). “Application of a case study methodology.” The Qual. Rep., 3(3), 1–17.
Thomas, H. R., Horman, M. J., Minchin, R. E., Jr., and Chen, D. (2003). “Improving labor flow reliability for better productivity as lean construction principle.” J. Constr. Eng. Manage., 251–261.
Tirumala, A.S. (2006). “An assumptions management framework for systems software.” Ph.D. thesis, Univ. of Illinois at Urbana-Champaign, Champaign, IL.
Ward, S., and Chapman, C. (2003). “Transforming project risk management into project uncertainty management.” Int. J. Project Manage., 21(2), 97–105.
Yin, R. K. (2008). Case study research: Design and methods, Sage Publications, CA.
Information & Authors
Information
Published In
Copyright
© 2013 American Society of Civil Engineers.
History
Received: May 15, 2013
Accepted: Oct 30, 2013
Published online: Nov 28, 2013
Published in print: Mar 1, 2014
Discussion open until: Apr 28, 2014
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.