Last Planner Control System Applied to a Chemical Plant Construction
Publication: Journal of Construction Engineering and Management
Volume 138, Issue 2
Abstract
The main difference between the Last Planner production control system developed by Ballard and classical control systems is the way in which projects are controlled and planned. The Last Planner system focuses on controlling production units, workflows, and the quality of the performed work. It also permits the identification of the causes for the noncompletion of planned work and decision making in accordance with the project requirements so that actions are timely and productivity is increased. The objective of this paper is to present the results obtained from implementing the Last Planner system in the construction department of a chemical company. In this department, an information flow problem was detected among its members, in which supervisors lacked knowledge about the work to be performed until the project had been perfectly designed. This problem often led to long delays in the projects. The results from the Last Planner system implementation show that identifying the constraints of the planned work leads to an improvement in the percentage and quality of completed activities.
Get full access to this article
View all available purchase options and get full access to this article.
References
Alarcón, L. F., Ashley, D. B., and Cruz, J. (2000). “The impact of planning strategies on project performance: Learning from real and model project.” CIB W092 Int. Symp. on Information and Communication in Construction Procurement, Universidad Católica de Chile, Santiago, Chile.
Alarcón, L. F., Diethelm, S., Rojo, O., and Calderón, R. (2008). “Assessing the impacts of implementing lean construction.” Rev. Ing. Constr., 23(1), 26–33.
Ballard, H. G. (2000). “The last planner system of production control.” Ph.D. thesis, Dept. of Engineering, Univ. of Birmingham, Birmingham, UK.
Ballard, H. G., Howell, G., and Casten, M. (1996). “PARC: A case study.” Proc., 4th Annual Conf. of the Int. Group for Lean Construction, University of Birmingham, Birmingham, UK.
Choo, H., Tommelein, I., Ballard, G., and Zabelle, T. (1999). “Workplan: Constraint-based database for work package scheduling.” J. Constr. Eng. Manage., 125(3), 151–160.
Conte, A. (1998). “Last Planner, Lookahead, PPC: A driver to the site operations.” Proc., 6th Conf. of the Int. Group for Lean Construction, Guarujá, Brazil.
Fiallo, M., and Revelo, V. (2002). “Applying the Last Planner control system to a construction project: A case study in Quito, Ecuador.” Proc., 10th Conf. of the Int. Group for Lean Construction, Gramado, Brazil.
Koskela, L. (1999). “Management of production in construction: A theoretical view.” Proc., 7th Annual Conf. of the Int. Group for Lean Construction, University of California, Berkeley, CA.
Salem, O., Solomon, J., Genaidy, A., and Minkarah, I. (2006). “Lean construction: From theory to implementation.” J. Manage. Eng., 22(4), 168–175.
Information & Authors
Information
Published In
Copyright
© 2012 American Society of Civil Engineers.
History
Received: Apr 17, 2009
Accepted: May 12, 2011
Published online: May 14, 2011
Published in print: Feb 1, 2012
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.