Site Management of Work-in-Process Buffers to Enhance Project Performance Using the Reliable Commitment Model: Case Study
Publication: Journal of Construction Engineering and Management
Volume 137, Issue 9
Abstract
Buffers have been commonly used as a production strategy to protect construction processes from the negative impact of variability. Construction practitioners and researchers have proposed several buffering approaches for different production situations and contexts. However, these solutions have been impractical for managing buffers. To overcome this, this study proposes a new site methodology for managing work-in-process (WIP) buffer in repetitive projects, on the basis of the reliable commitment model (RCM). RCM is a decision-making tool based on lean principles, which uses statistical models to develop more reliable work plans at the operational level. RCM helps to manage WIP buffer in work plans by using site information and planning reliability indicators that result in improved project performance, such as labor productivity and process progress. A repetitive building project was used as a case study. The main finding was that labor productivity, process progress, and waiting times improved when using larger WIP buffers than those typically used among crews. This shows the potential of RCM as a practical tool to manage WIP buffer sizes and to promote the use of lean production strategies at the operational level.
Get full access to this article
View all available purchase options and get full access to this article.
References
Alarcón, L. F., Diethelm, S., Rojo, O., and Calderón, R. (2008). “Assessing the impacts of implementing lean construction.” Rev. Ing. Constr., 23(1), 26–33.
Ballard, G. (2000). “The last planner system of production control.” Ph.D. thesis, School of Civil Engineering, Faculty of Engineering, Univ. of Birmingham, Birmingham, U.K.
Ballard, G., and Howell, G. (1995). “Toward construction JIT.” Lean construction, L. F. Alarcón ed., A. A. Balkema, Netherlands, 291–300.
Ballard, G., and Howell, G. (1998). “What kind of production is construction?” Proc., 6th Annual Conf. of Int. Group for Lean Construction, Guaruja, Brazil.
Cohen, I., Mandelbaun, A., and Shtub, A. (2004). “Multi-project scheduling and control: A process-based comparative study of the critical chain methodology and some alternatives.” Proj. Manage. J., 35(2), 39–50.
Goldratt, E. M. (1997). Critical chain, North River, Great Barrington, MA.
González, V., and Alarcón, L. F. (2010). Uncertainty management in repetitive projects using work-in-process buffers, Editorial Lambert Academic Publishing, Germany.
González, V., Alarcón, L. F., Maturana, S., Mundaca, F., and Bustamante, J. (2010a). “Improving planning reliability and project performance using the reliable commitment model.” J. Constr. Eng. Manage., 136(10), 1129–1139.
González, V., Alarcón, L. F., and Molenaar, K. (2009). “Multiobjective design of work-in-process buffer for scheduling repetitive building projects.” Autom. Constr., 18(2), 95–108.
González, V., Alarcón, L. F., and Mundaca, F. (2008). “Investigating the relationship between planning reliability and project performance.” Prod. Plann. Contr., 19(5), 461–474.
González, V., Alarcón, L. F., and Ulloa, H. (2010b). “RCM-plan: A computer prototype for improving planning reliability from a lean production viewpoint.” Proc., CIB World Congress: Building a Better World, CIB, Rotterdam, Netherlands.
Hopp, W. J., and Spearman, M. L. (2000). Factory physics: Foundations of manufacturing management, 2nd Ed., Irwin/McGraw-Hill, Boston.
Horman, M. J. (2000). “Process dynamics: buffer management in building project operations.” Ph.D. thesis, Faculty of Architecture, Building and Planning, Univ. of Melbourne, Melbourne, Australia.
Horman, M. J., and Thomas, H. R. (2005). “Role of inventory buffers in construction labor performance.” J. Constr. Eng. Manage., 131(7), 834–843.
Jodlbauer, H., and Huber, A. (2008). “Service-level performance of MRP, Kanban, CONWIP and DBR due to parameter stability and environmental robustness.” Int. J. Prod. Res., 46(8), 2179–2195.
Kim, K., and De la Garza, J. M. (2003). “Phantom float.” J. Constr. Eng. Manage., 129(5), 507–517.
Laufer, A., Tucker, R. L., Shapira, A., and Shenhar, A. J. (1994). “The multiplicity concept in construction project planning.” Constr. Manage. Econ., 12(1), 53–65.
Leach, L. (2003). “Schedule and cost buffer sizing: How to account for the bias between project performance and your model.” Proj. Manage. J., 34(2), 34–47.
McGray, G. E., Purvis, R. L., and McCray, C. G. (2002). “Project management under uncertainty: The impact of heuristics and biases.” Proj. Manage. J., 33(1), 49–57.
Park, M., and Peña-Mora, F. (2004). “Reliability buffering for construction projects.” J. Constr. Eng. Manage., 130(5), 626–637.
Thomas, H. R., Horman, M. J., Lemes de Souza, U. E., and Zavrski, I. (2002). “Reducing variability to improve performance as a lean construction principle.” J. Constr. Eng. Manage., 128(2), 144–154.
Tommelein, I. D. (1998). “Pull-driven scheduling for pipe-spool installation: Simulation of lean construction technique.” J. Constr. Eng. Manage., 124(4), 279–288.
Tommelein, I. D., Riley, D. R., and Howell, G. A. (1999). “Parade game: Impact of work flow variability on trade performance.” J. Constr. Eng. Manage., 125(5), 304–310.
Womack, J. P., and Jones, D. T. (1996). Lean thinking: Banish waste and create wealth in your corporation, Simon and Schuster, New York.
Information & Authors
Information
Published In
Copyright
© 2011 American Society of Civil Engineers.
History
Received: Jul 30, 2010
Accepted: Jan 6, 2011
Published online: Jan 8, 2011
Published in print: Sep 1, 2011
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.