Site Management of Work-in-Process Buffers to Enhance Project Performance Using the Reliable Commitment Model: Case Study

Publication: Journal of Construction Engineering and Management
Volume 137, Issue 9

Abstract

Buffers have been commonly used as a production strategy to protect construction processes from the negative impact of variability. Construction practitioners and researchers have proposed several buffering approaches for different production situations and contexts. However, these solutions have been impractical for managing buffers. To overcome this, this study proposes a new site methodology for managing work-in-process (WIP) buffer in repetitive projects, on the basis of the reliable commitment model (RCM). RCM is a decision-making tool based on lean principles, which uses statistical models to develop more reliable work plans at the operational level. RCM helps to manage WIP buffer in work plans by using site information and planning reliability indicators that result in improved project performance, such as labor productivity and process progress. A repetitive building project was used as a case study. The main finding was that labor productivity, process progress, and waiting times improved when using larger WIP buffers than those typically used among crews. This shows the potential of RCM as a practical tool to manage WIP buffer sizes and to promote the use of lean production strategies at the operational level.

Get full access to this article

View all available purchase options and get full access to this article.

References

Alarcón, L. F., Diethelm, S., Rojo, O., and Calderón, R. (2008). “Assessing the impacts of implementing lean construction.” Rev. Ing. Constr., 23(1), 26–33.
Ballard, G. (2000). “The last planner system of production control.” Ph.D. thesis, School of Civil Engineering, Faculty of Engineering, Univ. of Birmingham, Birmingham, U.K.
Ballard, G., and Howell, G. (1995). “Toward construction JIT.” Lean construction, L. F. Alarcón ed., A. A. Balkema, Netherlands, 291–300.
Ballard, G., and Howell, G. (1998). “What kind of production is construction?” Proc., 6th Annual Conf. of Int. Group for Lean Construction, Guaruja, Brazil.
Cohen, I., Mandelbaun, A., and Shtub, A. (2004). “Multi-project scheduling and control: A process-based comparative study of the critical chain methodology and some alternatives.” Proj. Manage. J., 35(2), 39–50.
Goldratt, E. M. (1997). Critical chain, North River, Great Barrington, MA.
González, V., and Alarcón, L. F. (2010). Uncertainty management in repetitive projects using work-in-process buffers, Editorial Lambert Academic Publishing, Germany.
González, V., Alarcón, L. F., Maturana, S., Mundaca, F., and Bustamante, J. (2010a). “Improving planning reliability and project performance using the reliable commitment model.” J. Constr. Eng. Manage., 136(10), 1129–1139.
González, V., Alarcón, L. F., and Molenaar, K. (2009). “Multiobjective design of work-in-process buffer for scheduling repetitive building projects.” Autom. Constr., 18(2), 95–108.
González, V., Alarcón, L. F., and Mundaca, F. (2008). “Investigating the relationship between planning reliability and project performance.” Prod. Plann. Contr., 19(5), 461–474.
González, V., Alarcón, L. F., and Ulloa, H. (2010b). “RCM-plan: A computer prototype for improving planning reliability from a lean production viewpoint.” Proc., CIB World Congress: Building a Better World, CIB, Rotterdam, Netherlands.
Hopp, W. J., and Spearman, M. L. (2000). Factory physics: Foundations of manufacturing management, 2nd Ed., Irwin/McGraw-Hill, Boston.
Horman, M. J. (2000). “Process dynamics: buffer management in building project operations.” Ph.D. thesis, Faculty of Architecture, Building and Planning, Univ. of Melbourne, Melbourne, Australia.
Horman, M. J., and Thomas, H. R. (2005). “Role of inventory buffers in construction labor performance.” J. Constr. Eng. Manage., 131(7), 834–843.
Jodlbauer, H., and Huber, A. (2008). “Service-level performance of MRP, Kanban, CONWIP and DBR due to parameter stability and environmental robustness.” Int. J. Prod. Res., 46(8), 2179–2195.
Kim, K., and De la Garza, J. M. (2003). “Phantom float.” J. Constr. Eng. Manage., 129(5), 507–517.
Laufer, A., Tucker, R. L., Shapira, A., and Shenhar, A. J. (1994). “The multiplicity concept in construction project planning.” Constr. Manage. Econ., 12(1), 53–65.
Leach, L. (2003). “Schedule and cost buffer sizing: How to account for the bias between project performance and your model.” Proj. Manage. J., 34(2), 34–47.
McGray, G. E., Purvis, R. L., and McCray, C. G. (2002). “Project management under uncertainty: The impact of heuristics and biases.” Proj. Manage. J., 33(1), 49–57.
Park, M., and Peña-Mora, F. (2004). “Reliability buffering for construction projects.” J. Constr. Eng. Manage., 130(5), 626–637.
Thomas, H. R., Horman, M. J., Lemes de Souza, U. E., and Zavrski, I. (2002). “Reducing variability to improve performance as a lean construction principle.” J. Constr. Eng. Manage., 128(2), 144–154.
Tommelein, I. D. (1998). “Pull-driven scheduling for pipe-spool installation: Simulation of lean construction technique.” J. Constr. Eng. Manage., 124(4), 279–288.
Tommelein, I. D., Riley, D. R., and Howell, G. A. (1999). “Parade game: Impact of work flow variability on trade performance.” J. Constr. Eng. Manage., 125(5), 304–310.
Womack, J. P., and Jones, D. T. (1996). Lean thinking: Banish waste and create wealth in your corporation, Simon and Schuster, New York.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 137Issue 9September 2011
Pages: 707 - 715

History

Received: Jul 30, 2010
Accepted: Jan 6, 2011
Published online: Jan 8, 2011
Published in print: Sep 1, 2011

Permissions

Request permissions for this article.

Authors

Affiliations

Vicente González [email protected]
Lecturer, Dept. of Civil and Environmental Engineering, Univ. of Auckland, Private Bag 92019, Auckland 1142, New Zealand (corresponding author). E-mail: [email protected]
Luis Fernando Alarcón lAlarcó[email protected]
Professor, Dept. of Construction, Engineering, and Management, Pontificia Universidad Católica de Chile, Casilla 306, Correo 22, Santiago, Chile. E-mail: lAlarcó[email protected]
Sergio Maturana [email protected]
Professor, Dept. of Industrial and Systems Engineering, Pontificia Universidad Católica de Chile, Casilla 306, Correo 22, Santiago, Chile. E-mail: [email protected]
José Antonio Bustamante [email protected]
Planning and Development Engineer, Socovesa, Santiago, Chile. E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share