Erection Procedure Effects on Deformations and Stresses in a Large-Radius, Horizontally Curved, I-Girder Bridge
Publication: Journal of Bridge Engineering
Volume 12, Issue 4
Abstract
Special attention is required in the construction of horizontally curved steel I-girder bridges due to coupled effects of primary bending and torsional forces. Misguided steel erection procedures can lead to undesired stresses, deflections, and rotations in these types of bridges, resulting in a structure with misaligned geometry and in an unknown state of stress. Further complicating the issue, little guidance related to curved bridge behavior during construction is provided by current design codes, leaving contractors and designers uncertain as to the most appropriate steps to take to achieve an efficient, safe structure. A horizontally curved, six-span steel I-girder bridge located in central Pennsylvania that experienced severe geometric misalignments and fit-up complications during steel erection was studied to investigate curved girder behavior during construction. The structure was monitored during corrective procedures intended to realign it with the design geometry, and field data used to calibrate a three-dimensional computer model generated via SAP2000. The techniques and assumptions proven in the calibration process were used to create a numerical model of a three-span continuous portion of the bridge, which was the subject of several analyses exploring the effects erection sequencing, implementation of upper lateral bracing, and use of temporary supports had on the final deformed shape of the curved superstructure. Findings indicated that using paired girder erection produced smaller radial and vertical deformations than single girder techniques for this structure, and that the use of lateral bracing between the fascia and adjacent interior girders and the placement of temporary shoring towers at span quarter points are both effective means of further reducing levels of deflection.
Get full access to this article
View all available purchase options and get full access to this article.
References
Bell, B. J. (2004). “Effects of erection sequencing on the response of a horizontally curved I-girder bridge.” MS thesis, The Pennsylvania State Univ., University Park, Pa.
Bradford, M. A., Uy, B., and Pi, Y. L. (2001). “Behavior of unpropped composite girders curved in plan under construction loading.” Eng. Struct., 23, 779–789.
Chavel, B. W., and Earls, C. J. (2002). “Evaluation of erection procedures of the horizontally curved steel I-girder Ford City bridge.” Univ. of Pittsburgh Research Rep. No. CE/ST 18, Univ. of Pittsburgh, Pittsburgh.
Davidson, J. S., Keller, M. A., and Yoo, C. C. (1996). “Cross-frame spacing and parametric effects in horizontally curved I-girder bridges.” J. Struct. Eng., 122(9), 1089–1096.
Galambos, T. V., Hajjar, J. F., Leon, R. T., Huang, W., Pulver, B. E., and Rudie, B. J. (1996). “Stresses in steel curved girder bridges.” Minnesota Dept. of Transportation Rep. No. MN/RC-96/28, Minneapolis.
Huang, W. H. (1996). “Curved I-girder systems.” Ph.D. dissertation, Univ. of Minnesota, Minneapolis.
Linzell, D. G. (1999). “Studies of a full-scale horizontally curved steel I girder bridge system under self-weight.” Ph.D. dissertation, Georgia Institute of Technology, Atlanta.
Linzell, D. G. (2000). “Elastic experimental and analytical studies of curved steel bridge behavior under self-weight.” Proc., 3rd Structural Specialty Conf. of the Canadian Society of Structural Engineers, London, Ontario, Canada, 232–239.
Linzell, D. G. (2001). “Curved steel bridges—What happens during construction? Information from experimental and analytical studies in the U.S.” 9th Proc., Annual Conf. and Exhibition, Structure Faults and Repair—2001, London.
Pi, Y.-L., Bradford, M. A., and Trahair, N. S. (2000). “Inelastic analysis and behavior of steel I-beams curved in plan.” J. Struct. Eng., 126(7), 772–779.
Schelling, D., Namini, A. H., and Fu, C. C. (1989). “Construction effects on bracing on curved I-girders.” J. Struct. Eng., 115(9), 2145–2165.
Sennah, K. E. O., and Lee, G. (2000). “Moment distribution in curved composite steel I-girder bridges at construction phase.” Proc., 3rd Structural Specialty Conf. of the Canadian Society for Civil Engineering, London, Ontario, Canada, 240–245.
Zureick, A., Leon, R. T., Burrell, J., and Linzell, D. (2000). “Curved steel girders: Experimental and analytical studies.” Eng. Struct., 22(2), 180–190.
Zureick, A., Naqib, R., and Yadlosky, J. M. (1994). “Curved steel bridge research project. Interim report I: Synthesis.” Publication Number FHWA-RD-93-129, HDR Engineering, Inc., Pittsburgh.
Information & Authors
Information
Published In
Copyright
© 2007 ASCE.
History
Received: May 31, 2005
Accepted: Jul 6, 2006
Published online: Jul 1, 2007
Published in print: Jul 2007
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.