Realized Economic Efficiency of Road Project Delivery Systems

Publication: Journal of Infrastructure Systems
Volume 13, Issue 4

Abstract

Lately project delivery methods where the implementer offers broader service packages are increasingly used in infrastructure projects worldwide. At the same time, the number of alternative project delivery methods has increased making selection of the best one difficult. The road authority must understand the features of the methods in order to select the most effective ones in terms of economic efficiency. To assist in the selection, this research compared the operating principles and performance of design–bid–build, construction management, design–build (DB), and design–build–maintain (DBM) based on an international interview survey and an extensive literature review. Opinions presented by the interviewees and literature review all pointed to the same direction. Based on the analysis of road procurement, broader service packages give, on average, better value for the money and enable clients to attain their goals better than more traditional methods. DB and DBM seem to outperform more conservative procurement methods both in cost and value generation terms. Each method, however, is particularly suitable for specific projects and should be selected accordingly.

Get full access to this article

View all available purchase options and get full access to this article.

References

AECOM Consulting and Science Applications International Corporation (AECOM). (2003). “Design–build effectiveness study—As required by TEA-21 Section 1307(f).” US DOT Advisory Team slides, AECOM, Birmingham, Ala.
Alhazmi, T., and McCaffer, R. (2000). “Project procurement system selection model.” J. Constr. Eng. Manage., 126(3), 176–184.
Ardani, A., and Jesaitis, P. (1999). “Evaluation of design–build practice in Colorado IR(CX)70-4(143).” Rep. No. CDOT-DTD-R-99-5, Colorado Dept. of Transportation, Denver.
Arditi, D., and Lee, D.-E. (2003). “Assessing corporate service quality performance of design–build contracts using quality function deployment.” Constr. Manage. Econom., 21, 175–185.
Arthur Andersen and Enterprise LSE. (2000). Value for money drivers in the private finance initiative, Treasury Taskforce, London.
Federal Highway Administration (FHWA). (2002). “Contract administration: Technology and practice in Europe.” FHwA-PL-03-002, FHwA, Washington, D.C.
Gransberg, D. D., Dillon, W. D., Reynolds, L., and Boyd, J. (1999). “Quantitative analysis of partnered project performance.” J. Constr. Eng. Manage., 125(3), 161–166.
Konchar, M. D. (1997). “A comparison of United States project delivery systems.” Ph.D., Pennsylvania State Univ., University Park, Pa.
Koppinen, T., and Lahdenperä, P. (2004a). “Road sector experiences on project delivery methods.” VTT Research Notes 2260, Espoo, Finland.
Koppinen, T., and Lahdenperä, P. (2004b). “The current and future performance of road project delivery methods.” VTT Publications 549, Espoo, Finland.
Kumaraswamy, M. M., and Dissanayaka, S. M. (1996). “Procurement by objectives.” J. Constr. Procure., 2(2), 38–51.
Kumaraswamy, M. M., and Dissanayaka, S. M. (2001). “Developing a decision support system for building project procurement.” Build. Environ., 36(3), 337–349.
Lahdenperä, P., and Koppinen, T. (2003). “Incentive payment bases for a construction project—Part 1. International state-of-art review.” VTT Research Notes 2191, Espoo, Finland (in Finnish).
Love, E. D. (2002). “Influence of project type and procurement method on rework costs in building construction projects.” J. Constr. Eng. Manage., 128(1), 18–29.
Molenaar, K. R., and Songer, A. D. (1998). “Model for public sector design–build project selection.” J. Constr. Eng. Manage., 124(6), 467–479.
Molenaar, K. R., Songer, A. D., and Barash, M. (1999). “Public-sector design–build evolution and performance.” J. Manage. Eng., 15(2), 54–62.
National Audit Office (NAO). (2001). “Managing the relationship to secure a successful partnership in PFI projects.” National Audit Office, Report by the Comptroller and Auditor General HC 375, National Audit Office, London.
National Audit Office (NAO). (2003). “PFI: Construction performance.” National Audit Office, Report by the Comptroller and Auditor General, HC 371, National Audit Office, London.
Ng, S. T., Luu, D. T., Chen, S. E., and Lam, K. C. (2002). “Fuzzy membership functions of procurement selection criteria.” Constr. Manage. Econom., 20, 285–296.
Palaneeswaran, E. (2000). “Contractor selection systems for design–build projects.” Ph.D. thesis, Univ. of Hong Kong, Hong Kong.
Pakkala, P. (2002). Innovative project delivery methods for infrastructure. An international perspective, Finnish Road Enterprise, Helsinki, Finland.
Zhang, X. (2006). “Public clients’ best value perspectives of public private partnerships in infrastructure development.” J. Constr. Eng. Manage., 132(2), 107–114.

Information & Authors

Information

Published In

Go to Journal of Infrastructure Systems
Journal of Infrastructure Systems
Volume 13Issue 4December 2007
Pages: 321 - 329

History

Received: Sep 27, 2006
Accepted: Jan 30, 2007
Published online: Dec 1, 2007
Published in print: Dec 2007

Permissions

Request permissions for this article.

Authors

Affiliations

Tiina Koppinen
Research Scientist, VTT Technical Research Centre of Finland, P.O. Box 1300, 33101 Tampere, Finland. E-mail: [email protected]
Pertti Lahdenperä
Research Professor, VTT Technical Research Centre of Finland, P.O. Box 1300, 33101 Tampere, Finland.

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share