Integrated Design/Construction/Operations Analysis for Fast-Track Urban Freeway Reconstruction
Publication: Journal of Construction Engineering and Management
Volume 131, Issue 12
Abstract
The California Department of Transportation is rehabilitating or reconstructing deteriorated urban freeways using long-life (30+ years) strategies. These pavements were constructed between 1955 and 1970 with design lives of 20 years. This paper summarizes preconstruction analysis of the fast-track pavement reconstruction on Interstate-15 (I-15) at Devore which used two one-roadbed continuous (about 210 h) closures with round-the-clock operations. The integrated analysis concluded that the one-roadbed continuous closures are the most economical scenario when compared to traditional nighttime or weekend closures from the perspective of schedule, delay, and costs. The preconstruction was validated with as-built construction and traffic performances monitored during construction. The construction management plan—including contingency, incentives, and critical path method schedule—was developed utilizing the Construction Analysis for Pavement Rehabilitation Strategies (CA4PRS) computer model. The results of this planning study are useful for transportation agencies in developing highway rehabilitation strategies that balance the maximization of construction productivity with a minimization of traffic delay.
Get full access to this article
View all available purchase options and get full access to this article.
Acknowledgments
This study was funded by the California Department of Transportation (Caltrans). The research team acknowledges the information and coordination support contributed by Caltrans District 8. Thanks are extended to Loren Bloomberg (CH2M Hill), Tom Salata (American Concrete Pavement Association), and Nadarajah Sivaneswara (Washington State Department of Transportation), for their technical advice and comments on this project.
References
Arditi, D., Khisty, J., and Yasamis, F. (1997). “Incentive/disincentive provisions in highway contracts.” J. Constr. Eng. Manage., 123(3), 302–307.
Bureau of the Census. (1994). Statistical abstracts of the United States 1994: The national data book, U.S. Department of Commerce, Washington, D.C.
California Department of Transportation (Caltrans). (2003). “Long-life pavement rehabilitation strategies.” Sacramento, Calif. ⟨http://www.dot.ca.gov/research/roadway/llprs/llprs.htm⟩ (October 1).
California Department of Transportation (Caltrans). (2004). “I-15 Devore Rapid Rehab Project.” Sacramento, Calif. ⟨http://www.dot.ca.gov/dist8/i15devore/⟩ (October 3).
Federal Highway Administration (FHWA). (1996). “Public roads.” J. Highway Research Development, 59(3), winter.
Herbsman, Z. J., and Glagola, C. R. (1998). “Lane rental–Innovative way to reduce road construction time.” J. Constr. Eng. Manage., 124(5), 411–417.
Lee, E. B., and Ibbs, C. W. (2005). “A computer simulation model: Construction analysis for highway rehabilitation strategies (CA4PRS).” J. Constr. Eng. Manage., 131(4), 449–458.
Lee, E. B., Ibbs, W., Roesler, J., and Harvey, J. (2000). “Construction productivity and constraints for concrete pavement rehabilitation in urban corridors.” Transportation Research Record, 1712, Transportation Research Board, Washington, D.C., 13–22.
Lee, E. B, Ibbs, C. W., and Thomas, D. (2005a). “Minimizing total cost for urban freeway reconstruction with integrated construction/traffic analysis.” J. Infrastruct. Syst., in press.
Lee, E. B., Lee, H. J., and Akbarian, M. (2005b). “Accelerated pavement rehabilitation and reconstruction with long-life asphalt concrete on high-trafficked urban highway.” J. Transportation Research Board, in press.
Lee, E. B., Roesler, J. R., Harvey, J. T., and Ibbs, C. W. (2002). “Case study of urban concrete pavement reconstruction on Interstate 10.” J. Constr. Eng. Manage., 128(1), 49–56.
Roesler, J. R., Harvey, J., Hung, D., du Plessis, L., and Bush, D. (1999). “Evaluation of longer-life concrete pavements for California using accelerated pavement testing.” Proc., Accelerated Pavement Testing International Conf., Reno, Nev.
Timm, D., Voller, V., Lee, E. B., and Harvey, J. (2001). “MultiCool: A numerical solution program for multi-layer cooling time of asphalt concrete pavement.” Int. J. Pavement Eng., 2(3), 169–185.
Transportation Research Board. (2000) Highway capacity manual (HCM), National Research Council, Washington, D.C.
Wisconsin Department of Transportation (WisDOT. (2002). “Plans & projects: Existing highways.” Madison, Wis. ⟨http://www.dot.wisconsin.gov/projects/state/sixyear/hwys.htm⟩ (June 12).
Information & Authors
Information
Published In
Copyright
© 2005 ASCE.
History
Received: Nov 6, 2003
Accepted: May 3, 2005
Published online: Dec 1, 2005
Published in print: Dec 2005
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.