Improved Measured Mile Analysis Technique

Publication: Journal of Construction Engineering and Management
Volume 131, Issue 12

Abstract

Quantifying lost labor productivity on construction projects is difficult and sometimes subjective. A widely accepted way to quantify losses is the “measured mile” approach. It compares periods of a project that have been impacted by change to those that have not been impacted. As currently practiced the measured mile relies on subjectively identifying that reference period. In this paper the measured mile and a variant, the baseline method, are analyzed and compared to a new, proposed statistical clustering method. This new approach is advocated because it determines its reference period using objective criteria. A case study is included to show how the three methods work, and advantages and disadvantages of each method are presented in this paper.

Get full access to this article

View all available purchase options and get full access to this article.

References

Chitester, D. D. (2003). “The measured mile: Going the distance to calculate lost productivity.” ⟨www.chitester.com⟩.
Diekmann, J. E., and Nelson, M. C. (1985). “Construction claims: Frequency and severity.” J. Constr. Eng. Manage., 111(1), 74–81.
Dillon, W. R. (1984). Multivariate analysis, Wiley, N.Y.
Hanna, A. S., Russell, J. S., Gotzion, T. W., and Nordheim, E. V. (1999a). “Impact of change orders on labor efficiency for mechanical construction.” J. Constr. Eng. Manage., 125(3), 176–184.
Hanna, A. S., Russell, J. S., Nordheim, E. V., and Bruggink, M. J. (1999b). “Impact of change orders on labor efficiency for electrical construction.” J. Constr. Eng. Manage., 125(4), 224–232.
Hester, W. T., Kuprenas, J., and Chang, T. C. (1991). “Construction changes and change orders.” Source Document 66, Construction Industry Institute, Univ. of Texas, Tex.
Ibbs, C. W. (1997). “Quantitative impacts of project change: Size issues.” J. Constr. Eng. Manage., 123(3), 308–311.
Ibbs, C. W., and Allen, W. E. (1995). “Quantitative impacts of project change.” Source Document 108, Construction Industry Institute, Univ. of Texas, Tex.
Ibbs, C. W., Kwak, Y. H., Ng, T., and Odabasi, M. (2003). “Project delivery systems and project change: Quantitative analysis.” J. Constr. Eng. Manage., 129(4), 382–387.
Ibbs, C. W., Lee, S., and Li, M. (1998). “Fast-tracking’s impact on project change.” Proj. Manage. J., 29(4), 25–31.
Leonard, C. A. (1988). “The effects of change orders on productivity.” MS thesis, Concordia Univ., Montreal.
Loulakis, M. C., and Santiago, S. J. (1999). “Getting the most out of your ‘measured mile’ approach.” Civ. Eng. (N.Y.), 69(11), 69.
Mechanical Contractors Association of America (MCAA). (1986). Labor estimating manual, Rockville, Md.
National Electrical Contractors Association (NECA). (1976). Manual of labor units, Bethesda, Md.
Rachad, A. (2003). Interpreting quantitative data with SPSS, Sage, London.
Semple, C., Hartman, F. T., and Jergeas, G. (1994). “Construction claims and disputes: Causes and cost/time overruns.” J. Constr. Eng. Manage., 120(4), 785–795.
Thomas, H. R., Horman, M. J., de Souza, U. E. L., and Zavrski, I. (2002). “Reducing variability to improve performance as a lean construction principle.” J. Constr. Eng. Manage., 128(2), 144–154.
Thomas, H. R., Horman, M. J., Minchin, R. E., and Chen, D. (2003a). “Improving labor flow reliability for better productivity as lean construction principle.” J. Constr. Eng. Manage., 129(3), 251–261.
Thomas, H. R., Minchin, R. E., and Chen, D. (2003b). “Role of workforce management in bridge superstructure labor productivity.” J. Manage. Eng., 19(1), 9–16.
Thomas, H. R., Riley, D. R., and Sanvido, V. E. (1999). “Loss of labor productivity due to delivery methods and weather.” J. Constr. Eng. Manage., 125(1), 39–46.
Thomas, H. R., and Sanvido, V. E. (2000a). “Quantification of losses caused by labor inefficiencies: Where is the elusive measured mile?” Constr. Law Bus., 1(3), 1–14.
Thomas, H. R., and Sanvido, V. E. (2000b). “Role of the fabricator in labor productivity.” J. Constr. Eng. Manage., 126(5), 358–365.
Thomas, H. R., and Zavrski, I. (1999). “Construction baseline productivity: Theory and practice.” J. Constr. Eng. Manage., 125(5), 295–303.
U.S. Army Corps of Engineers (UACE). (1979). “Modification impact evaluation guide.” EP-415-1̱3, Office of the Chief of Engineers, Washington, D.C.
Zink, D. A. (1986). “The measured mile: Proving construction inefficiency costs.” Cost Eng., 28(4), 19–21.
Zink, D. A. (1990). “Impacts and construction inefficiency.” Cost Eng., 32(11), 21–23.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 131Issue 12December 2005
Pages: 1249 - 1256

History

Received: Dec 5, 2003
Accepted: May 16, 2005
Published online: Dec 1, 2005
Published in print: Dec 2005

Permissions

Request permissions for this article.

Authors

Affiliations

William Ibbs [email protected]
Professor of Construction Management, Dept. of Civil & Environmental Engineering, Univ. of California, Berkeley, CA 94720. E-mail: [email protected]
Doctoral Student, Dept. of Civil & Environmental Engineering, Univ. of California, Berkeley, CA 94720. E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share