Constraint-Based Planning with Integrated Production Scheduler over Internet
Publication: Journal of Construction Engineering and Management
Volume 129, Issue 3
Abstract
Identifying and removing constraints from bottleneck activities help to reduce uncertainties in construction processes and increases the transparency of project management. The present means of look-ahead planning do poorly in resolving hidden constraints in the supply chain and information flow. Accordingly, work plans are vulnerable to the uncertainties that result in flow variation. It has been realized that reducing and eliminating critical constraints through better means of look-ahead planning are the keys to achieving reliable workflow and, consequently, increased productivity. This paper presents a constraint-based planning tool, Integrated Production Scheduler (IPS), to enhance planning reliability while adopting lean construction principles and the theory of constraints. Unlike the critical path method, the IPS models two additional types of constraints related to resource supply and information exchange. It employs four activity buffers: working, shielding, pulling, and screening for managing critical constraints and shielding the production from uncertainties. The implementation of the IPS is prototyped as a distributed scheduling system using Internet technologies such as Java and XML. It facilitates setting up a transparent project management environment where faster communication and active collaboration among project members are achievable.
Get full access to this article
View all available purchase options and get full access to this article.
References
Ballard, G., and Howell, G.(1998). “Shielding production: Essential step in production control.” J. Constr. Eng. Manage., 124(1), 11–17.
Chua, D. K. H., Shen, L. J., and Bok, S. H. (1999). “Integrated production scheduler for construction look-ahead planning.” Proc., 7th Annual Conf. on Lean Construction, Construction Engineering and Management Program, Univ. of California, Berkeley, Calif., 287–298.
Fullerton, R. R., and McWatters, C. S.(2001). “The production performance benefits from JIT implementation.” J. Operations Manage., 19(1), 81–96.
Goldratt, E. M.(1988). “Computerized shop floor scheduling.” Int. J. Prod. Res., 26(4), 443–455.
Goldratt, E. M. (1990). What is this thing called theory of constraints and how should it be implemented?, North River Press, New York.
Hansen, K. L., Gann, D. M., and Groak, S.(1998). “Information technology decision support and business process change in the USA.” J. of Engrg., Constr. and Arch. Mgmt., 5(2), 115–126.
Hoel, K., and Taylor, S. G.(1999). “Quantifying buffers for project schedules.” Prod. and Inv. Mgmt. J., 40(2), 43–47.
Horton, I. (1999). Beginning Java 2, Wrox Press, Arden House, Birmingham, U.K.
Howell, G., and Ballard, G. (1996). “Can project control do its job?” Proc., 4th Annual Int. Conf. on Lean Construction, School of Civil Engineering, Univ. of Birmingham, Birmingham, U.K.
Krumel, A. (1999). “Write high-performance RMI servers and swing clients.” JavaWorld, Itworld.com, Inc. (available at http://www.javaworld.com/javaworld/jw-04-1999/jw-04-enterprise.html).
Koskela, L. (1992). “Application of the new production philosophy to construction.” Tech. Rep. No. 72, Center for Integrated Facility Engineering, Dept. of Civil Engineering, Stanford Univ., Stanford, Calif.
Myers, T., and Nakhimovsky, A. (1999). Professional Java XML programming with servlets and JSP, Wrox Press, Arden House, Birmingham, U.K.
Radovilsky, Z. D.(1998). “A quantitative approach to estimate the size of the time buffer in the theory of constraints.” Int. J. of Prod. Econ., 55(2), 113–119.
Rahman, S.(1998). “Theory of constraints. A review of the philosophy and its applications.” Int. J. Operat. Product. Manage., 18(4), 336–355.
Shen, L. J., Chua, D. K. H., and Bok, S. H. (2000). “Distributed scheduling with integrated production scheduler.” Proc., 8th Annual Conf. on Lean Construction, Programme on Innovation in the Built Environment SPRU, Univ. of Sussex, Brighton, U.K. (available at http://www.sussex.ac.uk/spru/imichair/iglc8).
Tommelein, I. D., and Ballard, G. (1997). “Look-ahead planning: Screening and pulling.” Tech. Rep. No. 97-9, Civil and Environmental Engineering Dept., Univ. of California, Berkeley, Calif.
Tu, Y.-M., and Li, R.-K.(1998). “Constraint time buffer determination model.” Int. J. Prod. Res., 36(4), 1091–1103.
Information & Authors
Information
Published In
Copyright
Copyright © 2003 American Society of Civil Engineers.
History
Received: Apr 24, 2001
Accepted: May 8, 2002
Published online: May 15, 2003
Published in print: Jun 2003
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.