Resource Leveling in Construction by Optimization
Publication: Journal of Construction Engineering and Management
Volume 115, Issue 2
Abstract
Resource leveling is needed in construction to avoid the difficulties associated with the large variations in resource usage. This paper presents an integer‐linear optimization model of resource leveling (single resource, continuous activities) which guarantees the optimal leveling. The objective function of the model minimizes the absolute deviations between the resource requirements and a uniform resource level, between consecutive resource requirements, or between the resource requirements and desirable nonuniform resource levels. The model requires as input the critical path method (CPM) scheduling results, from which the constraints and objective function of the model are established automatically by an interface program. Extensions of the model to multiple resources and trade‐off of cost scheduling are suggested. The model is applicable to activity‐on‐arrow, activity‐on‐node, and precedence networks and is intended for small‐ to medium‐sized construction projects.
Get full access to this article
View all available purchase options and get full access to this article.
References
1.
Adrian, J. (1973). Quantitative methods in construction management. American Elsevier Publishing Co., New York, N.Y.
2.
Ahuja, H. (1976). Construction performance control by networks. John Wiley and Sons, New York, N.Y.
3.
Antill, J., and Woodhead, R. (1982). Critical path methods in construction practice. 3d Ed., Wiley‐Interscience, New York, N.Y.
4.
Burges, A., and Killebrew, J. (1962). Variation in activity level in a cyclical arrow diagram. J. Indust. Engrg., 13(2).
5.
Galbreath, R. (1965). Computer program for leveling resource usage. J. Constr. Div., ASCE, 91(1), 107–124.
6.
Harris, R. (1978). Precedence and arrow networking techniques for construction. John Wiley and Sons, New York, N.Y.
7.
Karaa, F., and Nasr, A. (1986). Resource management in construction. J. Constr. Engrg. and Mgmt., ASCE, 112(3), 346–357.
8.
Moder, J., Phillips, C., and Davis, E. (1983). Project management with CPM, PERT, and precedence diagramming. 3d Ed., Van Nostrand Reinhold Company, New York, N.Y.
9.
Phillips, D., and Garcia‐Diaz, A. (1981). Fundamentals of network analysis. Prentice‐Hall, Inc., Englewood Cliffs, N.J.
10.
Schrage, L. (1981). Linear programming models with LINDO. The Scientific Press, Palo Alto, Calif.
11.
Schrage, L. (1984). Linear, integer, and quadratic programming with LINDO: User's manual. The Scientific Press,. Palo Alto, Calif.
12.
Shaffer, L., Ritter, J., and Mayer, W. (1965). The critical path method. McGraw‐Hill Book Co., New York, N.Y.
Information & Authors
Information
Published In
Copyright
Copyright © 1989 ASCE.
History
Published online: Jun 1, 1989
Published in print: Jun 1989
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.