Case Studies
May 31, 2023

Analyzing Contingency Cost Risks in a Pipeline EPC Project Using a Monte Carlo Simulation

Publication: Journal of Pipeline Systems Engineering and Practice
Volume 14, Issue 3

Abstract

Indonesia was the eighth largest exporter of liquefied natural gas in 2021, with a total export volume of 14.6  billionm3. Therefore, transporting natural gas becomes an essential program to support the increase of liquefied natural gas. Through the Cooperation Contract Contractors (CCC), a cooperation contract between government of Indonesia (GoI) and Oil Company, the government appoints the engineering, procurement, and construction (EPC) contractor to build the pipeline. However, EPC contractors are at significant risk in calculating contingency costs resulting in cost overruns. This study identified contingency risk factors, determined the most effective risks, and developed contingency costs for EPC pipeline projects. A literature review was conducted, a probability matrix for risk ranks was developed, and Monte Carlo simulation was used. The results indicated that there are risk factors significantly influencing the calculation of contingency costs for EPC pipeline projects, namely changes in the scope of work, delays in permits from the government or regulatory authorities, issues with local communities and the project environment, delays in the construction work, and the material delivery of long-lead items. Based on these factors, the contingency cost risk in a pipeline EPC project determined using Monte Carlo simulation was 14.87%. Before utilizing risk modeling, an efficiency of 4.23%, or a cost savings of $3,323,064.71, was achieved. For future research, it would be preferable to simulate more than three sample EPC projects to analyze variances in contingency costs.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code that support the findings of this study are available from the corresponding author upon reasonable request.

Acknowledgments

Some parts of this study were based on the research work conducted during the thesis research at Universitas Pelita Harapan.

References

AACE (The Association for the Advancement of Cost Engineering) International. 2008. Risk analysis and contingency determination using range estimating. Fairmont, WV: AACE.
Adi, T. J. W., and S. Yunwanti. 2014. “Pemodelan estimasi biaya kontingensi berbasis risiko pada proyek engineering-procurement-construction.” [In Indonesian.] Infrastruktur: Teknik Sipil 4 (1): 50–57.
Alsan, R. 2014. “Faktor-Faktor Risiko Pada Tahap Eksekusi Proyek di Konstruksi EPC Yang Berpengaruh Kepada Kinerja Waktu (Berbasis PMBOK Guide 2008) Studi Kasus PT. X dan PT. Y.” [In Indonesian.] Master’s thesis, Engineering Faculty, Universitas Indonesia.
ANSI/ASSP/ISO/IEC (American National Standards/American Society of Safety Professionals/International Organization for Standardization/International Electrotechnical Commission). 2019. Risk management—Risk assessment techniques. Park Ridge, IL: ASSP.
Beckers, F., N. Chiara, A. Flesch, J. Maly, E. Silva, and U. Stegemann. 2013. “A risk-management approach to a successful infrastructure project Initiation, financing, and execution.” Accessed August 25, 2022. https://www.mckinsey.com/business-functions/operations/our-insights/a-risk-management-approach-to-a-successful-infrastructure-project.
Boateng, P., Z. Chen, and S. O. Ogunlana. 2017. Megaproject risk analysis and simulation: A dynamic systems approach. Bingley, UK: Emerald.
BSI (British Standards Institution). 2019. Project management—Principles and guidance for the management of projects. London: BS.
Derakhshanalavijeh, R., and J. M. Cardoso Teixeira. 2013. “Cost overrun in construction projects in developing countries, gas-oil industry of Iran as a case study.” J. Civ. Eng. Manage. 23 (1): 125–136. https://doi.org/10.3846/13923730.2014.992467.
Dey, P. K. 2002. “Project risk management: A combined analytic hierarchy process and decision tree approach.” Cost Eng. 44 (3): 13–27.
Dobson, M. S., and D. S. Dobson. 2012. Project risk and cost analysis. New York: American Management Association.
ESDM (Energi dan Sumber Daya Mineral). 2009. Peraturan Menteri ESDM No. 19 Tahun 2009 tentang Kegiatan usaha Gas Bumi Melalui Pipa. Jakarta, IN: ESDM.
Gunarso, G., and K. K. D. Sungkono. 2018. “Risk analysis of engineering design stage at EPC project construction (case study: Asam-Asam CPP And OLC Project, PT. Krakatau Engineering).” [In Indonesian.] Jurnal Teknik Sipil dan Arsitektur 22 (26): 1–11.
Hamid, M., I. Sufi, W. Konadi, Y. Akmal, and J. Iddris. 2019. Analisis Jalur Dan Aplikasi SPSS Versi 25. [In Indonesian.] Bireuen, IN: Edisi Pertama.
Hatmoko, J. U. D., and R. R. Khasani. 2019. “Mapping delay risks of EPC projects: A case study of a platform and subsea pipeline of an oil and gas project.” IOP Conf. Ser.: Mater. Sci. Eng. 598 (1): 012095. https://doi.org/10.1088/1757-899X/598/1/012095.
Hickson, R. J., and T. L. Owen. 2022. Project management for mining: Handbook for delivering project success. Englewood, CO: Society for Mining, Metallurgy & Exploration.
Hollmann, J. K. 2014. “Improve your contingency estimates for more realistic project budgets.” Accessed July 18, 2021. https://www.chemengonline.com/improve-your-contingency-estimates-for-more-realistic-project-budgets/?printmode=1.
Kominfomas, J. U. 2021. “Pemerintah Kota Administrasi Jakarta Utara.” [In Indonesian.] Accessed June 10, 2021. https://utara.jakarta.go.id/Walikota-Geram-Proyek-Pemasangan-Pipa-Gas-Belum-Rampung.
Latupeirissa, J. E., P. F. Marzuki, and R. D. Wirahadikusumah. 2007. “Perceptions of contractors’ contingency costs in Indonesia: A survey.” [In Indonesian.] Jurnal Teknik Sipil Universitas Atma Jaya Yogyakarta 7 (3): 287–299.
Lyon, B. K., and G. Popov. 2022. “On the concept of risk, uncertainty & black swans.” Profession. Saf. 67 (3): 18–23.
Malhotra, M. 2020. Marketing research: An applied orientation. Harlow, UK: Pearson.
Messah, Y. A., T. Widodo, and M. L. Adoe. 2013. “Study of causes of delay in implementation of building construction projects in Kupang City.” [In Indonesian.] Jurnal Teknik Sipil 2 (2): 157–168.
Meyers, L. S., G. C. Gamst, and A. J. Guarino. 2013. Performing data analysis using IBM SPSS. New York: Wiley.
Ministry of Energy and Mineral Resources Republic of Indonesia. 2021. Handbook of energy & economic statistic of Indonesia. Jakarta, IN: Ministry of Energy and Mineral Resources Republic of Indonesia.
Mubin, S., and A. Mannan. 2013. “Innovative approach to risk analysis and management of oil and gas sector EPC contracts from a contractor’s perspective.” J. Bus. Econ. 5 (2): 149–170.
Orangi, A., E. Palaneeswaran, and J. Wilson. 2011. “Exploring delays in Victoria-based Australian pipeline projects.” Procedia Eng. 14 (2011): 874–881. https://doi.org/10.1016/j.proeng.2011.07.111.
Ostadi, B., and S. A. Harofteh. 2020. “A novel risk assessment approach using Monte Carlo simulation based on co-occurance of risk factors: A case study of a petrochemical plant construction.” Sci. Iran. 29 (3): 1755–1765. https://doi.org/10.24200/sci.2020.55513.4258.
Pambagio, A. 2019. “The future of natural gas.” [In Indonesian.] Accessed Auguest 20, 2020. https://news.detik.com/kolom/d-4673035/masa-depan-gas-bumi.
Park, M.-J., E.-B. Lee, S.-Y. Lee, and J.-H. Kim. 2021. “A digitalized design risk analysis tool with machine-learning algorithm for EPC contractor’s technical specifications assessment on bidding.” Energies 14 (18): 1–32. https://doi.org/10.3390/en14185901.
Peginusa, S. S., D. Willar, and F. J. Manoppo. 2020. “Risk-based contingency cost estimation model for river normalization projects in urban areas.” [In Indonesian.] Jurnal Ilmiah Media Eng. 10 (1): 35–46.
PMI (Project Mangement Institute). 2017. A guide to the project management body of knowledge (PMBOK). 6th ed. Newton Square, PA: PMI.
Pratasik, F., G. Y. Malingkas, T. Arsjad, and H. Tarore. 2013. “Analyzing the sensitivity of project duration delays using the CPM method (case study: Puri Kelapa Gading Housing).” [In Indonesian.] Jurnal Sipil Statik 1 (9): 603–607.
Simanjuntak, M. R. A., and B. Christin. 2020. “Analysis of risk factors contingency cost EPC pipeline project.” [In Indonesian.] Prosiding SNITT Poltekba 4 (2020): 429–437.
Sospeter, N. G., and N. Chileshe. 2021. “Risk handling responsibilities in Tanzanian project-based organisations.” Sustainability 13 (14): 8078. https://doi.org/10.3390/su13148078.
Srivastava, P. 2011. “Wetting risk premiums in EPC bid value using Monte Carlo simulation.” Org. Tech. Manage. Constr. 3 (1): 227–242.
Statista. 2022. “Leading exporting countries of liquefied natural gas worldwide in 2021(in billion cubic meters).” Accessed August 8, 2022. https://www.statista.com/statistics/274528/major-exporting-countries-of-lng/#:∼:text=The%20world’s%20largest%20exporter%20of,that%20time%2C%20Qatar%20ranked%20second.
Sugiyono. 2017. Research methods: Quantitative, qualitative, and R&D. [In Indonesian.] Bandung, IN: Alfabeta.
Suprapto, H. 2018. “Tuntut Kompensasi Pemasangan Pipa Gas, Warga Mura Datangi Gedung Dewan.” Accessed June 14, 2021. https://sumselupdate.com/tuntut-kompensasi-pemasangan-pipa-gas-warga-mura-datangi-gedung-dewan/.
Valipour, A., H. Sarvari, Y. Nordin, M. N. Norhazilan, and S. M. Khoshnava. 2014. “Analytic network process approach to risk allocation of EPC projects case study: Gas refinery EPC projects in Iran.” Appl. Mech. Mater. 567 (Jun): 654–659. https://doi.org/10.4028/www.scientific.net/AMM.567.654.
Wibowo, K. S. 2016. “After Din Minimi, Members of the King of the Jungle Group Surrender.” [In Indonesian.] Accessed April 17, 2021. https://nasional.tempo.co/read/737113/setelah-din-minimi-anggota-kelompok-raja-rimba-menyerah.
Wicaksono, P. E. 2020. “Indonesia’s oil reserves only sufficient for 9 more years.” [In Indonesian.] Accessed January 14, 2020. https://www.liputan6.com/bisnis/read/4155492/cadangan-minyak-indonesia-hanya-cukup-untuk-9-tahun-lagi.
Widajatun, V. W. 2015. “Application of risk management in a literature study.” [In Indonesian.] Jurnal Bisnis dan Manajemen 14 (2): 65.
Xia, M., L. Zhao, and L. Zhao. 2022. “A comprehensive risk-assessment method for prefabricated buildings using EPC: A case study from China.” Sustainability 14 (3): 1–28. https://doi.org/10.3390/su14031910.
Yuhanes, D. 2011. “Optimization of natural gas transportation through pipeline from Natuna to Singapore.” [In Indonesian.] Master’s thesis, Dept. of Chemistry, Faculty of Engineering, Universitas Indonesia.
Zhu, F., H. Hu, and F. Xu. 2022. “Risk assessment model for international construction projects considering sk interdependence using the DEMATEL method.” PLoS One 17 (5): e0265972. https://doi.org/10.1371/journal.pone.0265972.

Information & Authors

Information

Published In

Go to Journal of Pipeline Systems Engineering and Practice
Journal of Pipeline Systems Engineering and Practice
Volume 14Issue 3August 2023

History

Received: May 12, 2022
Accepted: Mar 13, 2023
Published online: May 31, 2023
Published in print: Aug 1, 2023
Discussion open until: Oct 31, 2023

Permissions

Request permissions for this article.

Authors

Affiliations

Lukas Beladi Sihombing, Ph.D., M.ASCE https://orcid.org/0000-0003-2495-1591 [email protected]
Assistant Professor, Dept. of Civil Engineering, Universitas Pembangunan Jaya, Banten 15413, Indonesia (corresponding author). ORCID: https://orcid.org/0000-0003-2495-1591. Email: [email protected]
Bernadette Christin [email protected]
Graduate Student, Master of Civil Engineering Program, Universitas Pelita Harapan, Banten 15811, Indonesia. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share