Decision Support Framework for the Choice of Delay Analysis Techniques Used in Extension of Time Claims
Publication: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 16, Issue 4
Abstract
One of the inevitable challenges that face the construction industry is the delay of project completion. The current state of the industry makes the need for delay analysis apparent, however the process of choosing the most reliable delay analysis technique can get very complex in some situations. This research aims to develop a framework to identify and analyze the most important factors to consider when choosing a delay analysis technique. The most reliable technique is decided based on a weighted multicriteria decision matrix. The proposed numerical weight for each factor and the pointing system it is derived from are supported by a conducted survey, previous research, and recommended practices. Different scenarios of each factor are listed, each scenario recommends the use of a certain delay analysis technique if it occurs in the project. To present the framework, a user-interface is developed that takes every factor’s scenario as an input to yield the most recommended delay analysis technique. It is concluded that the most important factor to consider is the presence of reliable contemporaneous records. Furthermore, the technique that is most recommended in many cases is time impact analysis while collapsed as-built is recommended in very specific situations. The developed framework serves as a tool for professionals in the construction management industry to facilitate the choice of the delay analysis technique.
Get full access to this article
View all available purchase options and get full access to this article.
Data Availability Statement
All data, models, or code that support the findings of this study are available from the corresponding author upon reasonable request.
References
Works Cited
AACE International. 2006. 52R-06: Time impact analysis–As applied in construction. Fairmont, WV: AACE International.
AACE International. 2011. “29R-03: Forensic schedule analysis.” Accessed April 18, 2022. https://www.yumpu.com/en/document/read/44677564/29r-03-forensic-schedule-analysis-aace-international.
Abouorban, H., O. Hosny, K. Nassar, and R. Eltahan. 2018. “Delay analysis techniques in construction project.” In Proc., Building Tomorrow’s Society. Berlin: ResearchGate.
Alkass, S., M. Mazerolle, and F. Harris. 2010. “Construction delay analysis techniques.” Construct. Manage. Econ. 14 (5): 375–394. https://doi.org/10.1080/014461996373250.
Arditi, D., and T. Pattanakitchamroon. 2006. “Selecting a delay analysis method in resolving construction claims.” Int. J. Project Manage. 24 (2): 145–155. https://doi.org/10.1016/j.ijproman.2005.08.005.
Bektas, S., M. T. Birgonul, and I. Dikmen. 2020. “Integrated probabilistic delay analysis method to estimate expected outcome of construction delay disputes.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 13 (1): 04520037. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000439.
Bilgin, G., I. Dikmen, and M. T. Birgonul. 2018. “An ontology-based approach for delay analysis in construction.” KSCE J. Civ. Eng. 22 (2): 384–398. https://doi.org/10.1007/s12205-017-0651-5.
Braimah, N. 2013a. “Construction delay analysis techniques—A review of application issues and improvement needs.” Buildings 3 (3): 506–531. https://doi.org/10.3390/buildings3030506.
Braimah, N. 2013b. “Understanding construction delay analysis and the role of preconstruction programming.” J. Manage. Eng. 30 (5): 04014023. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000216.
Braimah, N., and I. Ndekugri. 2008. “Factors influencing the selection of delay analysis methodologies.” Int. J. Project Manage. 26 (8): 789–799. https://doi.org/10.1016/j.ijproman.2007.09.001.
Cevikbas, M., and Z. Işık. 2023. “Detecting the most appropriate delay analysis methods for mega airport projects.” Eng. Constr. Archit. Manage. 30 (6): 2463–2480. https://doi.org/10.1108/ECAM-12-2021-1107.
Elhusseiny, H. O., I. Nosair, and A. S. Ezeldin. 2021. “Systematic processing framework for analyzing the factors of construction projects’ delays in Egypt.” Ain Shams Eng. J. 12 (2): 1501–1511. https://doi.org/10.1016/j.asej.2020.10.016.
Hegazy, T., and W. Menesi. 2008. “Delay analysis under multiple baseline updates.” J. Constr. Eng. Manage. 134 (8): 575–582. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:8(575).
Hillig, J. B., D. Dan-Asabe, S. Donyavi, O. Dursun, and A. Thampuratty. 2010. “FIDIC’s Red Book 1999 edition: A study review.” Proc. Inst. Civ. Eng. Manage. Procure. Law 163 (3): 129–133. https://doi.org/10.1680/mpal.2010.163.3.129.
Hinze, J. 2008. Vol. 3 of Construction planning and scheduling. Upper Saddle River, NJ: Pearson Prentice Hall.
Meena, A. V., and A. K. Suresh Babu. 2015. “Study on time delay analysis for construction project delay analysis.” Accessed April 20, 2022. www.ijert.org.
Muhamad, N. H., M. F. Mohammad, A. C. Ahmad, and I. H. Ibrahim. 2016. “Delay analysis methodologies (DAMs) in delivering quality projects: Contractors and consultants’ perceptions.” Procedia-Social Behav. Sci. 222 (Jun): 121–131. https://doi.org/10.1016/j.sbspro.2016.05.200.
Nukman, Y., H. Ariff, and M. S. Salit. 2009. “Use of analytical hierarchy process (AHP) for selecting the best design concept.” Jurnal Teknologi 49 (A): 1–18. https://doi.org/10.11113/jt.v49.188.
Perera, N. A., M. Sutrisna, and T. W. Yiu. 2016. “Decision-making model for selecting the optimum method of delay analysis in construction projects.” J. Manage. Eng. 32 (5): 04016009. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000441.
Radujkovic, M., M. Vukomanović, and I. Burcar Dunovic. 2010. “Application of key performance indicators in South-Eastern European construction.” J. Civ. Eng. Manage. 16 (Mar): 521–530. https://doi.org/10.3846/jcem.2010.58.
RICS (Royal Institution of Chartered Surveyors). 2015. “Extensions of time RICS guidance note.” Accessed August 2, 2022. www.rics.org.
Sanni-Anibire, M. O., R. Mohamad Zin, and S. O. Olatunji. 2022. “Causes of delay in the global construction industry: A meta analytical review.” Int. J. Construct. Manage. 22 (8): 1395–1407. https://doi.org/10.1080/15623599.2020.1716132.
SCL (Society of Construction Law). 2017. “Society of construction law delay and disruption protocol.” Accessed April 19, 2022. www.scl.org.ukwww.scl.org.uk.
Shahsavand, P., A. Marefat, and M. Parchamijalal. 2018. “Causes of delays in construction industry and comparative delay analysis techniques with SCL protocol.” Eng. Constr. Archit. Manage. 25 (4): 497. https://doi.org/10.1108/ECAM-10-2016-0220.
Trauner, T. 2009. “Construction delays: Understanding them clearly, analyzing them correctly–Theodore J. Trauner–Google books.” Accessed November 11, 2022. https://books.google.com.eg/books/about/Construction_Delays.html?id=oAXtvyysljkC&printsec=frontcover&source=kp_read_button&hl=en&redir_esc=y#v=onepage&q&f=false.
Viles, E., N. C. Rudeli, and A. Santilli. 2020. “Causes of delay in construction projects: A quantitative analysis.” Eng. Constr. Archit. Manage. 27 (4): 917–935. https://doi.org/10.1108/ECAM-01-2019-0024.
Information & Authors
Information
Published In
Copyright
© 2024 American Society of Civil Engineers.
History
Received: Aug 26, 2023
Accepted: Apr 1, 2024
Published online: Jul 9, 2024
Published in print: Nov 1, 2024
Discussion open until: Dec 9, 2024
ASCE Technical Topics:
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.