Analyzing Underlying Factors of Rework in Generating Contractual Claims in Construction Projects

Publication: Journal of Construction Engineering and Management
Volume 149, Issue 6

Abstract

Claim management plays an essential role in the success of construction contracts. The enhancement of the contractual claim process in construction projects improves the relationship between parties and impacts conflicts and disputes. Previous studies related to contractual claims focused primarily on general causes with relatively little attention paid to reasons associated with reworking. Rework in construction contracts generates cost overruns and delays, resulting in claims, conflicts, and disputes. Given the causal relations of rework, contractual claims, and disputes in construction projects, the necessity to implement rework management has become more critical. Although construction reworks lead to claims and disputes, a quantitative approach has not been undertaken to analyze the relationship between rework causes and contractual claims. This study aims to identify the key causes of rework that affect construction contracts and categorize them as rework factors in generating contractual claims by apprising the correlative rework causes and contractual claims. A quantitative approach is considered an appropriate method for data collection. Based on a review of the literature, a questionnaire including a comprehensive list of rework causes was developed, and the collected data were then analyzed using the exploratory factor analysis method. The results provided evidence of categorizing the causes of rework under four underlying factors: process, management and planning, material and equipment, and human resources. This study bridges the knowledge gap of dimensionality between rework and contractual claims, which can create measures to address rework causes in generating contractual claims. The paper suggests that effective rework management could reduce contractual claims through attention to the causes of rework at the early stages of contracting.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All data, models, and code generated or used during the study appear in the published article.

References

Abdul Nabi, M., I. H. El-adaway, S. Fayek, C. Howell, and J. Gambatese. 2020. “Contractual guidelines for construction safety–related issues under design–build standard forms of contract.” J. Constr. Eng. Manage. 146 (7): 04020074. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001855.
Aiyetan, A. O. 2013. “Causes of rework on building construction projects in Nigeria.” Int. Interdiscip. J. 12 (3): 1–15.
Ajayi, O., and O. Oyeyipo. 2015. “Effect of rework on project performance in building project in Nigeria.” Int. J. Eng. Res. Technol. 4 (2): 294–300. https://doi.org/10.17577/IJERTV4IS020266.
Ajayi, O. M. 2017. “Occurrence of rework on components of building project in Lagos state, Nigeria.” Int. J. Sustainable Constr. Eng. Technol. 8 (1): 84–93.
Ajayi, S. O., L. O. Oyedele, M. Bilal, O. O. Akinade, H. A. Alaka, and H. A. Owolabi. 2017. “Critical management practices influencing on-site waste minimization in construction projects.” Waste Manage. 59 (Jan): 330–339. https://doi.org/10.1016/j.wasman.2016.10.040.
Arcadis. 2022. “Global construction disputes report.” In Successfully navigating through turbulent times. Amsterdam Netherlands: ARCADIS.
Asadi, R., J. O. B. Rotimi, and S. Wilkinson. 2022. “Investigating the relationship between rework and contractual claims: The salience of contract conditions.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 14 (1): 04521046. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000519.
Asadi, R., S. Wilkinson, and J. O. B. Rotimi. 2021a. “The common causes of rework in construction contracts: A diagnostic approach.” J. Eng. Des. Technol. https://doi.org/10.1108/JEDT-04-2021-0215.
Asadi, R., S. Wilkinson, and J. O. B. Rotimi. 2021b. “Towards contracting strategy usage for rework in construction projects: A comprehensive review.” Construct. Manage. Econ. 39 (12): 953–971. https://doi.org/10.1080/01446193.2021.2004609.
Assaad, R., A. Elsayegh, G. Ali, M. Abdul-Nabi, and I. H. El-adaway. 2020. “Back-to-back relationship under standard subcontract agreements: Comparative study.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (3): 04520020. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000406.
Aulia, T. B., J. Mubarak, and R. Irfan. 2012. “Factors causing rework at building construction in the department of highways and settlements of Aceh Province.” In Proc., 2nd Annual Int. Conf. Syiah Kuala University, the 8th IMT-GT Uninet Biosciences Conf. Banda Aceh, Indonesia: Syiah Kuala Univ.
Bagozzi, R. P., and Y. Yi. 2012. “Specification, evaluation, and interpretation of structural equation models.” J. Acad. Mark. Sci. 40 (1): 8–34. https://doi.org/10.1007/s11747-011-0278-x.
Banwo, O., K. Parker, and A. Sagoo. 2015. “Principles of contract claims management—A review of the Nigerian construction industry.” In Proc., 2015 Int. Conf. on Industrial Engineering and Operations Management, 1–9. New York: IEEE. https://doi.org/10.1109/IEOM.2015.7093726.
Besaiso, H., P. Fenn, M. Emsley, and D. Wright. 2018. “A comparison of the suitability of FIDIC and NEC conditions of contract in Palestine.” Eng. Constr. Archit. Manage. 25 (2): 241–256. https://doi.org/10.1108/ECAM-10-2016-0235.
Broome, J. C., and R. W. Hayes. 1997. “A comparison of the clarity of traditional construction contracts and of the new engineering contracts.” Int. J. Project Manage. 15 (4): 255–261. https://doi.org/10.1016/S0263-7863(96)00078-6.
Buniya, M., I. Othman, R. Y. Sunindijo, E. M. Kineber, and H. Ahmad. 2021. “Barriers to safety program implementation in the construction industry.” Ain Shams Eng. J. 12 (1): 65–72. https://doi.org/10.1016/j.asej.2020.08.002.
Dosumu, O. S. 2018. “Perceived effects of prevalent errors in contract documents on construction projects.” Constr. Econ. Build. 18 (1): 1–26. https://doi.org/10.5130/AJCEB.v18i1.5663.
El-adaway, I. H., S. Fawzy, T. Allard, and A. Runnels. 2016. “Change order provisions under national and international standard forms of contract.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 8 (3): 03716001. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000187.
El-adaway, I. H., S. Fawzy, H. Burrell, and N. Akroush. 2017. “Studying payment provisions under national and international standard forms of contracts.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 9 (2): 04516011. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000200.
Enshassi, A., R. Choudhry, and S. El-Ghandour. 2009. “Contractors’ perception towards causes of claims in construction projects.” Int. J. Construct. Manage. 9 (1): 79–92. https://doi.org/10.1080/15623599.2009.10773123.
Enshassi, A., M. Sundermeier, and M. Abo Zeiter. 2017. “Factors contributing to rework and their impact on construction projects performance.” Int. J. Sustainable Constr. Eng. Technol. 8 (1): 12–33.
Eze, E. C., and J. E. Idiake. 2018. “Impact of rework on building project and organisation performance; A view of construction professionals in Nigeria.” Int. J. Sustainable Constr. Eng. Technol. 9 (1): 29–43. https://doi.org/10.30880/ijscet.2018.09.01.003.
Forcada, N., G. M. RusinolMacarulla, M. Macarulla, and P. E. D. Love. 2014. “Rework in highway projects.” J. Civ. Eng. Manage. 20 (4): 445–465. https://doi.org/10.3846/13923730.2014.893917.
Gad, G. M., J. S. Shane, K. C. Strong, and J. Choi. 2016. “Rethinking trust in construction contract formation: Dispute resolution method selection.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 8 (3): 04516003. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000191.
Gunduz, M., and H. A. Elsherbeny. 2020. “Operational framework for managing construction-contract administration practitioners’ perspective through modified Delphi method.” J. Constr. Eng. Manage. 146 (3): 04019110. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001768.
Harper, C. M., K. R. Molenaar, and J. P. Cannon. 2016. “Measuring constructs of relational contracting in construction projects: The owner’s perspective.” J. Constr. Eng. Manage. 142 (10): 04016053. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001169.
Hassan, F. U., and T. Le. 2020. “Automated requirements identification from construction contract documents using natural language processing.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (2): 04520009. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000379.
Hwang, B. G., S. R. Thomas, C. T. Haas, and C. H. Caldas. 2009. “Measuring the impact of rework on construction cost performance.” J. Constr. Eng. Manage. 135 (3): 187–198. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:3(187).
Hwang, B. G., and S. Yang. 2014. “Rework and schedule performance; A profile of incidence, impact, causes and solutions.” Eng. Constr. Archit. Manage. 21 (2): 190–205. https://doi.org/10.1108/ECAM-10-2012-0101.
Hwang, B. G., X. Zhao, and K. J. Goh. 2014. “Investigating the client-related rework in building projects: The case of Singapore.” Int. J. Project Manage. 32 (4): 698–708. https://doi.org/10.1016/j.ijproman.2013.08.009.
Hwang, B. G., X. Zhao, and K. W. Yang. 2019. “Effect of BIM on rework in construction projects in Singapore status Quo, magnitude, impact, and strategies.” J. Constr. Eng. Manage. 145 (2): 04018125. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001600.
Hyun, H., H. H. S. KimLee, H. S. Lee, M. Park, and J. H. Lee. 2020. “Integrated design process for modular construction projects to reduce rework.” Sustainability 12 (2): 530. https://doi.org/10.3390/su12020530.
Irumba, R., A. G. Kerali, and M. Wilhelmsson. 2010. “Modelling the dynamic of safety on construction projects: An undiscovered rework perspective.” In Proc., CIB Working Commission—Safety and Health in Construction, 227–240. Salford Quays, UK: The Lowry.
Jadidoleslami, S., E. Saghatforoush, and Z. Ravasan. 2018. “Constructability obstacles: An exploratory factor analysis approach.” Int. J. Construct. Manage. 21 (3): 312–325. https://doi.org/10.1080/15623599.2018.1534044.
Jalal, M. P., and H. Moharreri. 2020. “Model for preparing optimal contracts to prevent or reduce claims in projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (2): 04520004. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000363.
Jelodar, M. B., T. W. Yiu, and S. Wilkinson. 2016. “Dispute manifestation and relationship quality in practice.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 8 (1): C4515003. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000171.
Josephson, P. E., B. Larsson, and H. Li. 2002. “Illustrative benchmarking rework and rework costs in Swedish construction industry.” J. Manage. Eng. 18 (2): 76–83. https://doi.org/10.1061/(ASCE)0742-597X(2002)18:2(76).
Juhari, M. L., and K. Arifin. 2020. “Validating measurement structure of materials and equipment factors model in the MRT construction industry using confirmatory factor analysis.” Saf. Sci. 131 (Nov): 104905. https://doi.org/10.1016/j.ssci.2020.104905.
Kim, Y. J., and M. J. Skibniewski. 2020. “Cash and claim: Data-based inverse relationships between liquidity and claims in the construction industry.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (3): 04520021. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000402.
Kisi, K. P., N. Lee, R. Kayastha, and J. Kovel. 2020. “Alternative dispute resolution practices in international road construction contracts.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (2): 04520001. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000373.
Lee, J. H., Y. Ham, J. S. Yi, and J. W. Son. 2020a. “Effective risk positioning through automated identification of missing contract conditions from the contractor’s perspective based on FIDIC contract cases.” J. Manage. Eng. 36 (3): 05020003. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000757.
Lee, Z. P., A. R. Rahimi, and S. I. Doh. 2020b. “Critical success factors for implementing design-build: Analysing Malaysian public projects.” J. Eng. Des. Technol. 20 (5): 1041–1056. https://doi.org/10.1108/JEDT-08-2020-0321.
Lessing, B., D. Thurnell, and S. Durdyev. 2017. “Main factors causing delays in large construction projects: Evidence from New Zealand.” J. Manage. Econ. Ind. Organ. 1 (2): 63–82. https://doi.org/10.31039/jomeino.2017.1.2.5.
Liu, Q., G. Ye, Y. Feng, C. Wang, and Y. Peng. 2020. “Case based insights into rework costs of residential building projects in China.” Int. J. Construct. Manage. 20 (4): 347–355. https://doi.org/10.1080/15623599.2018.1484856.
Love, P. E. D., and D. J. Edwards. 2004a. “Determinants of rework in building construction projects.” Eng. Constr. Archit. Manage. 11 (4): 259–274. https://doi.org/10.1108/09699980410547612.
Love, P. E. D., and D. J. Edwards. 2004b. “Forensic project management: The underlying causes of rework in construction projects.” Civ. Eng. Environ. Syst. 21 (3): 207–228. https://doi.org/10.1080/10286600412331295955.
Love, P. E. D., D. J. Edwards, and Z. Irani. 2008. “Forensic project management: An exploratory examination of the causal behaviour of design-induced error.” IEEE Trans. Eng. Manage. 55 (2): 234–247. https://doi.org/10.1109/TEM.2008.919677.
Love, P. E. D., D. J. Edwards, Z. Irani, and N. Forcada. 2014. “The latent causes of rework in floating production storage and offloading projects.” J. Civ. Eng. Manage. 20 (3): 315–329. https://doi.org/10.3846/13923730.2013.802725.
Love, P. E. D., D. J. Edwards, and J. Smith. 2005a. “Contract documentation and the incidence of rework in projects.” Archit. Eng. Des. Manage. 1 (4): 247–259. https://doi.org/10.1080/17452007.2005.9684596.
Love, P. E. D., D. J. Edwards, and J. Smith. 2005b. “A forensic examination of the causal mechanisms of rework in a structural steel supply chain.” Managerial Auditing J. 20 (2): 187–197. https://doi.org/10.1108/02686900510574593.
Love, P. E. D., D. J. Edwards, H. Watson, and P. Davis. 2010. “Rework in civil infrastructure projects determination of cost predictors.” J. Constr. Eng. Manage. 136 (3): 275–282. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000136.
Love, P. E. D., Z. Irani, and D. J. Edwards. 2004. “A rework reduction model for construction projects.” IEEE Trans. Eng. Manage. 51 (4): 426–440. https://doi.org/10.1109/TEM.2004.835092.
Love, P. E. D., and J. Smith. 2003. “Benchmarking, bench-action, and bench-learning rework mitigation in projects.” J. Manage. Eng. 19 (4): 147–159. https://doi.org/10.1061/(ASCE)0742-597X(2003)19:4(147).
Love, P. E. D., and J. Smith. 2018. “Unpacking the ambiguity of rework in construction making sense of the literature.” Civ. Eng. Environ. Syst. 35 (1–4): 180–203. https://doi.org/10.1080/10286608.2019.1577396.
Love, P. E. D., J. Smith, F. Ackermann, and Z. Irani. 2019. “Making sense of rework and its unintended consequence in projects: The emergence of uncomfortable knowledge.” Int. J. Project Manage. 37 (3): 501–516. https://doi.org/10.1016/j.ijproman.2019.02.004.
Love, P. E. D., J. Smith, and H. Li. 1999. “The propagation of rework benchmark metrics for construction.” Int. J. Qual. Reliab. Manage. 16 (7): 638–658. https://doi.org/10.1108/02656719910249829.
Ma, D., X. Li, and C. Cheng. 2020. “The impact of the international construction standard application capability on contractor’s competitiveness: Chinese Contractors experience.” J. Civ. Eng. Manage. 26 (8): 757–774. https://doi.org/10.3846/jcem.2020.13749.
Ma, G., S. Jiang, T. Zhu, and J. Jia. 2019. “A novel method of developing construction projects schedule under rework scenarios.” Sustainability 11 (20): 5710. https://doi.org/10.3390/su11205710.
Mahamid, I. 2016. “Analysis of rework in residential building projects in Palestine.” Jordan J. Civ. Eng. 10 (2): 197–208. https://doi.org/10.14525/JJCE.10.1.3536.
Mahamid, I. 2017. “Effect of change orders on rework in highway projects in Palestine.” J. Financ. Manage. Property Constr. 22 (1): 62–76. https://doi.org/10.1108/JFMPC-03-2016-0015.
Mahamid, I. 2022. “Impact of rework on material waste in building construction projects.” Int. J. Construct. Manage. 22 (8): 1500–1507. https://doi.org/10.1080/15623599.2020.1728607.
Mazzurco, A., B. K. Jesiek, and A. Godwin. 2020. “Development of global engineering competency scale: Exploratory and confirmatory factor analysis.” J. Civ. Eng. Educ. 46 (2): 04019003. https://doi.org/10.1061/(ASCE)EI.2643-9115.0000006.
Mendis, D., K. N. Hewage, and J. Wrzesniewski. 2013a. “Contractual obligations analysis for construction waste management in Canada.” J. Civ. Eng. Manage. 21 (7): 866–880. https://doi.org/10.3846/13923730.2014.893907.
Mendis, D., K. N. Hewage, and J. Wrzesniewski. 2013b. “Reduction of construction wastes by improving construction contract management: A multinational evaluation.” Waste Manage. Res. 31 (10): 1062–1069. https://doi.org/10.1177/0734242X13495724.
Mohamad, M. I., and Z. Madon. 2006. “Understanding contract documentation.” In Proc., 6th Asia-Pacific Structural Engineering and Construction Conf., C12–C18. Berlin: Springer.
Moza, A., and V. K. Paul. 2018. “Analysis of claims in public works construction contracts in India.” J. Constr. Dev. Countries 23 (2): 7–26. https://doi.org/10.21315/jcdc2018.23.2.2.
Oke, A. E., A. F. Kineber, I. Albukhari, I. Othman, and C. Kingsley. 2021. “Assessment of cloud computing success factors for sustainable construction industry: The case of Nigeria.” Buildings 11 (2): 36. https://doi.org/10.3390/buildings11020036.
Olanipekun, A. O., B. Xia, C. Hon, and Y. Hu. 2017. “Project owners’ motivation for delivering green building projects.” J. Constr. Eng. Manage. 143 (9): 04017068. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001363.
Oyewobi, L. O., O. A. Falemu, and O. T. Ibironke. 2016. “The impact of rework and organisational culture on project delivery.” J. Eng. Des. Technol. 14 (2): 214–237. https://doi.org/10.1108/JEDT-05-2013-0038.
Oyewobi, L. O., and D. R. Ogunsemi. 2010. “Factors influencing rework occurrence in construction: A study of selected building projects in Nigeria.” J. Build. Perform. 1 (1): 1–20.
Palaneeswaran, E., P. E. D. Love, M. Kumaraswamy, and T. Ng. 2008. “Mapping rework causes and effects using artificial neural networks.” Build. Res. Inf. 36 (5): 450–465. https://doi.org/10.1080/09613210802128269.
Palaneeswaran, E., P. E. D. Love, M. M. Kumaraswamy, and T. S. T. Ng. 2014. “Causal ascription of rework in building and civil engineering projects: A multivariate exploration.” Eng. Constr. Archit. Manage. 21 (1): 111–126. https://doi.org/10.1108/ECAM-04-2010-0029.
Rajeh, M., J. E. Tookey, and J. O. B. Rotimi. 2015. “Estimating transaction costs in the New Zealand construction procurement—A structural equation modelling methodology.” Eng. Constr. Archit. Manage. 22 (2): 242–267. https://doi.org/10.1108/ECAM-10-2014-0130.
Ramachandra, T., and J. O. B. Rotimi. 2015. “Causes of payment problems in the New Zealand construction industry.” Constr. Econ. Build. 15 (1): 43–55. https://doi.org/10.5130/AJCEB.v15i1.4214.
Robinson, F. A., M. Dissanayake, and O. Campero. 2004. “Developing a standard methodology for measuring and classifying construction field rework.” Can. J. Civ. Eng. 31 (6): 1077–1089. https://doi.org/10.1139/l04-068.
Safapour, E., and S. Kermanshachi. 2019. “Identifying early indicators of manageable rework causes and selecting mitigating best practices for construction.” J. Manage. Eng. 35 (2): 04018060. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000669.
Safapour, E., S. Kermanshachi, and P. Taneja. 2019. “Investigation and analysis of the rework leading indicators in construction projects state-of-the-art review.” In Proc., 7th CSCE Int. Construction Specialty Conf. Laval, QC, Canada: Canadian Society for Civil Engineering.
Saseendran, A., B. F. Bigelow, Z. K. Rybkowski, and D. E. Jourdan. 2020. “Disputes in construction: Evaluation of contractual effects of ConsensusDOCS.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (2): 04520008. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000377.
Seo, W., and Y. Kang. 2020. “Performance indicators for the claim management of general contractors.” J. Manage. Eng. 36 (6): 04020070. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000835.
Sobieraja, J., and D. Metelsk. 2020. “Identification of the key investment project management factors in the housing construction sector in Poland.” Int. J. Constr. Project Manage. 23 (1): 1–12. https://doi.org/10.1080/15623599.2020.1844855.
Soewin, E., and T. Chinda. 2018. “Factors affecting construction performance: Exploratory factor analysis.” IOP Conf. Ser.: Earth Environ. Sci. 140 (1): 012102. https://doi.org/10.1088/1755-1315/140/1/012102.
Sorde, M. S., and P. H. Sawant. 2015. “Analysis of contract clauses affecting the cost performance of a construction project.” J. Civ. Eng. Technol. 2 (5): 437–440.
Taggart, M., L. Koskela, and J. Rooke. 2014. “The role of the supply chain in the elimination and reduction of construction rework and defects an action research approach.” Construct. Manage. Econ. 32 (7–8): 829–842. https://doi.org/10.1080/01446193.2014.904965.
Umar, A. A., N. A. Zawawi, and A. R. Abdul-Aziz. 2019. “Exploratory factor analysis of skills requirement for PPP contract governance.” Built Environ. Project Asset Manage. 9 (2): 277–290. https://doi.org/10.1108/BEPAM-01-2018-0011.
Wang, C., J. B. H. Yap, L. C. Wood, and H. Abdul-Rahman. 2019. “Knowledge modelling for contract disputes and change control.” Prod. Plann. Control. 30 (8): 650–664. https://doi.org/10.1080/09537287.2019.1572247.
Windapo, A., and A. Adediran. 2017. “The influence of procurement strategy on SME contractor development in the construction industry.” In Proc., Int. Research Conf. 2017. Salford, UK: Univ. of Salford.
Wright, J. N., and W. Fergusson. 2009. “Benefits of the NEC ECC form of contract: A New Zealand case study.” Int. J. Project Manage. 27 (3): 243–249. https://doi.org/10.1016/j.ijproman.2008.03.005.
Xia, B., B. Xiong, M. Skitmore, P. Wu, and F. Hu. 2015. “Investigating the impact of project definition clarity on project performance: Structural equation modeling study.” J. Manage. Eng. 32 (1): 04015022. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000386.
Xiong, B., M. Skitmore, B. Xia, M. A. Masrom, K. Ye, and A. Bridge. 2014. “Examining the influence of participant performance factors on contractor satisfaction: A structural equation model.” Int. J. Project Manage. 32 (3): 482–491. https://doi.org/10.1016/j.ijproman.2013.06.003.
Yap, J. B. H., H. Abdul-Rahman, C. Wang, and M. Skitmore. 2018. “Exploring the underlying factors inducing design changes during building production.” Prod. Plann. Control. 29 (7): 586–601. https://doi.org/10.1080/09537287.2018.1448127.
Yap, J. B. H., J. R. Chong, M. Skitmore, and W. P. Lee. 2020. “Rework causation that undermines safety performance during production in construction.” J. Constr. Eng. Manage. 146 (9): 04020106. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001902.
Yap, J. B. H., P. L. Low, and C. Wang. 2017. “Rework in Malaysian building construction impacts causes and potential solutions.” J. Eng. Des. Technol. 15 (5): 591–618. https://doi.org/10.1108/JEDT-01-2017-0002.
Ye, G., Z. Jin, B. Xia, and M. Skitmore. 2015. “Analysing causes for reworks in construction projects in China.” J. Manage. Eng. 31 (6): 04014097. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000347.
Zaneldin, E. K. 2020. “Investigating the types, causes and severity of claims in construction projects in the UAE.” Int. J. Construct. Manage. 20 (5): 385–401. https://doi.org/10.1080/15623599.2018.1484863.
Zhang, D., C. T. Haas, P. M. Goodrum, C. H. Caldas, and R. Granger. 2012. “Construction small-projects rework reduction for capital facilities.” J. Constr. Eng. Manage. 138 (12): 1377–1385. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000552.
Zhang, S. B., Y. F. Fu, Y. Gao, and X. D. Zheng. 2016. “Influence of trust and contract on dispute negotiation behavioral strategy in construction subcontracting.” J. Manage. Eng. 32 (4): 1–11. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000427.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 149Issue 6June 2023

History

Received: Dec 9, 2021
Accepted: Jan 30, 2023
Published online: Apr 7, 2023
Published in print: Jun 1, 2023
Discussion open until: Sep 7, 2023

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Ph.D. Student, School of Built Environment, Massey Univ., North Shore, Auckland 0629, New Zealand (corresponding author). ORCID: https://orcid.org/0000-0002-2073-3557. Email: [email protected]
James Olabode Bamidele Rotimi https://orcid.org/0000-0001-6744-4683
Professor, School of Built Environment, Massey Univ., North Shore, Auckland 0629, New Zealand. ORCID: https://orcid.org/0000-0001-6744-4683
Suzanne Wilkinson
Professor, School of Built Environment, Massey Univ., North Shore, Auckland 0629, New Zealand.

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share