Evolutionary Game Analysis for the Behaviors of Risk Allocation Participants in Public–Private Partnerships

Publication: ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
Volume 9, Issue 2

Abstract

A fair allocation of risk is essential for successful projects involving public–private partnerships (PPPs). The participants to the risk allocation determine whether to take risks and how much of the share of the risks to assume according to their preference for and ability to manage risk. Owing to the different preferences of the public sector and private sector in the context of risk allocation, the perspective of local governance demands that the participants of risk allocation express their cognitive demands and interests through negotiation and dialog to arrive at a consensus on the choice of the scheme to use for risk allocation. To examine how risk-taking behaviors evolve in PPPs, this study develops an evolutionary game model in which the private and public sectors initiate the negotiation. This model is used to analyze the evolutionary stability of each player’s strategy, discuss the influence of various factors on the choices of strategy of the two parties, and to examine the stability of the point of equilibrium of the game system for the participants of risk allocation. The results provide decision-making support in negotiating appropriate concessions in PPP projects to reduce the incidences of renegotiation and incentives for either party to seek to renegotiate.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All of the data, models, and code that support the findings of this study are available from the corresponding author upon reasonable request.

Acknowledgments

This work was supported by the National Social Science Foundation of China (Grant No. 19BJY226).

References

Bao, X., and S. Ye. 2018. “Research on the special role of development finance in improving the landing rate of PPP projects—Based on the three party bargaining model of mutual deterrence.” [In Chinese.] J. Cent. Univ. Finance Econ. 2: 13–22. https://doi.org/10.19681/j.cnki.jcufe.2018.02.002.html.
Baruah, P., and M. Kakati. 2020. “Developing some fuzzy modules for finding risk probabilities in Indian PPP projects.” Transp. Res. Procedia 48 (4): 3939–3968. https://doi.org/10.1016/j.trpro.2020.08.026.
Buzzetto, R. R., and M. Monteiro de Carvalho. 2022. “The Arm-wrestling between public and private partners: An investigation of critical success factors and risk allocation preference in PPP Projects.” Eng. Manage. J. https://doi.org/10.1080/10429247.2022.2131293.
Cebotari, A. 2008. Contingent liabilities: Issues and practice, 1–60. New York: Social Science Electronic Publishing. https://doi.org/10.5089/9781451871036.001.
Chen, S., Y. Liu, and C. Weng. 2019. “Dynamic risk-sharing game and reinsurance contract design.” Insur. Math. Econ. 86 (May): 216–231. https://doi.org/10.1016/j.insmatheco.2019.03.004.
Chou, J. S., C. P. Yeh, H. P. Tserng, and C. Lin. 2012. “Critical factors and risk allocation for PPP policy: Comparison between HSR and general infrastructure projects.” Transp. Policy 22 (1): 36–48. https://doi.org/10.1016/j.tranpol.2012.05.009.
Chung, D., and D. Hensher. 2015. “Risk management in public private partnerships.” Aust. Acc. Rev. 25 (1): 13–17. https://doi.org/10.1111/auar.12062.
Cressman, R. 1992. “The stability concept of evolutionary game theory.” In Vol. 94 of Lecture notes in biomathematics. Berlin: Springer. https://doi.org/10.1007/978-3-642-49981-4_1.
De Clerck, D., and E. Demeulemeester. 2016. “Creating a more competitive PPP procurement market: Game theoretical analysis.” J. Constr. Eng. Manage. 32 (6): 04016015. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000440.
Feng, J., Y. Tang, S. Xue, and K. Zhang. 2021. “Study on cooperative strategies of rural water environment governance PPP project between companies and farmers from the perspective of evolutionary game.” Environ. Dev. Sustainability 24 (1): 138–155. https://doi.org/10.1007/s10668-020-01148-4.
Gao, L., and Z. Y. Zhao. 2018. “System dynamics analysis of evolutionary game strategies between the government and investors based on new energy power construction public-private-partnership (PPP) project.” Sustainability 10 (7): 2533. https://doi.org/10.3390/su10072533.
Gao, L., and Z. Y. Zhao. 2020. “The evolutionary game of stakeholders’ coordination mechanism of new energy power construction PPP project: A China case.” Sustainability 12 (3): 1045. https://doi.org/10.3390/su12031045.
Gao, R., and J. Liu. 2019. “Selection of government supervision mode of PPP projects during the operation stage.” Construct. Manage. Econ. 37 (10): 584–603. https://doi.org/10.1080/01446193.2018.1564347.
Geddes, R. 2011. The road to renewal: Private investment in the U.S. transportation infrastructure. Washington, DC: AEI Press.
Grimsey, D., and M. K. Lewis. 2002. “Evaluating the risks of public private partnerships for infrastructure projects.” Int. J. Project Manage. 20 (2): 107–118. https://doi.org/10.1016/S0263-7863(00)00040-5.
Guo, B., and J. Li. 2018. “Research on the evolution of participants collaboration mechanism in PPP model based on computer simulation: Based on the old community renovation project.” J. Supercomput. 76 (Feb): 2417–2434. https://doi.org/10.1007/s11227-018-2631-z.
Gupta, P. K., and H. Verma. 2020. “Risk perception in PPP infrastructure project financing in India.” J. Financ. Manage. Prop. Constr. 25 (3): 347–369. https://doi.org/10.1108/JFMPC-07-2019-0060.
Ho, S. P. 2009. “Government policy on PPP financial issues: Bid compensation and financial renegotiation.” In Policy, finance & management for public-private partnerships. Hoboken, NJ: Wiley.
Ho, S. P., R. Levitt, C. W. Tsui, and Y. Hsu. 2015. “Opportunism-focused transaction cost analysis of public-private partnerships.” J. Manage. Eng. 31 (6): 04015007. https://doi.org/10.1061/(ASCE)0742-597X(2000)16:6(34).
Iqbal, R. M., and H. Purwanto. 2022. “Risk analysis of investment costs in PPP projects using Monte Carlo simulation.” Logic: Jurnal Rancang Bangun dan Teknologi 22 (1): 13–21. https://doi.org/10.31940/logic.v22i1.13-21.
Jang, W., G. Yu, W. Jung, D. Kim, and S. H. Han. 2018. “Financial conflict resolution for public-private partnership projects using a three-phase game framework.” J. Constr. Eng. Manage. 144 (3): 05017022. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001442.
Jia, C., R. Zhang, and D. Wang. 2021. “Evolutionary game analysis of BIM adoption among stakeholders in PPP projects.” Complexity 6: 1–14. https://doi.org/10.1155/2021/5553785.
Jokar, E., B. Aminnejad, and A. Lork. 2022. “A risk allocation model among the elements of freeway projects in public-private partnership (PPP) method using integrated fuzzy multi-criteria decision-making techniques.” Aust. J. Civ. Eng. 1–25. https://doi.org/10.1080/14488353.2022.2083288.
Kang, C. C., T. S. Lee, and S. C. Huang. 2013. “Royalty bargaining in public-private partnership projects: Insights from a theoretic three-stage game auction model.” Transp. Res. Part E 59 (11): 1–14. https://doi.org/10.1016/j.tre.2013.08.001.
Lam, K. C., D. Wang, P. T. K. Lee, and Y. T. Tsang. 2007. “Modelling risk allocation decision in construction contracts.” Int. J. Project Manage. 25 (5): 485–493. https://doi.org/10.1016/j.ijproman.2006.11.005.
Li, B., A. Akintoye, P. J. Edwards, and C. Hardcastle. 2005. “The allocation of risk in PPP/PFI construction projects in UK.” Int. J. Project Manage. 23 (1): 25–35. https://doi.org/10.1016/j.ijproman.2004.04.006.
Li, C., X. Li, and Y. Wang. 2016. “Evolutionary game analysis of the supervision behavior for public-private partnership projects with public participation.” Math. Probl. Eng. 1–8. https://doi.org/10.1155/2016/1760837.
Li, H., L. Lv, J. Zuo, L. Su, L. Wang, and C. Yuan. 2020. “Dynamic reputation incentive mechanism for urban water environment treatment PPP projects.” J. Constr. Eng. Manage. 146 (8): 04020088. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001879.
Li, H., F. Wang, L. Lv, Q. Xia, and L. Wang. 2021. “Evolutionary game analysis of the government supervision and private sector ecological technology innovation behavior for water environment treatment PPP projects on the basis of public participation.” Can. J. Civ. Eng. 49 (1): 41–51. https://doi.org/10.1139/cjce-2020-0640.
Li, L., Z. H. Liu, and K. C. Zhang. 2013. “Game model for PPP project’s risk allocation under the asymmetry condition of participant’s position.” [In Chinese.] Syst. Eng. Theory Pract. 33 (8): 1940–1948.
Liu, F., Y. Wang, H. Yan, H. Li, and Y. Zhang. 2017. “Negotiation transaction cost of PPP based on the cumulative prospect-evolutionary game model.” In Proc., Int. Conf. on Construction and Real Estate Management. Reston, VA: ASCE. https://doi.org/10.1061/9780784481059.038.
Luo, Z., Y. Sun, and Z. Zhu. 2021. “Research on risk sharing of construction waste recycling PPP project based on game theory.” In Proc., 24th Int. Symp. on Advancement of Construction Management and Real Estate, 481–495. Singapore: Springer. https://doi.org/10.1007/978-981-15-8892-1_34.
Lv, J., T. An, X. Tan, and Q. Zou. 2021a. “How to alleviate rent-seeking behavior in performance appraisal of government-paid PPP projects? Tripartite evolutionary game approach.” Discrete. Dyn. Nat. Soc. 1–15. https://doi.org/10.1155/2021/5266167.
Lv, J., M. Lin, and W. Zhou. 2021b. “Fluctuation in construction costs and its effect on contract renegotiation behavior in PPP wastewater treatment projects: An evolutionary game analysis.” J. Cleaner Prod. 314 (11): 128025. https://doi.org/10.1016/j.jclepro.2021.128025.
Lv, J., M. Lin, W. Zhou, and M. Xu. 2021c. “How PPP renegotiation behaviors evolve with traffic changes: Evolutionary game approach.” J. Constr. Eng. Manage. 147 (1): 04021032. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002024.
Lv, J., G. Ye, W. Liu, L. Shen, and H. Wang. 2015. “Alternative model for determining the optimal concession period in managing BOT transportation projects.” J. Manage. Eng. 31 (4): 04014066. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000291.
Medda, F. 2007. “A game theory approach for the allocation of risks in transport public private partnerships.” Int. J. Project Manage. 25 (3): 213–218. https://doi.org/10.1016/j.ijproman.2006.06.003.
Morais, P. R., J. A. Matos, N. Bessa Vilela, and Ž. J. Oplotnik. 2022. “Transparency and risk allocation in PPP: Addressing complex contracts’ mathematical formulas in the Portuguese Case.” Lex Localis–J. Local Self-Gov. 20 (2): 435–453. https://doi.org/10.4335/10.4335/20.2.435-453(2022).
Mouraviev, N., and N. K. Kakabadse. 2014. “Risk allocation in a public-private partnership: A case study of construction and operation of kindergartens in Kazakhstan.” J. Risk Res. 17 (5–6): 621–640. https://doi.org/10.1080/13669877.2013.815650.
Myerson, R. B. 1991. Game theory: Analysis of conflict. Cambridge, MA: Harvard University Press.
Narbaev, T., Ö. Hazır, and M. Agi. 2022. “A Review of the use of game theory in project management.” J. Manage. Eng. 38 (6): 03122002. https://doi.org/10.1061/(ASCE)ME.1943-5479.0001092.
Ng, A., and M. Loosemore. 2007. “Risk allocation in the private provision of public infrastructure.” Int. J. Project Manage. 25 (1): 66–76. https://doi.org/10.1016/j.ijproman.2006.06.005.
Perez, D., J. Gray, and M. Skitmore. 2017. “Perceptions of risk allocation methods and equitable risk distribution: A study of medium to large Southeast Queensland commercial construction projects.” Int. J. Constr. Manage. 17 (2): 132–141. https://doi.org/10.1080/15623599.2016.1233087.
Rasheed, N., W. M. Shahzad, M. M. Khalfan, and J. O. Rotimi. 2022. “Risk identification, assessment, and allocation in PPP projects: A systematic review.” Buildings 12 (8): 1109. https://doi.org/10.3390/buildings12081109.
Rees, C., and F. Hossain. 2012. Public sector reform in developing and transitional countries: Decentralisation and local governance. New York: Routledge.
Rosas, A. 2010. “Evolutionary game theory meets social science: Is there a unifying rule for human cooperation?” J. Theor. Biol. 264 (2): 450–456. https://doi.org/10.1016/j.jtbi.2010.02.015.
Roumboutsos, A., and K. P. Anagnostopoulos. 2008. “Public-private partnership projects in Greece: Risk ranking and preferred risk allocation.” Construct. Manage. Econ. 26 (7): 751–763. https://doi.org/10.1080/01446190802140086.
Sanda, Y. N., N. A. Anigbogu, L. Y. Nuhu, and O. S. Olumide. 2020. “A life-cycle framework for managing risks in public private partnership housing projects.” J. Eng. Project Prod. Manage. 10 (1): 27–34. https://doi.org/10.2478/jeppm-2020-0004.
Shang, L., and A. M. Abdel Aziz. 2020. “Stackelberg game theory-based optimization model for design of payment mechanism in performance-based PPPs.” J. Constr. Eng. Manage. 146 (Jun): 04020029. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001806.
Shapira, A., and M. Simcha. 2009. “AHP-based weighting of factors affecting safety on construction sites with tower cranes.” J. Constr. Eng. Manage. 135 (4): 307–318. https://doi.org/10.1061/(ASCE)0733-9364(2009)135:4(307).
Sharma, S. 2021. “Ranking, allocation and response of risk factors of hybrid annuity model for highway construction projects.” Int. J. Res. Appl. Sci. Eng. Technol. 9 (4): 623–629. https://doi.org/10.22214/IJRASET.2021.33541.
Shen, K., X. Li, X. Cao, and Z. Zhang. 2021. “Prefabricated housing subsidy analysis in China based on an evolutionary game model.” J. Civ. Eng. Manage. 27 (7): 553–570. https://doi.org/10.3846/jcem.2021.15610.
Shen, L. Y., A. Platten, and X. P. Deng. 2006. “Role of public private partnerships to manage risks in public sector projects in Hong Kong.” Int. J. Project Manage. 24 (7): 587–594. https://doi.org/10.1016/j.ijproman.2006.07.006.
Smith, J. R. M. 1973. “The logic of animal conflict.” Nature 246 (5427): 15–18. https://doi.org/10.1038/246015a0.
Song, D., J. Song, H. Yuan, and Y. Fan. 2020. “An evolutionary game analysis of user-pay public–private partnership projects.” Eng. Constr. Archit. Manage. 28 (7): 2042–2062. https://doi.org/10.1108/ECAM-06-2020-0460.
Sterman, J. 2000. Business dynamics. 1st ed. New York: McGraw-Hill.
Tang, L., Q. Shen, and E. W. L. Cheng. 2010. “A review of studies on public-private partnership projects in the construction industry.” Int. J. Project Manage. 28 (7): 683–694. https://doi.org/10.1016/j.ijproman.2009.11.009.
Vining, A. R., and D. L. Weimer. 2015. “The challenges of fractionalized property rights in public-private hybrid organizations: The good, the bad, and the ugly.” Regul. Gov. 10 (2): 161–178. https://doi.org/10.1111/rego.12086.
Wang, H., Y. Liu, W. Xiong, and J. Song. 2018. “The moderating role of governance environment on the relationship between risk allocation and private investment in PPP markets: Evidence from developing countries.” Int. J. Project Manage. 37 (1): 117–130. https://doi.org/10.1016/j.ijproman.2018.10.008.
Wang, T. 2018. Research on local government governance reform under the guidance of public demand preference. [In Chinese.] Nanning, China: Guangxi Univ.
Wang, Z., Y. Zhou, X. Jin, N. Zhao, and J. Sun. 2022. “Risk allocation and benefit distribution of PPP projects for construction waste recycling: A case study of China.” Eng. Constr. Archit. Manage. https://doi.org/10.1108/ecam-10-2021-0855.
Weibull, J. 1995. Evolutionary game theory. Princeton, NJ: Princeton University Press.
Xiang, P., Q. F. Zhang, Q. Jiang, and Z. Liu. 2022. “Operational risk allocation in urban rail transit public–private partnership projects.” Front. Environ. Sci. 10 (Aug): 1195. https://doi.org/10.3389/fenvs.2022.900322.
Yue, X., and Y. Lin. 2019. “Effectiveness of punishment and operating subsidy in supervision of China’s pension PPP projects: An evolutionary game and simulation analysis.” Math. Probl. Eng. https://doi.org/10.1155/2019/9641429.
Zhang, P., and N. Wang. 2020. “Measurement of spatial distribution of hidden debt risk of local governments in China under PPP perspective.” [In Chinese.] Contemp. Finance 12: 39–49.
Zhang, R., and Y. Zhang. 2017. “Risk sharing of PPP project based on the three-party mutual deterrence and bargaining model.” [In Chinese.] J. Wuhan Univ. Technol. 39 (1): 558–563. https://doi.org/10.3963/j.issn.2095-3852.2017.01.012.
Zhang, S., J. Li, Y. Li, and X. Zhang. 2021. “Revenue risk allocation mechanism in public-private partnership projects: Swing option approach.” J. Constr. Eng. Manage. 147 (1): 04020153. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001952.
Zhang, X. Q. 2005. “Critical success factors for public-private partnerships in infrastructure development.” J. Constr. Eng. Manage. 131 (3): 3–14. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:1(3).
Zhou, X., D. Liu, and C. Yin. 2021. “Research on public rental housing PPP project launching dilemmas with dynamic evolutionary game.” Adv. Civ. Eng. 1–15. https://doi.org/10.1155/2021/1805874.
Zhou, Y., and J. Liu. 2020. “Study on supervision strategy of PPP project considering the participation of higher-level government.” Chinese J. Manage. Sci. 1–16. https://doi.org/10.16381/j.cnki.issn1003-207x.2020.0801.
Zuo, W., Q. Wang, and P. Li. 2022. “Rent-seeking decisions of the main participants in construction projects based on evolutionary-game and system dynamics.” J. Civ. Eng. Manage. 28 (2): 106–119. https://doi.org/10.3846/jcem.2022.16159.

Information & Authors

Information

Published In

Go to ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
Volume 9Issue 2June 2023

History

Received: Sep 12, 2022
Accepted: Dec 6, 2022
Published online: Feb 8, 2023
Published in print: Jun 1, 2023
Discussion open until: Jul 8, 2023

Permissions

Request permissions for this article.

Authors

Affiliations

Associate Professor, School of Finance, Hebei Univ. of Economics and Business, Shijiazhuang, Hebei 050061, PR China. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share