Public–Private Partnership Contract Framework Development for Highway Projects: A Delphi Approach

Publication: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 15, Issue 1

Abstract

Construction projects can be delivered through various approaches; nevertheless, all practitioners and involved parties have a mutual goal, which is completing the project within the original scope, defined budget, and schedule. Reviewing the literature on public–private partnerships (PPPs) showed that many efforts have been made to cover different research areas, including policies, risks, roles and responsibilities, and finance. The existing literature lacks studies involving the comprehensive process of preparing and implementing PPP contracts associated with highway projects in the US. This research, therefore, fills this noticeable gap in the body of knowledge on the PPP delivery method. The main objective of this research was to develop a framework for PPP contracts focusing on highway projects. To meet this objective, the authors conducted a Delphi study with highway professionals to identify the major issues that they should carefully deal with during contract document preparation, contract procurement, and contract implementation phases to make PPP highway projects successful. The Delphi study consisted of two rounds, with 25 open-ended interview questions over three phases. The study found that highway agencies must fix the scope of a project before a PPP project starts. They should also choose a lump sum contract type and a design-build-finance-operate-maintenance PPP type with a 35 to 40-year concession period for highway projects. Contracts should consist of incentive and disincentive clauses along with availability payments as the mode of compensating concessioners for their work. Before initiating a PPP contract, agencies should make sure that their state legislation allows this type of contract. The study also found that during the contract procurement phase, owners should use the best-value selection method to choose a PPP contractor; the competition should be fair and transparent, and the owner must have expertise in order to successfully procure PPP contracts. The experts recommended setting performance standards for PPP concessioners, performing inspections using independent third parties, and handing over condition data to maintenance personnel at the end of construction. The primary contribution of this research to the body of knowledge was to highlight the fact that each country, with the help of professional expertise and key stakeholders, background, and/or lessons learned, needs to develop a framework that lists the main issues and processes to be considered in implementing PPP highway contracts. This study presents a framework that can work nationwide, something that is missing in previous research studies. This framework can guide professionals in the transportation industry toward effective contract document preparation, procurement, and implementation of PPP highway projects in addition to giving academicians better insights to understand PPP highway projects in the US.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All data, models, or codes that support the findings of this study are available from the corresponding authors upon reasonable request.

Acknowledgments

This research could not have been conducted without the help of state DOT personnel, particularly the Delphi study’s long phone interviews and surveys. The authors would like to thank the state DOTs involved in this study, especially the Texas, Florida, Colorado, and California DOTs, who contributed greatly by spending a considerable amount of time on interviews and further discussions.

References

Works Cited

Adler, M., and E. Ziglio. 1996. Gazing into the oracle: The Delphi method and its application to social policy and public health. London: Jessica Kingsley Publishers.
Airoldi, M., J. Chua, P. Gerbert, J. Justus, and R. Rilo. 2013. Meeting the infrastructure challenge with public-private partnerships: Bridging the gap. Boston: Boston Consulting Group.
Airport Cooperative Research Program. 2008. A guidebook for selecting airport capital project delivery methods. ACRP Report No. 21. Washington, DC: Transportation Research Board.
Aziz, N., Z. Zain, R. M. Z. R. Mafuzi, A. M. Mustapa, N. H. M. Najib, and N. F. N. Lah. 2016. “Relative importance index (RII) in ranking of procrastination factors among university students.” In Vol. 1761 of Proc., AIP Conf. Proc., 020022. Melville, NY: AIP Publishing LLC.
Boadi, R. 2020. “A best practice framework for Public-Private Partnerships (PPPs) in road projects: The case of Ghana.” Ph.D. dissertation, School of Science, Engineering and Environment, Univ. of Salford.
Castelblanco, G., and J. Guevara. 2020. “Risk Allocation in PPP Unsolicited and Solicited Proposals in Latin America: Pilot Study in Colombia.” In Proc., Construction Research Congress 2020: Project Management and Controls, Materials, and Contracts, 1321–1329. Reston, VA: ASCE.
CCPPP (Canadian Council for Public-Private Partnerships). 2004. About PPP. Toronto: CCPPP.
Cherkos, F. D., and K. N. Jha. 2021. “Drivers of road sector public-private partnership adoption in new and inexperienced markets.” J. Constr. Eng. Manage. 147 (3): 04020186. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002004.
Cicchetti, D. V. 1994. “Guidelines, criteria, and rules of thumb for evaluating normed and standardized assessment instruments in psychology.” Psychol. Assess. 6 (4): 284. https://doi.org/10.1037/1040-3590.6.4.284.
Currier, K. F., F. Chan, N. L. Berven, R. V. Habeck, and D. W. Taylor. 2001. “Functions and knowledge domains for disability management practice: A Delphi study.” Rehabil. Couns. Bull. 44 (3): 133–143. https://doi.org/10.1177/003435520104400303.
Demirel, H. Ç., W. Leendertse, L. Volker, and M. Hertogh. 2017. “Flexibility in PPP contracts–dealing with potential change in the pre-contract phase of a construction project.” Construct. Manage. Econ. 35 (4): 196–206. https://doi.org/10.1080/01446193.2016.1241414.
Dewulf, G., and M. J. Garvin. 2020. “Responsive governance in PPP projects to manage uncertainty.” Construct. Manage. Econ. 38 (4): 383–397. https://doi.org/10.1080/01446193.2019.1618478.
Ding, J., N. Wang, and L. Hu. 2018. “Framework for designing project delivery and contract strategy in Chinese construction industry based on value-added analysis.” J. Adv. Civ. Eng. 2018: 1–14. https://doi.org/10.1155/2018/5810357.
Dochia, S., and M. Parker. 2009. “Introduction to public private partnerships with availability payments.” Accessed May 28, 2022. https://www.financingtransportation.org/pdf/jpa_introduction_to_availability_payments_0709.pdf.
Fathi, M. 2020. “Public-private partnership contract framework development and project performance analysis compared to design-build in the us highway projects.” Accessed October 10, 2020. https://digitalscholarship.unlv.edu/thesesdissertations/3893/.
Fathi, M., and P. P. Shrestha. 2019. “Review of public-private partnerships and the current status of PPP highway projects in the United States.” In Proc., Int. Road Federation (IRF) Global R2T Conf., 271–281. Alexandria, VA: IRF.
FHWA (Federal Highway Administration). 2017. Center for innovative finance support: Public private partnerships (P3s). Washington, DC: FHWA.
FHWA (Federal Highway Administration). 2019. Center for innovative finance support: P3 projects. Washington, DC: DOT.
Fleiss, J. L. 1975. “Measuring agreement between two judges on the presence or absence of a trait.” Biometrics 31 (3): 651–659. https://doi.org/10.2307/2529549.
Gad, G. M., B. Davis, P. P. Shrestha, and M. Fathi. 2020. “Legal and contractual issues in lump-sum design-build implementation on large-scale airport projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (1): 05019011. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000364.
Gao, R. 2010. Evaluation of incentive/disincentive contracting methods for highway construction projects. M.S. thesis, Dept. of Building Construction Management, Purdue Univ.
Gharaibeh, H. M. 2014. “Cost control in mega projects using the Delphi method.” J. Manage. Eng. 30 (5): 04014024. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000218.
Graham, M., A. Milanowski, and J. Miller. 2012. Measuring and promoting inter-rater agreement of teacher and principal performance ratings. Washington, DC: Dept. of Education, Institute of Education Sciences.
Gündüz, M., Y. Nielsen, and M. Özdemir. 2013. “Quantification of delay factors using the relative importance index method for construction projects in Turkey.” J. Manage. Eng. 29 (2): 133–139. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000129.
Gunhan, S., and D. Arditi. 2005. “Factors affecting international construction.” J. Constr. Eng. Manage. 131 (3): 273–282. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:3(273).
Hallgren, K. A. 2012. “Computing inter-rater reliability for observational data: An overview and tutorial.” Tutorials Quant. Methods Psychol. 8 (1): 23. https://doi.org/10.20982/tqmp.08.1.p023.
Hallowell, M. R., and J. A. Gambatese. 2009. “Construction safety risk mitigation.” J. Constr. Eng. Manage. 135 (12): 1316–1323. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000107.
Hallowell, M. R., and J. A. Gambatese. 2010. “Qualitative research: Application of the Delphi method to CEM research.” J. Constr. Eng. Manage. 136 (1): 99–107. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000137.
Heiko, A. 2012. “Consensus measurement in Delphi studies: Review and implications for future quality assurance.” Technol. Forecasting Social Change 79 (8): 1525–1536. https://doi.org/10.1016/j.techfore.2012.04.013.
Henchion, M., and B. McIntyre. 2005. “Market access and competitiveness issues for food SMEs in Europe’s lagging rural regions (LRRs).” Br. Food J. 107 (6): 404–422. https://doi.org/10.1108/00070700510602183.
Hinks, J., and P. McNay. 1999. “The creation of a management-by-variance tool for facilities management performance assessment.” Facilities 17 (1–2): 31–53. https://doi.org/10.1108/02632779910248893.
Hosseini, A., O. Lædre, B. Andersen, O. Torp, N. Olsson, and J. Lohne. 2016. “Selection criteria for delivery methods for infrastructure projects.” Procedia-Social Behav. Sci. 226 (Jul): 260–268. https://doi.org/10.1016/j.sbspro.2016.06.187.
Jin, H., S. Liu, C. Liu, and N. Udawatta. 2019. “Optimizing the concession period of PPP projects for fair allocation of financial risk.” Eng. Constr. Archit. Management. 26 (10): 2347–2363. https://doi.org/10.1108/ECAM-05-2018-0201/full/html.
Jin, L., Z. Zhang, and J. Song. 2020. “Profit allocation and subsidy mechanism for public–private partnership toll road projects.” J. Manage. Eng. 36 (3): 04020011. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000766.
Ke, Y., S. Wang, A. P. Chan, and P. T. Lam. 2010. “Preferred risk allocation in China’s public–private partnership (PPP) projects.” Int. J. Project Manage. 28 (5): 482–492. https://doi.org/10.1016/j.ijproman.2009.08.007.
Kessler, F. W. 2016. Arizona wades into P3 mainstream with south mountain freeway $916m DBM deal. Peterborough, NH: Public Works Financing.
Kometa, S. T., P. O. Olomolaiye, and F. C. Harris. 1994. “Attributes of UK construction clients influencing project consultants’ performance.” Construct. Manage. Econ. 12 (5): 433–443. https://doi.org/10.1080/01446199400000053.
Kwak, Y. H., Y. Chih, and C. W. Ibbs. 2009. “Towards a comprehensive understanding of public private partnerships for infrastructure development.” Calif. Manage. Rev. 51 (2): 51–78. https://doi.org/10.2307/41166480.
Li, S., D. Abraham, and H. Cai. 2017. “Infrastructure financing with project bond and credit default swap under public-private partnerships.” Int. J. Project Manage. 35 (3): 406–419. https://doi.org/10.1016/j.ijproman.2017.01.005.
Linstone, H. A., and M. Turoff. 1975. “Introduction to the Delphi method: Techniques and applications.” In The Delphi method: Techniques and applications, 3–12. Boston: Addison-Wesley.
Lu, Z., and Q. Meng. 2017. “Analysis of optimal BOT highway capacity and economic toll adjustment provisions under traffic demand uncertainty.” Transp. Res. Part E: Logist. Transp. Rev. 100 (Apr): 17–37. https://doi.org/10.1016/j.tre.2017.01.007.
Lucko, G., and E. M. Rojas. 2010. “Research validation: Challenges and opportunities in the construction domain.” J. Constr. Eng. Manage. 136 (1): 127–135. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000025.
Ludwig, B. 1997. “Predicting the future: Have you considered using the Delphi methodology.” J. Extension 35 (5): 1–4.
Lugard, S. B. 2020. “Risks and challenges in public-private partnership projects in Nigeria: A case study of the concession of Murtala Mohammed airport 2 terminal (Lagos) to Bi-Courtney Nigeria Ltd.” KAS African Law Study Library 6 (4): 563–576.
Luo, L., Q. He, J. Xie, D. Yang, and G. Wu. 2017. “Investigating the relationship between project complexity and success in complex construction projects.” J. Manage. Eng. 33 (2): 04016036. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000471.
Luzon, B., and S. M. El-Sayegh. 2016. “Evaluating supplier selection criteria for oil and gas projects in the UAE using AHP and Delphi.” Int. J. Constr. Manage. 16 (2): 175–183. https://doi.org/10.1080/15623599.2016.1146112.
MacCarthy, B. L., and W. Atthirawong. 2003. “Factors affecting location decisions in international operations: A Delphi study.” Int. J. Oper. Prod. Manage. 23 (7): 794–818. https://doi.org/10.1108/01443570310481568.
Maslak, K., and B. Franz. 2018. “Exploring the Growth of Public-Private Partnerships by Examining Enabling Legislation.” In Proc., Construction Research Congress 2018, 95–104. Reston, VA: ASCE.
Migliaccio, G. C. 2007. “Planning for strategic change in the project delivery strategy.” Ph.D. dissertation. Dept. of Civil, Architectural and Environmental Engineering, Univ. of Texas.
Migliaccio, G. C., G. E. Gibson, and J. T. O’Connor. 2009. “Procurement of design-build services: Two-phase selection for highway projects.” J. Manage. Eng. 25 (1): 29–39. https://doi.org/10.1061/(ASCE)0742-597X(2009)25:1(29).
Molenaar, K., C. Harper, and I. Yugar-Arias. 2014. Guidebook for selecting alternative contracting methods for roadway projects: Project delivery methods, procurement procedures, and payment provisions. Washington, DC: Transportation Research Board.
Montgomery, A. A., A. Graham, P. H. Evans, and T. Fahey. 2002. “Inter-rater agreement in the scoring of abstracts submitted to a primary care research conference.” BMC Health Serv. Res. 2 (1): 8. https://doi.org/10.1186/1472-6963-2-8.
Nakatsu, R. T., and C. L. Iacovou. 2009. “A comparative study of important risk factors involved in offshore and domestic outsourcing of software development projects: A two-panel Delphi study.” Inf. Manage. 46 (1): 57–68. https://doi.org/10.1016/j.im.2008.11.005.
National Cooperative Highway Research Program. 2020. Guidebook for implementing alternative technical concepts in all types of highway project delivery methods. Washington, DC: Transportation Research Board.
Nguyen, D., and M. Garvin. 2016. “Risk allocation and management practices in highway PPP contracts: Pilot study of Virginia.” In Proc., Construction Research Congress 2016, 559–568. Reston, VA: ASCE. https://doi.org/10.1061/9780784479827.057.
Nguyen, D. A., and M. J. Garvin. 2019. “Life-cycle contract management strategies in US highway public–private partnerships: Public control or concessionaire empowerment?” J. Manage. Eng. 35 (4): 04019011. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000687.
Nunnally, J. C. 1994. Psychometric theory 3E. New York: Tata McGraw-Hill Education.
Nuwagaba, I., and T. Molokwane. 2020. “A qualitative analysis of public private partnership (PPP) project contracts in the roads sector. A contextual elucidation of Uganda national roads authority (UNRA).” Int. J. Bus. Administration 11 (5): 44–57. https://doi.org/10.5430/ijba.v11n5p44.
Olawumi, T. O., and D. W. Chan. 2018. “Critical success factors (CSFs) for amplifying the integration of BIM and sustainability principles in construction projects: A Delphi study.” In Proc., RICS COBRA, Conf. 2018 RICS, 23–25. London: Royal Institution of Chartered Surveyors.
Orndoff, C. J. 2005. “Promising new tool for stakeholder interaction.” J. Archit. Eng. 11 (4): 139–146. https://doi.org/10.1061/(ASCE)1076-0431(2005)11:4(139).
Pätäri, S., S. Annala, A. Jantunen, S. Viljainen, and A. Sinkkonen. 2016. “Enabling and hindering factors of diffusion of energy service companies in Finland—Results of a Delphi study.” Energy Effic. 9 (6): 1447–1460. https://doi.org/10.1007/s12053-016-9433-z.
Perera, B. A. K. S., R. Rameezdeen, N. Chileshe, and M. R. Hosseini. 2014. “Enhancing the effectiveness of risk management practices in Sri Lankan road construction projects: A Delphi approach.” Int. J. Construct. Manage. 14 (1): 1–14. https://doi.org/10.1080/15623599.2013.875271.
PPP (Public Private Partnership). 2022. “Payment mechanism.” Accessed May 28, 2022. https://pppknowledgelab.org/guide/sections/63-payment-mechanism.
Rahman, I. A., I. B. Ismail, and M. M. Jaber. 2018. “Risk assessment of time and cost overrun factors throughout construction project lifecycle: Pilot study.” Int. J. Eng. Technol. 7 (3–20): 717–723.
Sambasivan, M., and Y. W. Soon. 2007. “Causes and effects of delays in Malaysian construction industry.” Int. J. Project Manage. 25 (5): 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007.
Shrestha, K. 2016. Framework of performance-based contracting for chip seal and striping maintenance activities. Las Vegas: Univ. of Nevada.
Shrestha, K., J. T. O’Conoor, and G. E. Gibson. 2012. “Performance comparison of large design-build and design-bid-build highway projects.” J. Constr. Eng. Manage. 138 (1): 1–13. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000390.
Shrestha, K., and P. P. Shrestha. 2020. “Framework development of performance-based striping maintenance contracts.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (2): 04520014. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000385.
Shrestha, K., and P. P. Shrestha. 2022. “Framework to implement performance-based contracting for chip-seal road maintenance.” J. Constr. Eng. Manage. 148 (1): 04021183. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002207.
Shrestha, K. K., and P. P. Shrestha. 2019. “Change orders on road maintenance contracts: Causes and preventive measures.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 11 (3): 04519009. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000299.
Shrestha, P. P., B. D. Davis, and G. M. Gad. 2020. “Legal and contractual issues in lump-sum design-build implementation on large-scale airport projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (3): 04520022. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000404.
Shrout, P. E., and J. L. Fleiss. 1979. “Intraclass correlations uses in assessing rater reliability.” Psychol. Bull. 86 (2): 420. https://doi.org/10.1037/0033-2909.86.2.420.
Sourani, A., and M. Sohail. 2015. “The Delphi method: Review and use in construction management research.” Int. J. Constr. Educ. Res. 11 (1): 54–76. https://doi.org/10.1080/15578771.2014.917132.
Verweij, S. 2015. “Achieving satisfaction when implementing PPP transportation infrastructure projects: A qualitative comparative analysis of the A15 highway DBFM project.” Int. J. Project Manage. 33 (1): 189–200. https://doi.org/10.1016/j.ijproman.2014.05.004.
Vesković, S., Ž. Stević, G. Stojić, M. Vasiljević, and S. Milinković. 2018. “Evaluation of the railway management model by using a new integrated model DELPHI-SWARA-MABAC.” Dec. Making: Appl. Manage. Eng. 1 (2): 34–50. https://doi.org/10.31181/dmame1802034v.
Vidal, L. A., F. Marle, and J. C. Bocquet. 2011. “Using a Delphi process and the analytic hierarchy process (AHP) to evaluate the complexity of projects.” Expert Syst. Appl. 38 (5): 5388–5405. https://doi.org/10.1016/j.eswa.2010.10.016.
Wang, Y., and Z. J. Zhao. 2018a. “Evaluating the effectiveness of public–private partnerships in highway development: The case of Virginia.” Transp. Res. Rec. 2672 (4): 43–53. https://doi.org/10.1177/0361198118791629.
Wang, Y., and Z. J. Zhao. 2018b. “Performance of public–private partnerships and the influence of contractual arrangements.” Public Perf. Manage. Rev. 41 (1): 177–200. https://doi.org/10.1080/15309576.2017.1400989.
Xia, B., and A. P. Chan. 2012a. “Identification of selection criteria for operational variations of the design-build system: A Delphi study in China.” J. Civ. Eng. Manage. 18 (2): 173–183. https://doi.org/10.3846/13923730.2012.657417.
Xia, B., and A. P. Chan. 2012b. “Measuring complexity for building projects: A Delphi study.” Eng. Constr. Archit. Manage. 19 (1): 7–24. https://doi.org/10.1108/09699981211192544.
Xia, B., A. P. Chan, and J. F. Yeung. 2011. “Developing a fuzzy multicriteria decision-making model for selecting design-build operational variations.” J. Constr. Eng. Manage. 137 (12): 1176–1184. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000381.
Xia, B., K. Molenaar, A. Chan, M. Skitmore, and J. Zuo. 2013. “Determining optimal proportion of design in design-build request for proposals.” J. Constr. Eng. Manage. 139 (6): 620–627. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000643.
Xu, Y., J. F. Yeung, and S. Jiang. 2014. “Determining appropriate government guarantees for concession contract: Lessons learned from 10 PPP projects in China.” Int. J. Strategic Property Manage. 18 (4): 356–367. https://doi.org/10.3846/1648715X.2014.971088.
Yeung, J. F., A. P. Chan, and D. W. Chan. 2009. “Developing a performance index for relationship-based construction projects in Australia: Delphi study.” J. Manage. Eng. 25 (2): 59–68. https://doi.org/10.1061/(ASCE)0742-597X(2009)25:2(59).
Yong, H. K. 2010. Public-private partnerships policy and practice: A reference guide London: Commonwealth Secretariat.
Zaiontz, C. 2015. “Real statistics using excel.” Accessed July 7, 2021. https://www.real-statistics.com.
Zhang, S., J. Li, Y. Li, and X. Zhang. 2021. “Revenue risk allocation mechanism in public-private partnership projects: Swing option approach.” J. Constr. Eng. Manage. 147 (1): 04020153. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001952.
Zhao, Z. G., J. Q. Cheng, S. L. Xu, W. L. Hou, and J. H. Richardus. 2015. “A quality assessment index framework for public health services: A Delphi study.” Public Health 129 (1): 43–51. https://doi.org/10.1016/j.puhe.2014.10.016.

Information & Authors

Information

Published In

Go to Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 15Issue 1February 2023

History

Received: Aug 4, 2021
Accepted: Aug 4, 2022
Published online: Nov 7, 2022
Published in print: Feb 1, 2023
Discussion open until: Apr 7, 2023

Permissions

Request permissions for this article.

ASCE Technical Topics:

Authors

Affiliations

Assistant Professor, Dept. of Civil and Environmental Engineering, Manhattan College, NY 10471 (corresponding author). ORCID: https://orcid.org/0000-0001-8274-8431. Email: [email protected]
P.E.
Professor of Construction Engineering Management, Civil and Environmental Engineering and Construction, Howard R. Hughes College of Engineering, Univ. of Nevada, Las Vegas, NV 89154. ORCID: https://orcid.org/0000-0001-6362-2315. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share