Application of Takt and Kanban to Modular Wind Turbine Construction

Publication: Journal of Construction Engineering and Management
Volume 148, Issue 2

Abstract

This study focuses on the applicability of Takt planning in combination with Kanban, plan-do-check-act (PDCA)/Deming cycle, and visual management to modular offshore wind turbine construction. The modular offshore wind industry, and in particular an offshore wind project in the British section of the North Sea, faced issues with delivery times, productivity, and uncertainty management (safety and/or pandemic disruptions). The objective of our research was to develop and test a conceptual model that responds to these challenges, which further will increase the likelihood of reducing delays in offshore energy operations. The initial literature review made it evident that few, if any, have covered Takt implementation in modular construction, and certainly not in offshore energy operations. A design science approach was chosen, and in collaboration with the case organization, the model was constructed and evaluated in a longitudinal field study. The application of mixed methods ensured data input originating from practical experience provided by field experts both within and outside the case-study organizations, theoretical knowledge from academics, and state-of-the-art literature allowed the development of a model that embeds Kanban, Takt, and PDCA to the context of modular offshore wind turbine tower construction. After its implementation, a 10% increase in labor productivity was recorded. Furthermore, through the stable productivity measures in a time of crisis, the model revealed its robustness during COVID-19. The contributions to the body of knowledge are the developed model combining Takt, Kanban, and PDCA, and the visual management interface. The model was implemented together with the visual management interface to achieve a flexible planning framework that can respond to challenges with delivery times and productivity and withstand major disruptions, such as the COVID-19 pandemic.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Data generated or analyzed during the study appear in the paper presented. Information about the Journal’s data-sharing policy can be found here: https://ascelibrary.org/doi/10.1061/(ASCE)CO.1943-7862.0001263.

References

Ballard, G., and G. Howell. 1994. “Implementing lean construction: Stabilizing work flow.” In Lean construction, 101–110. Rotterdam, Netherlands: A.A. Balkema.
Ballard, G., and I. Tommelein. 2016. “Current process benchmark for the last planner system.” Lean Construct. J. 89 (Jun): 57–89.
Barlow, E., D. Tezcaner Öztürk, M. Revie, K. Akartunalı, A. H. Day, and E. Boulougouris. 2018. “A mixed-method optimisation and simulation framework for supporting logistical decisions during offshore wind farm installations.” Eur. J. Oper. Res. 264 (3): 894–906. https://doi.org/10.1016/j.ejor.2017.05.043.
Bascoul, A. M., and I. D. Tommelein. 2017. “Visualizing daily on-site space use.” In Proc., 25th Annual Conf. of the Int. Group for Lean Construction, 597–604. Heraklion, Greece: International Group for Lean Construction.
Baskerville, R. 2008. “What design science is not.” Eur. J. Inf. Syst. 17 (5): 441–443. https://doi.org/10.1057/ejis.2008.45.
Binninger, M., J. Dlouhy, M. Müller, M. Schattmann, and S. Haghsheno. 2018. “Short Takt time in construction—A practical study.” In Proc., 26th Annual Conf. of the Int. Group for Lean Construction, 1133–1143. Chennai, India: International Group for Lean Construction.
Bonvik, A. M., C. E. Couch, and S. B. Gershwin. 1997. “A comparison of production-line control mechanisms.” Int. J. Prod. Res. 35 (3): 789–804. https://doi.org/10.1080/002075497195713.
Braglia, M., D. Castellano, M. Gallo, and G. Romagnoli. 2019. “A visual planning solution to streamline the processes of hybrid cross-dockings.” Prod. Plann. Control 30 (1): 33–47. https://doi.org/10.1080/09537287.2018.1520317.
Chua, D. K. H., and L. J. Shen. 2005. “Key constraints analysis with integrated production scheduler.” J. Constr. Eng. Manage. 131 (7): 753–764. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:7(753).
Cusack, M. M. 1984. “The use and limitations of mathematical models in the planning and control of construction projects.” Construct. Manage. Econ. 2 (3): 219–224. https://doi.org/10.1080/01446198400000020.
Dalgic, Y., I. Lazakis, O. Turan, and S. Judah. 2015. “Investigation of optimum jack-up vessel chartering strategy for offshore wind farm O&M activities.” Ocean Eng. 95 (Feb): 106–115. https://doi.org/10.1016/j.oceaneng.2014.12.011.
Deming, W. E. 2000. The new economics: For industry, government, education. Cambridge, MA: MIT Press.
El-Sabek, L. M., and B. Y. McCabe. 2018. “Coordination challenges of production planning in the construction of international mega-projects in the Middle East.” Int. J. Construct. Educ. Res. 14 (2): 118–140. https://doi.org/10.1080/15578771.2016.1276109.
Enevoldsen, P., and G. Xydis. 2019. “Examining the trends of 35 years growth of key wind turbine components.” Energy Sustainable Dev. 50 (Jun): 18–26. https://doi.org/10.1016/j.esd.2019.02.003.
Enshassi, M. S. A., S. Walbridge, J. S. West, and C. T. Haas. 2020. “Dynamic and proactive risk-based methodology for managing excessive geometric variability issues in modular construction projects using Bayesian theory.” J. Constr. Eng. Manage. 146 (2): 04019096. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001747.
FIDIC (International Federation of Consulting Engineers). 2019. “Fédération Internationale des Ingénieurs Conseils.” Accessed July 5, 2019. http://fidic.org/books/plant-and-design-build-contract-2nd-ed-2017-yellow-book.
Flynn, B. B., S. Sakakibara, R. G. Schroeder, K. A. Bates, and E. J. Flynn. 1990. “Empirical research methods in operations management.” J. Oper. Manage. 9 (2): 250–284. https://doi.org/10.1016/0272-6963(90)90098-X.
Flyvbjerg, B. 2011. “Over budget, over time, over and over again: Managing major projects.” In The Oxford handbook of project management, edited by J. K. P. Peter, W. G. Morris, and J. Söderlund, 321–344. Oxford, UK: Oxford University Press.
Flyvbjerg, B., N. Bruzelius, and W. Rothengatter. 2003. Megaprojects and risk: An anatomy of ambition. Cambridge, UK: Cambridge University Press.
Framinan, J. M., P. L. González, and R. Ruiz-Usano. 2003. “The CONWIP production control system: Review and research issues.” Prod. Plann. Control 14 (3): 255–265. https://doi.org/10.1080/0953728031000102595.
Germs, R., and J. Riezebos. 2010. “Workload balancing capability of pull systems in MTO production.” Int. J. Prod. Res. 48 (8): 2345–2360. https://doi.org/10.1080/00207540902814314.
Gill, T. G., and A. R. Hevner. 2013. “A fitness-utility model for design science research.” ACM Trans. Manage. Inf. Syst. 4 (2): 1–24. https://doi.org/10.1145/2499962.2499963.
Goel, R. K., J. W. Saunoris, and S. S. Goel. 2021. “Supply chain performance and economic growth: The impact of COVID-19 disruptions.” J. Policy Model. 43 (2): 298–316. https://doi.org/10.1016/j.jpolmod.2021.01.003.
Goh, M., and Y. M. Goh. 2019. “Lean production theory-based simulation of modular construction processes.” Autom. Constr. 101 (May): 227–244. https://doi.org/10.1016/j.autcon.2018.12.017.
Gong, D. 1997. “Optimization of float use in risk analysis-based network scheduling.” Int. J. Project Manage. 15 (3): 187–192. https://doi.org/10.1016/S0263-7863(95)00083-6.
Gong, J., J. D. Borcherding, and C. H. Caldas. 2011. “Effectiveness of craft time utilization in construction projects.” Construct. Manage. Econ. 29 (7): 737–751. https://doi.org/10.1080/01446193.2011.595013.
Hajji, A., A. Gharbi, J.-P. Kenné, and Y. Hidehiko. 2009. “Production and changeover control policies of a class of failure prone buffered flow-shops.” Prod. Plann. Control 20 (8): 785–800. https://doi.org/10.1080/09537280903232354.
Handa, V. K., and O. Abdalla. 1989. “Forecasting productivity by work sampling.” Construct. Manage. Econ. 7 (1): 19–28. https://doi.org/10.1080/01446198900000003.
Heinonen, A., and O. Seppänen. 2016. “Takt time planning: Lessons for construction industry from a cruise ship cabin refurbishment case study.” In Proc., 24th Annual Conf. of the Int. Group for Lean Construction. Boston: International Group for Lean Construction.
Hevner, A. R., S. T. March, J. Park, and S. Ram. 2004. “Design science in information systems research.” MIS Q. 28 (1): 75–105. https://doi.org/10.2307/25148625.
Hollnagel, E. 2008. “Risk+barriers=safety?” Saf. Sci. 46 (2): 221–229. https://doi.org/10.1016/j.ssci.2007.06.028.
Hopp, W. J., and M. L. Spearman. 1991. “Throughput of a constant work in process manufacturing line subject to failures.” Int. J. Prod. Res. 29 (3): 635. https://doi.org/10.1080/00207549108930093.
Hopp, W. J., and M. L. Spearman. 1996. Factory physics: Foundations of manufacturing management. New York: McGraw-Hill.
Hopp, W. J., and M. L. Spearman. 2004. “To pull or not to pull: What is the question?” Manuf. Serv. Oper. Manage. 6 (2): 133–148. https://doi.org/10.1287/msom.1030.0028.
Ikuma, L. H., I. Nahmens, and J. James. 2011. “Use of safety and lean integrated kaizen to improve performance in modular homebuilding.” J. Constr. Eng. Manage. 137 (7): 551–560. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000330.
Innella, F., M. Arashpour, and Y. Bai. 2019. “Lean methodologies and techniques for modular construction: Chronological and critical review.” J. Constr. Eng. Manage. 145 (12): 04019076. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001712.
Irawan, C. A., D. Jones, and D. Ouelhadj. 2017a. “Bi-objective optimisation model for installation scheduling in offshore wind farms.” Comput. Oper. Res. 78 (Feb): 393–407. https://doi.org/10.1016/j.cor.2015.09.010.
Irawan, C. A., X. Song, D. Jones, and N. Akbari. 2017b. “Layout optimisation for an installation port of an offshore wind farm.” Eur. J. Oper. Res. 259 (1): 67–83. https://doi.org/10.1016/j.ejor.2016.09.032.
Jabbari, A., I. D. Tommelein, and P. M. Kaminsky. 2020. “Workload leveling based on work space zoning for Takt planning.” Autom. Constr. 118 (Oct): 103223. https://doi.org/10.1016/j.autcon.2020.103223.
Järvinen, P. 2007. “Action research is similar to design science.” Qual. Quantity 41 (1): 37–54. https://doi.org/10.1007/s11135-005-5427-1.
Johnston, R. B., and M. Brennan. 1996. “Planning or organizing: The implications of theories of activity for management of operations.” Omega 24 (4): 367–384. https://doi.org/10.1016/0305-0483(96)00016-3.
Kelley, J. E., and M. R. Walker. 1959. “Critical-path planning and scheduling.” In Proc., IRE-AIEE-ACM’59, Eastern Joint IRE-AIEE-ACM Computer Conf., 160–173. New York: Association for Computing Machinery. https://doi.org/10.1145/1460299.1460318.
Kerkhove, L. P., and M. Vanhoucke. 2017. “Optimised scheduling for weather sensitive offshore construction projects.” Omega 66 (Jan): 58–78. https://doi.org/10.1016/j.omega.2016.01.011.
Kirchbach, K., L. Koskela, and F. Gehbauer. 2014. “Digital Kanban for earthwork site management.” In Proc., 22nd Annual Conf. of the Int. Group for Lean Construction, edited by B. T. Kalsaas, L. Koskela, and T. A. Saurin, 663–676. Oslo, Norway: International Group for Lean Construction.
Koch, C. 2012. “Contested overruns and performance of offshore wind power plants.” Construct. Manage. Econ. 30 (8): 609–622. https://doi.org/10.1080/01446193.2012.687830.
Koskela, L. 2000. An exploration towards a production theory and its application to construction. Espoo, Finland: Valtion teknillinen tutkimuskeskus Publications.
Koskela, L., and G. Howell. 2002. “The underlying theory of project management is obsolete.” In Proc., PMI Research Conf., 293–302. Newtown Square, PA: Project Management Institute.
Lacal-Arántegui, R., J. M. Yusta, and J. A. Domínguez-Navarro. 2018. “Offshore wind installation: Analysing the evidence behind improvements in installation time.” Renewable Sustainable Energy Rev. 92 (Sep): 133–145. https://doi.org/10.1016/j.rser.2018.04.044.
Lee, J., and H. Hyun. 2019. “Multiple modular building construction project scheduling using genetic algorithms.” J. Constr. Eng. Manage. 145 (1): 04018116. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001585.
Lehtovaara, J., O. Seppänen, A. Peltokorpi, P. Kujansuu, and M. Grönvall. 2021. “How Takt production contributes to construction production flow: A theoretical model.” Construct. Manage. Econ. 39 (1): 73–95. https://doi.org/10.1080/01446193.2020.1824295.
Lerche, J. 2020. “Offshore wind project production system: Reducing construction duration through planning.” Ph.D. thesis, Aarhus BSS, School of Business and Social Sciences, Aarhus Univ.
Lerche, J., H. Neve, S. Wandahl, and A. Gross. 2020a. “Continuous improvements at operator level.” J. Eng. Project Prod. Manage. 10 (1): 64–70. https://doi.org/10.2478/jeppm-2020-0008.
Lerche, J., H. H. Neve, G. Ballard, J. Teizer, S. Wandahl, and A. Gross. 2020b. “Application of last planner system to modular offshore wind construction.” J. Constr. Eng. Manage. 146 (11): 05020015. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001922.
Lerche, J., O. Seppänen, K. B. Pedersen, H. Neve, S. Wandahl, and A. Gross. 2019. “Why would location-based scheduling be applicable for offshore wind turbine construction?” In Proc., 27th Annual Conf. of the Int. Group for Lean Construction (IGLC), 1283–1294. Dublin, Ireland: International Group for Lean Construction.
Little, J. D. C. 1961. “A proof for the queuing formula: L=λW.” Oper. Res. 9 (3): 383–387. https://doi.org/10.1287/opre.9.3.383.
Murtaza, M. B., D. J. Fisher, and M. J. Skibniewski. 1993. “Knowledge-based approach to modular construction decision support.” J. Constr. Eng. Manage. 119 (1): 115–130. https://doi.org/10.1061/(ASCE)0733-9364(1993)119:1(115).
Neve, H., S. Wandahl, S. Lindhard, J. Teizer, and J. Lerche. 2020a. “Determining the relationship between direct work and construction labor productivity in North America: Four decades of insights.” J. Constr. Eng. Manage. 146 (9): 04020110. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001887.
Neve, H., S. Wandahl, S. Lindhard, J. Teizer, and J. Lerche. 2020b. “Learning to see value-adding and non-value-adding work time in renovation production systems.” Prod. Plann. Control 1–13. https://doi.org/10.1080/09537287.2020.1843730.
Norouzi, N., G. Z. Zarazua de Rubens, P. Enevoldsen, and A. Behzadi Forough. 2021. “The impact of COVID-19 on the electricity sector in Spain: An econometric approach based on prices.” Int. J. Energy Res. 45 (4): 6320–6332. https://doi.org/10.1002/er.6259.
O’Connor, J. T., W. J. O’Brien, and O. C. Jin. 2015. “Standardization strategy for modular industrial plants.” J. Constr. Eng. Manage. 141 (9): 04015026. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001001.
Paterson, J., F. D’Amico, P. R. Thies, R. E. Kurt, and G. Harrison. 2018. “Offshore wind installation vessels—A comparative assessment for UK offshore rounds 1 and 2.” Ocean Eng. 148 (Jan): 637–649. https://doi.org/10.1016/j.oceaneng.2017.08.008.
Peffers, K., T. Tuunanen, M. A. Rothenberger, and S. Chatterjee. 2007. “A design science research methodology for information systems research.” J. Manage. Inf. Syst. 24 (3): 45–77. https://doi.org/10.2753/MIS0742-1222240302.
Peltokorpi, A., H. Olivieri, A. D. Granja, and O. Seppänen. 2018. “Categorizing modularization strategies to achieve various objectives of building investments.” Construct. Manage. Econ. 36 (1): 32–48. https://doi.org/10.1080/01446193.2017.1353119.
Petersen, K. R., E. S. Madsen, and A. Bilberg. 2016. “First lean, then modularization: Improving the maintenance of offshore wind turbines.” Int. J. Energy Sect. Manage. 10 (2): 221–244. https://doi.org/10.1108/IJESM-04-2015-0006.
Quandt, M., T. Beinke, A. Ait-Alla, and M. Freitag. 2017. “Simulation based investigation of the impact of information sharing on the offshore wind farm installation process.” J. Renewable Energy 2017 (Jan): 1–11. https://doi.org/10.1155/2017/8301316.
Rippel, D., N. Jathe, M. Becker, M. Lütjen, H. Szczerbicka, and M. Freitag. 2019. “A review on the planning problem for the installation of offshore wind farms.” IFAC-PapersOnLine 52 (13): 1337–1342. https://doi.org/10.1016/j.ifacol.2019.11.384.
Sacks, R. 2016. “What constitutes good production flow in construction.” Construct. Manage. Econ. 34 (9): 641–656. https://doi.org/10.1080/01446193.2016.1200733.
Salama, T., A. Salah, and O. Moselhi. 2021. “Integrating critical chain project management with last planner system for linear scheduling of modular construction.” Constr. Innovation 21 (4): 525–554. https://doi.org/10.1108/CI-05-2018-0046.
Sanni-Anibire, M. O., R. Mohamad Zin, and S. O. Olatunji. 2020. “Causes of delay in the global construction industry: A meta analytical review.” Int. J. Construct. Manage. 1–13. https://doi.org/10.1080/15623599.2020.1716132.
Sarker, B. R., and T. I. Faiz. 2017. “Minimizing transportation and installation costs for turbines in offshore wind farms.” Renewable Energy 101 (Feb): 667–679. https://doi.org/10.1016/j.renene.2016.09.014.
Saurin, T. A., C. T. Formoso, and F. B. Cambraia. 2006. “Towards a common language between lean production and safety management.” In Proc., 14th Annual Conf. of the Int. Group for Lean Construction, 483–495. Santiago, Chile: International Group for Lean Construction.
Schmenner, R. W. 1993. Production/operations management: From the inside out. New York: Macmillan.
Schmenner, R. W., and M. L. Swink. 1998. “On theory in operations management.” J. Oper. Manage. 17 (1): 97–113. https://doi.org/10.1016/S0272-6963(98)00028-X.
Shannon, C. E., and W. Weaver. 1949. The mathematical theory of communication (republished in 1962). Champaign, IL: University of Illinois Press.
Simon, H. A. 1996. The sciences of the artificial. Cambridge, MA: MIT Press.
Sklet, S. 2006. “Safety barriers: Definition, classification, and performance.” J. Loss Prev. Process Ind. 19 (5): 494–506. https://doi.org/10.1016/j.jlp.2005.12.004.
Sovacool, B. K., P. Enevoldsen, C. Koch, and R. J. Barthelmie. 2017. “Cost performance and risk in the construction of offshore and onshore wind farms.” Wind Energy 20 (5): 891–908. https://doi.org/10.1002/we.2069.
Spearman, M. L., D. L. Woodruff, and W. J. Hopp. 1990. “CONWIP: A pull alternative to Kanban.” Int. J. Prod. Res. 28 (5): 879–894. https://doi.org/10.1080/00207549008942761.
Stauffer, J. M., A. J. Pedraza-Martinez, L. Yan, and L. N. Van Wassenhove. 2018. “Asset supply networks in humanitarian operations: A combined empirical-simulation approach.” J. Oper. Manage. 63 (Nov): 44–58. https://doi.org/10.1016/j.jom.2018.07.002.
Stock-Williams, C., and S. K. Swamy. 2019. “Automated daily maintenance planning for offshore wind farms.” Renewable Energy 133 (Apr): 1393–1403. https://doi.org/10.1016/j.renene.2018.08.112.
Tezel, A., L. Koskela, and Z. Aziz. 2018. “Lean thinking in the highways construction sector: motivation, implementation and barriers.” Prod. Plann. Control 29 (3): 247–269. https://doi.org/10.1080/09537287.2017.1412522.
Tezel, A., L. Koskela, and P. Tzortzopoulos. 2016. “Visual management in production management: A literature synthesis.” J. Manuf. Technol. Manage. 27 (6): 766–799. https://doi.org/10.1108/JMTM-08-2015-0071.
van Aken, J., A. Chandrasekaran, and J. Halman. 2016. “Conducting and publishing design science research: Inaugural essay of the Design Science Department of the Journal of Operations Management.” J. Oper. Manage. 47–48 (Nov): 1–8. https://doi.org/10.1016/j.jom.2016.06.004.
van der Laan, E., J. van Dalen, M. Rohrmoser, and R. Simpson. 2016. “Demand forecasting and order planning for humanitarian logistics: An empirical assessment.” J. Oper. Manage. 45 (1): 114–122. https://doi.org/10.1016/j.jom.2016.05.004.
Vis, I. F. A., and E. Ursavas. 2016. “Assessment approaches to logistics for offshore wind energy installation.” Sustainable Energy Technol. Assess. 14 (Apr): 80–91. https://doi.org/10.1016/j.seta.2016.02.001.
Voss, C., N. Tsikriktsis, and M. Frohlich. 2002. “Case research in operations management.” Int. J. Oper. Prod. Manage. 22 (2): 195–219. https://doi.org/10.1108/01443570210414329.
WHO (World Health Organization). 2020. Situation report - 18. Feb 7 2020. Geneva: WHO.
Wieringa, R. J. 2010. “Design science methodology: Principles and practice.” In Proc., 32nd ACM/IEEE Int. Conf. on Software Engineering, ICSE 2010, 493–494. New York: Association for Computing Machinery. https://doi.org/10.1145/1810295.1810446.
Winge, S., and E. Albrechtsen. 2018. “Accident types and barrier failures in the construction industry.” Saf. Sci. 105 (Jun): 158–166. https://doi.org/10.1016/j.ssci.2018.02.006.
Wu, X., H. Yuan, G. Wang, S. Li, and G. Wu. 2019. “Impacts of lean construction on safety systems: A system dynamics approach.” Int. J. Environ. Res. Public Health 16 (2): 221. https://doi.org/10.3390/ijerph16020221.
Ye, Y., W. Jiao, and H. Yan. 2020. “Managing relief inventories responding to natural disasters: Gaps between practice and literature.” Prod. Oper. Manage. 29 (4): 807–832. https://doi.org/10.1111/poms.13136.
Yeo, K. T., and J. H. Ning. 2002. “Integrating supply chain and critical chain concepts in engineer-procure-construct (EPC) projects.” Int. J. Project Manage. 20 (4): 253–262. https://doi.org/10.1016/S0263-7863(01)00021-7.
Yin, R. K. 2014. Case study research: Design and methods. Los Angeles: SAGE.
Yu, H., M. Al-Hussein, S. Al-Jibouri, and A. Telyas. 2013. “Lean transformation in a modular building company: A case for implementation.” J. Manage. Eng. 29 (1): 103–111. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000115.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 148Issue 2February 2022

History

Received: May 18, 2021
Accepted: Nov 12, 2021
Published online: Dec 9, 2021
Published in print: Feb 1, 2022
Discussion open until: May 9, 2022

Permissions

Request permissions for this article.

Authors

Affiliations

Dept. of Business Development and Technology, Aarhus Univ., Birk Centerpark 15, Herning 7400, Denmark (corresponding author). ORCID: https://orcid.org/0000-0001-7076-9630. Email: [email protected]
Peter Enevoldsen [email protected]
Associate Professor, Dept. of Business Development and Technology, Aarhus Univ., Birk Centerpark 15, Herning 7400, Denmark. Email: [email protected]
Associate Professor, Dept. of Civil Engineering, Aalto Univ. School of Engineering, Espoo 02150, Finland. ORCID: https://orcid.org/0000-0002-2008-5924. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Simulation-Based Approach for Master Planning and Scheduling in Offsite Construction Supply Chain Management, Computing in Civil Engineering 2023, 10.1061/9780784485231.017, (138-145), (2024).
  • Space–Time–Workforce Visualization and Conditional Capacity Synthesis in Uncertainty, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-4991, 39, 2, (2023).
  • Evaluation of Lean Off-Site Construction Literature through the Lens of Industry 4.0 and 5.0, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-13622, 149, 12, (2023).
  • Task Decomposition and Service Composition on an Innovative Blockchain-Based Construction Service Trading Platform to Select Construction Services, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-12956, 149, 12, (2023).
  • The impact of COVID -19 on offshore wind project productivity – A case study, Renewable and Sustainable Energy Reviews, 10.1016/j.rser.2022.112188, 158, (112188), (2022).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share