Assessing the Impacts of an IT LPS Support System on Schedule Accomplishment in Construction Projects

Publication: Journal of Construction Engineering and Management
Volume 145, Issue 10

Abstract

This paper seeks to identify improvements in the level of implementation of the Last Planner System (LPS) with the use of information technologies (IT) based on its methodology. In addition, we correlate the level of implementation of specific LPS components to the plan percent complete (PPC). The conjoint analysis of IT benefits in implementation and correlation to PPC allowed identification of two critical components: the standardization of the planning and control process, which can be quantitatively assessed by the PPC, and the systematic analysis and removal of constraints assessed through the percentage of constraints removed (PCR). A sample of 50 projects was used to corroborate that projects that have higher PPC and PCR also have better performance, measured by the schedule accomplishment and number of noncompliances. Consequently, results inferred that projects that use IT systems based on LPS have a more systematic planning and control and better constraint management that also correspond to better schedule accomplishment and less noncompliance.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Data analyzed during the study were provided by a third party. Requests for data should be directed to the provider indicated in the Acknowledgments. Information about the Journal’s data-sharing policy can be found here: http://ascelibrary.org/doi/10.1061/(ASCE)CO.1943-7862.0001263.

Acknowledgments

The authors would like to acknowledge the help and support provided by GEPUC and GEPRO SpA, which provided access to data collection for this study. Also, the authors acknowledge financial support from FONDECYT (1181648) and the Pontificia Universidad Católica de Chile. Rodrigo Herrera acknowledges financial support for Ph.D. studies from VRI of PUC and CONICYT-PCHA/National Doctorate/2018-21180884, and Camilo Lagos acknowledges support for Ph.D. studies from CONICYT.

References

Alarcón, L. F., and R. Calderón. 2003a. “A production planning support system for construction projects.” In Proc., 11th Annual Conf. of the Int. Group for Lean Construction. Haifa, Israel: International Group for Lean Construction.
Alarcón, L. F., and R. Calderón. 2003b. “Implementing lean production strategies in construction companies.” In Proc., Construction Research Congress in Construction—Wind of Change: Integration and Innovation. Haifa, Israel: International Group for Lean Construction.
Alarcón, L. F., S. Diethelm, Ó. Rojo, and R. Calderon. 2005. “Assessing the impacts of implementing lean construction.” In Proc., 13th Int. Group for Lean Construction Conf., 387–393. Haifa, Israel: International Group for Lean Construction.
Alarcón, L. F., J. L. Salvatierra, and J. A. Letelier. 2014. “Using last planner indicators to identify early signs of project performance.” In Proc., 22nd Annual Conf. on Int. Group for Lean Construction, 547–558. Haifa, Israel: International Group for Lean Construction.
Alsehaimi, A. O., P. T. Fazenda, and L. Koskela. 2014. “Improving construction management practice with the last planner system: A case study.” Eng. Constr. Archit. Manage. 21 (1): 51–64. https://doi.org/10.1108/ECAM-03-2012-0032.
Ballard, G. 2000. The last planner system of production control. Birmingham, UK: Univ. of Birmingham.
Ballard, G., and G. Howell. 1998. “Shielding production: Essential step in production control.” J. Constr. Eng. Manage. 124 (1): 11–17. https://doi.org/10.1061/(ASCE)0733-9364(1998)124:1(11).
Bernardes, M., and C. Formoso. 2002. “Contributions to the evaluation of production planning and control systems in building companies.” In Proc., 10th Annual Conf. of the Int. Group for Lean Construction, 1–11. Haifa, Israel: International Group for Lean Construction.
Choo, H. J., J. Hammond, I. D. Tommelein, S. A. Austin, and G. Ballard. 2004. “DePlan: A tool for integrated design management.” Autom. Constr. 13 (3): 313–326. https://doi.org/10.1016/j.autcon.2003.09.012.
Choo, H. J., I. D. Tommelein, G. Ballard, and T. Zabelle. 1998. “WorkPlan: Database for work package production scheduling.” In Proc., 6th Annual Conf. of the Int. Group for Lean Construction, 13–15. Haifa, Israel: International Group for Lean Construction.
Cisterna, D. 2013. Desarrollo y evaluación de indicadores de control para implementación en software de planificación y control de proyectos basado en metodología last planner. Santiago, Chile: Universidad de Chile.
Dalkey, N. 1969. The Delphi method: An experimental study of group opinion. Santa Monica, CA: RAND Corporation.
Daniel, E., C. Pasquire, and G. Dickens. 2015. “Exploring the implementation of the last planner system through IGLC community: Twenty-one years of experience.” In Proc., 23rd Annual Conf. of the Int. Group for Lean Construction, 153–162. Haifa, Israel: International Group for Lean Construction.
Dave, B., J. P. Hämäläinen, and L. Koskela. 2015. “Exploring the recurrent problems in the last planner implementation on construction projects.” In Proc., Indian Lean Construction Conf. (ILCC 2015), 1–9. Haifa, Israel: International Group for Lean Construction.
Emdanat, S., and M. Azambuja. 2016. “Aligning near and long-term planning for LPS implementations: A review of existing and new metrics.” In Proc., 24th Annual Conf. of the Int. Group for Lean Construction, 103–112. Haifa, Israel: International Group for Lean Construction.
Emdanat, S., M. Linnik, and D. Christian. 2016. “A framework for integrating Takt planning, last planner system and labor tracking.” In Proc., 24th Annual Conf. of the Int. Group for Lean Construction, 53–62. Haifa, Israel: International Group for Lean Construction.
Faloughi, M., W. Bechara, J. Chamoun, and F. Hamzeh. 2014. “SimpLean: An effective tool for optimizing construction workflow.” In Proc., 22nd Annual Conf. of the Int. Group for Lean Construction, 281–292. Haifa, Israel: International Group for Lean Construction.
Fernandez-Solis, J. L., Z. K. Rybkowski, S. Lavy, V. Porwal, N. Lagoo, K. Son, and A. Shafaat. 2012. “Survey of motivations, benefits and implementation challenges of last planner system users.” J. Constr. Eng. Manage. 139 (4): 354–360. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000606.
Formoso, C. T., and C. Moura. 2009. “Evaluation of the impact of the last planner system on the performance of construction projects.” In Proc., 17th Annual Conf. of the Int. Group for Lean Construction, 153–164. Haifa, Israel: International Group for Lean Construction.
Gao, S., and S. P. Low. 2014. “The last planner system in China’s construction industry—A SWOT analysis on implementation.” Int. J. Project Manage. 32 (7): 1260–1272. https://doi.org/10.1016/j.ijproman.2014.01.002.
Hamzeh, F., G. Ballard, and I. D. Tommelein. 2012. “Rethinking lookahead planning to optimize construction workflow.” Lean Constr. J. 8 (Apr): 15–34.
Hernández-Sampieri, R., C. Fernández-Collado, and P. Baptista-Lucio. 2006. Metodología de la investigación. México City: McGraw-Hill Interametricana.
Jang, J. W., and Y. W. Kim. 2007. “Use of percent of constraints removal to measure the make-ready process.” In Proc., 15th Annual Conf. of the Int. Group for Lean Construction, 529–538. Haifa, Israel: International Group for Lean Construction.
Lagos, C. 2017. Desarrollo e implementación de herramientas para el mejoramiento de la gestión de la información de last planner. Santiago, Chile: Pontificia Universidad Católica de Chile.
Lagos, C., L. F. Alarcón, and J. L. Salvatierra. 2016. Improving the use of information management for continuous improvement with the last planner system, 737–745. Bogotá, Colombia: Memorias Del VII Elagec.
Lagos, C., R. Herrera, and L. F. Alarcón. 2017. “Contributions of information technologies to last planner system implementation.” In Vol. 1 of Proc., Lean and Computing in Construction Congress (LC3). Haifa, Israel: International Group for Lean Construction.
Letelier, J. A. 2013. Análisis en el tiempo de indicadores de control de avance utilizados en el software computacional Impera para pronosticar efectos futuros en proyectos de construcción. Santiago, Chile: Universidad de Chile.
Linstone, H. A., and M. Turoff. 2002. “The Delphi method.” Accessed June 12, 2019. https://www.academia.edu/2352903/LEAN_CONSTRUCTION_IN_PORTUGAL_A_LAST_PLANNER_SYSTEM_IMPLEMENTATION_CASE_STUDY.
Peneirol, N. S. 2005. “Lean construction in Portugal: A last planner system implementation case study.” Accessed June 12, 2019. https://www.academia.edu/2352903/LEAN_CONSTRUCTION_IN_PORTUGAL_A_LAST_PLANNER_SYSTEM_IMPLEMENTATION_CASE_STUDY.
Priven, V., and R. Sacks. 2015. “Effects of the last planner system on social networks among construction trade crews.” J. Constr. Eng. Manage. 141 (6): 04015006. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000975.
Russell, M. M., M. Liu, G. Howell, and S. M. Hsiang. 2015. “Case studies of the allocation and reduction of time buffer through use of the last planner system.” J. Constr. Eng. Manage. 141 (2): 04014068. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000900.
Salvatierra, J. L., L. F. Alarcón, Á. López, and X. Velásquez. 2015. “Lean diagnosis for Chilean construction industry: Towards more sustainable lean practices and tools.” In Proc., 23rd Annual Conf. of the Int. Group for Lean Construction, 642–651. Haifa, Israel: International Group for Lean Construction.
Viana, D., B. Mota, C. T. Formoso, M. Echeveste, M. Peixoto, and C. L. Rodrigues. 2010. “A survey on the last planner system: Impacts and difficulties for implementation in Brazilian companies.” In Proc., 18th Annual Conf. of the Int. Group for Lean Construction, 497–507. Haifa, Israel: International Group for Lean Construction.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 145Issue 10October 2019

History

Received: May 21, 2018
Accepted: Feb 7, 2019
Published online: Jul 24, 2019
Published in print: Oct 1, 2019
Discussion open until: Dec 24, 2019

Permissions

Request permissions for this article.

Authors

Affiliations

Camilo Ignacio Lagos
Ph.D. Student, Production Management Centre, P. Univ. Católica de Chile, Vicuña Mackenna, Santiago 4860, Chile.
Professor of Civil Engineering, School of Civil Engineering, Pontificia Universidad Católica de Valparaíso, Valparaíso 23662804, Chile; Ph.D. Candidate, Production Management Centre, P. Univ. Católica de Chile, Vicuña Mackenna, Santiago 4860, Chile; Universitat Politècnica de València, Camino de Vera s/n, Valencia 46022, Spain (corresponding author). ORCID: https://orcid.org/0000-0001-5186-3154. Email: [email protected]
Luis Fernando Alarcón, M.ASCE
Professor of Engineering, Production Management Centre, P. Univ. Católica de Chile, Vicuña Mackenna, Santiago 4860, Chile.

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share