Planning-Phase Estimation of Construction Time for a Large Portfolio of Highway Projects

Publication: Journal of Construction Engineering and Management
Volume 145, Issue 4

Abstract

Estimation of highway project construction time prior to design development has received comparatively little focus from researchers. State transportation agencies (STAs) and their management teams need a method or tool to estimate construction time during the project planning and development phases, where STAs typically manage hundreds of projects at the program level. These programs of projects are updated periodically, which requires an estimation methodology that is efficient, less time consuming, and reliable during the phases where limited project information is available. This paper presents an approach to developing a planning-phase construction time estimation model using linear regression modeling on actual construction time and cost data from 623 highway projects completed by the Dallas District Office, Texas Department of Transportation (TxDOT). The study developed a multiple linear regression model with three project parameters that were identified as key predictors to construction time. The accuracy and reliability of the developed model were higher than those of the well-known Bromilow’s time-cost (BTC) model. The model was also validated by the Mann-Whitney test of its applicability to a large group of projects. The proposed model requires less effort to develop, update, and revise with new data, which allows STAs to conduct planning-phase estimation of the construction time of a large portfolio of diverse projects effectively and efficiently. STAs would benefit from using this model in various project planning areas such as financial planning, staff planning, transportation impact mitigation, budget allocation, and project prioritization. This study also contributes to the body of knowledge with the proposed construction time estimation methodology during the planning and development phase that has been less focused.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Data generated or analyzed during the study are available from the corresponding author by request. Information about the Journal’s data-sharing policy can be found here: http://ascelibrary.org/doi/10.1061/(ASCE)CO.1943-7862.0001263.

Acknowledgments

The authors would like to thank the Dallas District of the Texas Department of Transportation for providing support for data collection and analysis.

References

Albright, S. C., W. Winston, and C. Zappe. 2006. Data analysis and decision making. 3rd ed. Boston: Cengage Learning.
Bhokha, S., and S. O. Ogunlana. 1999. “Application of artificial neural network to forecast construction duration of buildings at the predesign stage.” Eng. Constr. Archit. Manage. 6 (2): 133–144. https://doi.org/10.1108/eb021106.
Bromilow, F. J. 1969. “Contract time performance expectations and the reality.” Build. Forum 1 (3): 70–80.
Czarnigowska, A., and A. Sobotka. 2014. “Estimating construction duration for public roads during the preplanning phase.” J. Eng. Prof. Prod. Manage. 4 (1): 26–35. https://doi.org/10.32738/JEPPM.201401.0004.
De la Garza, J. M., and K. G. Rouhana. 1995. “Neural networks versus parameter-based applications in cost.” Cost Eng. 37 (2): 14.
FHWA (Federal Highway Administration). 2002. “FHWA guide for construction contract time determination procedures.” Accessed June 18, 2017. https://www.fhwa.dot.gov/construction/contracts/t508015.cfm.
FHWA (Federal Highway Administration). 2017. The transportation planning process briefing book. Washington, DC: FHWA.
Hancher, D. E., W. F. McFarland, and R. T. Alabay. 1992. Construction contract time determination. Washington, DC: FHWA.
Herbsman, Z. J., and R. Ellis. 1995. Determination of contract time for highway construction projects. Washington, DC: National Cooperative Highway Research Program.
Hoffman, G. J., A. E. Thal Jr., T. S. Webb, and J. D. Weir. 2007. “Estimating performance time for construction projects.” J. Manage. Eng. 23 (4): 193–199. https://doi.org/10.1061/(ASCE)0742-597X(2007)23:4(193).
Irfan, M., M. B. Khurshid, P. Anastaspoulous, S. Labi, and F. Moavenzadeh. 2011. “Planning-stage estimation of highway project duration on the basis of anticipated project cost, project type, and contract type.” Int. J. Project Manage. 29 (1): 78–92. https://doi.org/10.1016/j.ijproman.2010.01.001.
Jarkas, A. M. 2016. “Predicting contract duration for building construction: Is Bromilow’s time-cost model a panacea?” J. Manage. Eng. 32 (1): 05015004. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000394.
Jin, R., S. Han, C. Hyun, and Y. Cha. 2016. “Application of case-based reasoning for estimating preliminary duration of building projects.” J. Constr. Eng. Manage. 142 (2): 04015082. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001072.
Kim, G. H., S. H. An, and K. I. Kang. 2004. “Comparison of construction cost estimating models based on regression analysis, neural networks, and case-based reasoning.” Build. Environ. 39 (10): 1235–1242. https://doi.org/10.1016/j.buildenv.2004.02.013.
Love, P. E., R. Y. Tse, and D. J. Edwards. 2005. “Time-cost relationships in Australian building construction projects.” J. Constr. Eng. Manage. 131 (2): 187–194. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:2(187).
Lu, M., S. M. AbouRizk, and U. H. Hermann. 2001. “Sensitivity analysis of neural networks in spool fabrication productivity studies.” J. Comput. Civ. Eng. 15 (4): 299–308. https://doi.org/10.1061/(ASCE)0887-3801(2001)15:4(299).
Mallela, J., and S. Sadavisam. 2011. Work zone road user costs: Concepts and applications. Washington, DC: Federal Highway Administration.
MassDOT (Massachusetts Department of Transportation). 2014. “Construction contract time determination (CTD) guidelines for designers/planners.” Accessed June 18, 2017. https://www.massdot.state.ma.us/Portals/8/docs/projectManagement/controlsGuidelines/CTDguidelines.pdf.
McCoy, K., A. Ingles, and W. Lyons. 2016. STIP State of the practice review: Development and use of statewide transportation improvement programs. Washington, DC: Federal Highway Administration.
Mendenhall, W., T. Sincich, and N. S. Boudreau. 2003. Vol. 6 of A second course in statistics: Regression analysis. Upper Saddle River, NJ: Prentice Hall.
Mensah, I., T. Adjei-Kumi, and G. Nani. 2016. “Duration determination for rural roads using the principal component analysis and artificial neural network.” Eng. Constr. Archit. Manage. 23 (5): 638–656. https://doi.org/10.1108/ECAM-09-2015-0148.
Nani, G., I. Mensah, and T. Adjei-Kumi. 2017. “Duration estimation model for bridge construction projects in Ghana.” J. Eng. Des. Technol. 15 (6): 754–777. https://doi.org/10.1108/JEDT-04-2017-0029.
NCDOT (North Carolina Department of Transportation). 2012. “Guidance for determining contract times.” Accessed June 18, 2017. https://connect.ncdot.gov/municipalities/Pages/Bid-Proposals-for-LGA.aspx.
Odabaşı, E. 2009. “Models for estimating construction duration: An application for selected buildings on the Metu campus.” M.S. thesis, Dept. of Architecture, Middle East Technical Univ.
Pewdum, W., T. Rujirayanyong, and V. Sooksatra. 2009. “Forecasting final budget and duration of highway construction projects.” Eng. Constr. Archit. Manage. 16 (6): 544–557. https://doi.org/10.1108/09699980911002566.
Skitmore, R. M., and S. T. Ng. 2003. “Forecast models for actual construction time and cost.” Build. Environ. 38 (8): 1075–1083. https://doi.org/10.1016/S0360-1323(03)00067-2.
Snee, R. D. 1977. “Validation of regression models: Methods and examples.” Technometrics 19 (4): 415–428. https://doi.org/10.1080/00401706.1977.10489581.
Sousa, V., N. M. Almeida, and L. A. Dias. 2014. “Role of statistics and engineering judgment in developing optimized time-cost relationship models.” J. Constr. Eng. Manage. 140 (8): 04014034. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000874.
TxDOT (Texas Department of Transportation). 2014. “Standard specifications for construction and maintenance of highways, streets and bridges.” Accessed June 18, 2017. ftp://ftp.dot.state.tx.us/pub/txdot-info/des/spec-book-1114.pdf.
TxDOT (Texas Department of Transportation). 2016. “2017–2020 Statewide transportation improvement program.” Accessed June 18, 2017. http://ftp.dot.state.tx.us/pub/txdot-info/tpp/stip/2017-2020/introduction.pdf.
TxDOT (Texas Department of Transportation). 2017a. “Highway cost index (1997 base) index report for May 2017.” Accessed June 18, 2017. http://ftp.dot.state.tx.us/pub/txdot-info/cst/hci-binder.pdf.
TxDOT (Texas Department of Transportation). 2017b. “Project development process manual.” Accessed June 18, 2017. http://onlinemanuals.txdot.gov/txdotmanuals/pdp/manual_notice.htm.
TxDOT (Texas Department of Transportation). 2018. “Project tracker.” Accessed April 30, 2018. http://apps.dot.state.tx.us/apps-cq/project_tracker/#.
US Census Bureau. 2010. “Centers of population by county: 2010.” Data Files. Accessed June 18, 2017. https://www2.census.gov/geo/docs/reference/cenpop2010/county/CenPop2010_Mean_CO48.txt.
VDOT (Virginia Department of Transportation). 2007. “Contract time determination guidelines.” Accessed June 18, 2017. http://www.vdot.virginia.gov/business/resources/const/CTDR_Guidelines_VDOT.pdf.
Washington, S. P., M. G. Karlaftis, and F. Mannering. 2010. Statistical and econometric methods for transportation data analysis. Boca Raton, FL: CRC Press.
Williams, R. C. 2008. “The development of mathematical models for preliminary prediction of highway construction duration.” Ph.D. dissertation, Dept. of Civil Engineering, Virginia Tech.
WSDOT (Washington State Department of Transportation). 2013. “Plans preparation manual.” Accessed June 18, 2017. http://www.wsdot.wa.gov/publications/manuals/fulltext/M22-31/M22-31.05Revision.pdf.
Zhai, D., Y. Shan, R. E. Sturgill, T. R. Taylor, and P. M. Goodrum. 2016. “Using parametric modeling to estimate highway construction contract time.” Transp. Res. Rec. 2573 (1): 1–9. https://doi.org/10.3141/2573-01.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 145Issue 4April 2019

History

Received: Mar 1, 2018
Accepted: Oct 1, 2018
Published online: Feb 14, 2019
Published in print: Apr 1, 2019
Discussion open until: Jul 14, 2019

Permissions

Request permissions for this article.

Authors

Affiliations

Research Associate, Center for Transportation Research, Univ. of Texas at Austin, 1616 Guadalupe, Suite 4.202, Austin, TX 78701 (corresponding author). ORCID: https://orcid.org/0000-0001-9460-0303. Email: [email protected]
Nabeel Khwaja [email protected]
P.E.
Assistant Director, Center for Transportation Research, Univ. of Texas at Austin, 1616 Guadalupe, Suite 4.202, Austin, TX 78701. Email: [email protected]
Duane S. Milligan [email protected]
P.E.
Director of Construction, Dallas District, Texas Dept. of Transportation, 4777 East Highway 80, Mesquite, TX 75150. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share