Lessons Learned from Applying the Individuals Control Charts to Monitoring Autocorrelated Project Performance Data
Publication: Journal of Construction Engineering and Management
Volume 142, Issue 5
Abstract
The well-known earned value technique measures and evaluates project performance. It uncovers schedule and cost deviations from the baseline plan. However, it is not established to determine acceptable levels of deviations from the baseline. This study applies the Shewhart individuals control charts to overcome this limitation; the charts monitor trends in the project performance behavior and allow them to be detected before the project deviates much from the baseline plan. The study statistically monitors several well-known earned value indexes of a construction project, where the data are autocorrelated and nonnormally distributed. The investigated case showed that the individuals control charts enhance capability of the earned value technique. The authors concluded that implementing the developed tool together with the traditional tools noticeably improves the project controlling scheme and provides more information on project progress. The study extends a previous study in which only independent data were investigated.
Get full access to this article
View all available purchase options and get full access to this article.
Acknowledgments
The authors would like to thank Mr. Hamed Keyvanfar for his generous support in providing the project information and progress reports, and the anonymous reviewers for their valuable comments on the first version of the paper.
References
Abba, W., and Niel, F. A. (2010). “Integrating technical performance measurement with earned value management.” Measurable News, 4, 6–8.
Aliverdi, R., Naeni, L. M., and Salehipour, A. (2013). “Monitoring project duration and cost in a construction project by applying statistical quality control charts.” Int. J. Project Manage., 31(3), 411–423.
Anbari, F. T. (2003). “Earned value project management method and extensions.” Project Manage. J., 34(4), 12–23.
Barraza, G. A., Back, E., and Mata, F. (2004). “Probabilistic forecasting of project performance using stochastic s curves.” J. Constr. Eng. Manage., 25–32.
Barraza, G. A., and Bueno, R. A. (2007). “Probabilistic control of project performance using control limit curves.” J. Constr. Eng. Manage., 957–965.
Bisgaard, S., and Kulahci, M. (2011). Time series analysis and forecasting by example, Wiley.
Blanco, V. D. (2003). “Earned value management: A predictive analysis tool.” Navy Supply Corps Newsletter, 2, 24–27.
Box, G., Jenkins, G., and Reinsel, G. (2008). Time series analysis: Forecasting and control, Wiley.
Burke, R. (2003). Project management planning and control techniques, 4th Ed., Wiley.
Christensen, D. S., Conley, R. J., and Kankey, R. D. (2000). “Some empirical evidence on the non-normality of cost variance on defense contracts.” J. Cost Anal. Manage., 2(1), 3–16.
Cioffi, D. F. (2006). “Designing project management: A scientific notation and an improved formalism for earned value calculations.” Int. J. Project Manage., 24(2), 136–144.
DeMarco, A., Briccarello, D., and Rafele, C. (2009). “Cost and schedule monitoring of industrial building projects: Case study.” J. Constr. Eng. Manage., 853–862.
Fleming, Q. W. and Koppelman, J. M. (2005). Earned value project management, 3rd Ed., Project Management Institute.
Henderson, K. (2004). “Further developments in earned schedule.” Measurable News, 3, 12–22.
Jacob, D. S., and Kane, M. (2004). “Forecasting schedule completion using earned value metrics revisited.” Measurable News, 4, 11–17.
Kandananond, K. (2014). “Guidelines for applying statistical quality control method to monitor autocorrelated processes.” J. Procedia Eng., 69, 1449–1458.
Kim, E., Wells, W. G. J., and Duffey, M. R. (2003). “A model for effective implementation of earned value management methodology.” Int. J. Project Manage., 21(5), 375–382.
Leu, S. S., and Lin, Y. C. (2008). “Project performance evaluation based on statistical process control techniques.” J. Constr. Eng. Manage., 813–819.
Lipke, W. (2002). “A study of the normality of earned value management indicators.” Measurable News, 3, 6–16.
Lipke, W. (2003). “Schedule is different.” Measurable News, 4, 31–34.
Lipke, W. (2004). “The probability of success.” J. Qual. Assur. Inst., 14–21.
Lipke, W. (2006). “Statistical methods applied to project management.” Proc., 3rd Int. Conf. on Project Management (PROMAC), 1022–1029.
Lipke, W. (2011). “Further study of the normality of CPI and SPI(t).” PM World Today, 13(10), 1–8.
Lipke, W., and Vaughn, J. (2000). “Statistical process control meets earned value.” J. Defense Software Eng., 13(6), 16–20.
Lipke, W., Zwikael, O., Henderson, K., and Anbari, F. (2009). “Prediction of project outcome, the application of statistical methods to earned value management and earned schedule performance indexes.” Int. J. Project Manage., 27(4), 400–407.
McKim, R., Hegazy, T., and Attalla, M. (2000). “Project performance control in reconstruction projects.” J. Constr. Eng. Manage., 137–141.
Minitab 17 [Computer software]. Minitab, Coventry, U.K.
Montgomery, D. C. (2009). Introduction to statistical quality control, 6th Ed., Wiley.
Naeni, L. M., Shadrokh, S., and Salehipour, A. (2011). “Evaluating fuzzy earned value indices and estimates by applying alpha cuts.” Expert Syst. Appl., 38(7), 8193–8198.
Naeni, L. M., Shadrokh, S., and Salehipour, A. (2014). “A fuzzy approach for the earned value management.” Int. J. Project Manage., 32(4), 709–716.
Narbaev, T., and Marco, A. D. (2011). “Cost estimate at completion methods in construction projects.” Proc., 2nd Int. Construction and Project Management Conf., Vol. 15, IACSIT Press, Singapore, 32–36.
Nelson, L. S. (1982). “Control charts for individual measurements.” J. Qual. Technol., 14(3), 172–174.
Nelson, L. S. (1984). “The Shewhart control chart-tests for special causes.” J. Qual. Technol., 16(4), 237–239.
PMI (Project Management Institute). (2004). Project management body of knowledge, 3rd Ed., PA.
PMI (Project Management Institute). (2005). Practice standard for earned value management, McGraw-Hill, PA.
PMI (Project Management Institute). (2008). Project management body of knowledge, 4th Ed., PA.
Rashmi, R. S. (2008). “Misuse and performance of individuals charts in statistical process control for single parameter distributions of unknown stability.” Master’s thesis, Dept. of Mechanical and Industrial Engineering, Northeastern Univ., Boston.
Russo, S. L., Camargo, M. E., and Fabris, J. P. (2012). Practical concepts of quality control, InTech, Rijeka, Croatia.
Shumway, R. H., and Stoffer, D. S. (2010). Time series analysis and its applications: With R examples, Springer, Berlin.
Vandevoorde, S., and Vanhoucke, M. (2006). “A comparison of different project duration forecasting methods using earned value metrics.” Int. J. Project Manage., 24(4), 289–302.
Wheeler, D. J. (2009). “When can we trust the limits on a process behavior chart?” Quality Digest, Chico, CA.
Wheeler, D. J. (2010). “Individuals charts done right and wrong.” Quality Digest, Chico, CA.
Information & Authors
Information
Published In
Copyright
© 2015 American Society of Civil Engineers.
History
Received: Feb 19, 2015
Accepted: Aug 28, 2015
Published online: Dec 23, 2015
Published in print: May 1, 2016
Discussion open until: May 23, 2016
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.