Causes of Variation in Construction Project Task Starting Times and Duration

Publication: Journal of Construction Engineering and Management
Volume 137, Issue 9

Abstract

In this research, variation is defined as the time difference between what was planned and what actually happened in terms of task starting times and duration. Variation in construction tasks is important as it can impact productivity performance. Construction projects consist of a large number of interdependent tasks. When the starting time and/or duration of one task varies, it can affect other downstream tasks and result in disruptions to the schedule and/or decreased productivity. The construction process is complex and involves numerous people with different levels of responsibility, which makes identifying the root causes of the variation difficult. A nationwide survey was administered to workers, foremen, and project managers to identify the most prevalent causes and magnitude of both starting time and task duration variation. Fifty individual causes of variation were divided into eight categories: prerequisite work, detailed design/working method, labor force, tools and equipment, material and components, work/job site conditions, management/supervision/information flow, and weather or external conditions. This research examined the similarities and differences in perceptions between craft workers, foremen, and project managers in terms of starting time and task duration variation. The top eight causes of starting time variation and top nine causes of task duration variation were identified. The research also quantitatively analyzed the underlying structure of the causes of variation using factor analysis. This was done by grouping the 50 individual causes into nine orthogonal factors that represent the underlying structure of the affecting causes. The findings will help construction project managers and field managers focus on the root causes of variation during planning in order to develop effective strategies to reduce variation and improve project productivity performance.

Get full access to this article

View all available purchase options and get full access to this article.

References

Ballard, G. (2000). “The last planner system of production control.” Ph.D. thesis, Dept. of Civil Engineering, Univ. of Birmingham, Birmingham, UK.
Borcherding, J., and Garner, D. (1981). “Work force motivation and productivity on large jobs.” J. Constr. Div., 107(3), 443–453.
Comrey, A. L., and Lee, H. B. (1992). A first course in factor analysis, Lawrence Erlbaum Assoc., Inc., Hillsdale, NJ.
Dai, J., Goodrum, P. M., and Maloney, W. F. (2009). “Construction craft workers’ perceptions of the factors affecting their productivity.” J. Constr. Eng. Manage., 135(3), 217–226.
Doloi, H. (2007). “Twinning motivation, productivity and management strategy in construction projects.” Eng. Manage. J., 19(3), 30–40.
Field, A. (2005). Discovering statistics using SPSS, 2nd Ed., SAGE Publications, Thousand Oaks, CA.
Goodrum, P. M., and Hass, C. T. (2002). “Partial factor productivity and equipment technology change at activity level in U.S. construction industry.” J. Constr. Eng. Manage., 128(6), 463–472.
Hallowell, M. R., and Gambatese, J. A. (2010). “Qualitative research: application of the Delphi method to CEM research.” J. Constr. Eng. Manage., 136(1), 99–107.
Herbsman, Z., and Ellis, R. (1990). “Research of factors influencing construction productivity.” Constr. Manage. Econ., 8, 49–61.
Harmon, H. H. (1976). Modern factor analysis, 3rd Ed., University of Chicago Press, Chicago.
Horman, M. J., and Thomas, H. R. (2005). “Role of inventory buffers in construction labor performance.” J. Constr. Eng. Manage., 131(7), 834–843.
Howell, G. A., and Ballard, G. (1994). “Implementing lean construction: Reducing inflow variation.” 2nd Annual Conf. on Lean Construction, Catolica Universidad de Chile, Santiago, Chile.
Howell, G. A., Ballard, G., Tommelein, I. D., and Koskela, I. (2004). “Discussion of ‘Reducing variability to improve performance as a lean construction principle.” J. Constr. Eng. Manage., 130(2), 299–304.
Kaiser, H. F. (1974). “An index of factorial simplicity.” Psychometrika, 39(1), 31–36.
Kaplan, H., Elburg, A., and Tommelein, I. D. (2005). “Analysis of variability in precasting and installation of pile foundations.” Proc., Construction Research Congr.(CD ROM), ASCE, Reston,VA, 〈http://ascelibrary.org/proceedings/resource/2/ascecp/183/40754?isAuthorized=no〉 (Aug. 25, 2011).
Kim, J. O., and Mueller, C. W. (1978). “Introduction to factor analysis.” Sage Univ. Paper Series on Quantitative Applications in Social Sciences, No. 07-013, Sage Publications, Newbury Park, CA.
Kim, D. Y., Han, S. H., and Kim, H. (2008). “Discriminant analysis for predicting ranges of cost variance in international construction projects.” J. Constr. Eng. Manage., 134(6), 398–411.
Kimpland, S. L. (2009). 2009 Contractor productivity survey results, FMI Corp., Raleigh, NC.
Kline, P. (1994). An easy guide to factor analysis, Routledge, New York.
Koskela, L. J. (2000). “An exploration towards a production theory and its application to construction.” Ph.D. thesis, Helsinki Univ. of Technology TKK, Helsinki, Finland.
Liberda, M., Ruwanpura, J., and Jergeas, G. (2003). “Construction productivity improvement: A study of human, management, and external issues.” Proc., Construction Research Congr., ASCE, Reston, Va.
Lu, W., Shen, L., and Yam, M. C. H. (2008). “Critical success factors for competitiveness of contractors: China study.” J. Constr. Eng. Manage., 134(12), 972–982.
Ott, R. L., and Longnecker, M. T. (2001). An introduction to statistical methods and data analysis, 5th Ed., Duxbury Press, Pacific Grove, CA
Pett, M. A., Lackey, N. R., and Sullivan, J. J. (2003). Making sense of factor analysis, Sage Publications, Thousand Oaks, CA.
Portas, J., and AbouRizk, S. (1997). “Neural network model for estimating construction productivity.” J. Constr. Eng. Manage., 123(4), 399–410.
Radosavljevic, M., and Horner, R. M. W. (2002). “The evidence of complex variability in construction labour productivity.” Constr. Manage. Econ., 20, 3–12.
Rilett, L. R. (1998). “Identifying component variability of end product specification tests.” J. Constr. Eng. Manage., 124(2), 133–138.
Rojas, M., and Aramvareekul, P. (2003). “Labor productivity drivers and opportunities in the construction industry.” J. Manage. Eng., 19(2), 78–82.
Somnez, R., and Rowlings, J. E. (1998). “Construction labor productivity modeling with neural networks.” J. Constr. Eng. Manage., 124(6), 498–504.
Spearman, C. (1927). The abilities of man, Macmillan, Oxford, UK.
Thomas, H. R., and Sakarcan, A. S. (1994). “Forecasting labor productivity using factor model.” J. Constr. Eng. Manage., 120(1), 228–239.
Thomas, H. R., and Yiakoumis, I. (1987). “Factor model of construction productivity.” J. Constr. Eng. Manage., 113(4), 623–639.
Thomas, H. R., Horman, M. J., Lemes de Souza, U. E., and Zavřski, I. (2002). “Reducing variability to improve performance as a lean construction principle.” J. Constr. Eng. Mgmt., 128(2), 144–154.
Tommelein, I. D., Riley, D. R., and Howell, G. A. (1999). “Parade game: Impact of work flow variability on trade performance.” J. Constr. Eng. Manage., 125(5), 304–310.
Trost, S. M., and Oberlender, G. D. (2003). “Predicting accuracy of early cost estimates using factor analysis and multivariate regression.” J. Constr. Eng. Manage., 129, 198–204.
Zayed, T. M., and Halpin, D. W. (2004). “Quantitative assessment for piles productivity factors.” J. Constr. Eng. Manage., 130(3), 405–414.
Zhang, X. (2006). “Factor analysis of public clients’ best-value objective in public—Privately partnered infrastructure projects.” J. Constr. Eng. Manage., 132(9), 956–965.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 137Issue 9September 2011
Pages: 663 - 677

History

Received: Jul 24, 2010
Accepted: Jan 4, 2011
Published online: Mar 14, 2011
Published in print: Sep 1, 2011

Permissions

Request permissions for this article.

Authors

Affiliations

Brad W. Wambeke, M.ASCE [email protected]
Lieutenant Colonel, U.S. Army, Ph.D. student, Dept. of Civil, Construction, and Environmental Engineering, North Carolina State Univ., Raleigh, NC 27695-7908; Academy Professor, Dept. of Civil and Mechanical Engineering, United States Military Academy, West Point, NY 10996. E-mail: [email protected]
Derr Professor, Industrial Engineering, Texas Tech Univ., Lubbock, TX 79409; formerly, Associate Professor, Fitts Dept. of Industrial and Systems Engineering, North Carolina State Univ., Raleigh, NC 27695-7908. Email: [email protected]
Min Liu, A.M.ASCE [email protected]
Assistant Professor, Dept. of Civil, Construction, and Environmental Engineering, North Carolina State Univ., Raleigh, NC 27695-7908 (corresponding author). E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share