Simulation-Based Schedule Estimation Model for ACS-Based Core Wall Construction of High-Rise Building

Publication: Journal of Construction Engineering and Management
Volume 137, Issue 6

Abstract

Many existing studies about construction schedule management focus on the planning phase of a project, particularly on schedule estimation based on the labor resources involved in the project. However, equipment resources, which are another crucial factor in the productivity of a construction project, have not been considered in existing research. Therefore, this study aimed to develop a schedule estimation model considering both labor and equipment resources. For the purpose of this study, core wall construction was selected because it is a very important construction activity in terms of schedule estimation for high-rise building construction. To develop a schedule estimation model for core wall construction, an in-depth case study was conducted. On the basis of the results of the case study, a simulation model was developed using the CYCLONE method. Finally, by using the results of the simulation, a schedule estimation model for core wall construction was developed by conducting multiple-regression analysis. By using the developed model, a project manager can easily, quickly, and accurately perform schedule estimation when there are problems that may cause construction schedule delays during the construction phase.

Get full access to this article

View all available purchase options and get full access to this article.

Acknowledgments

This work was supported by the Yonsei University Research Fund of 2009.

References

AbouRizk, S., Halpin, D., and Wilson, J. (1994). “Fitting beta distributions based on sample data.” J. Constr. Eng. Manage., 120(2), 288–305.
Ashley, D. B. (1980). “Simulation of repetitive-unit construction.” J. Constr. Div., 106(2), 185–194.
Back, W., Boles, W., and Fry, G. (2000). “Defining triangular probability distributions from historical cost data.” J. Constr. Eng. Manage., 126(1), 29–37.
Birrell, G. S. (1980). “Construction planning—Beyond the critical path.” J. Constr. Div., 106(3), 389–407.
Eldin, N. N., and Senouci, A. B. (1994). “Scheduling and control of linear projects.” Canadian J. Civ. Eng., 21(2), 219–230.
El-Rayes, K. (2001). “Object-oriented model for repetitive construction scheduling.” J. Constr. Eng. Manage., 127(3), 199–205.
El-Rayes, K., and Moselhi, O. (1998). “Resource-driven scheduling of repetitive activities on construction projects.” Constr. Manage. Econ., 16(4), 433–446.
Hair, J., Black, W., Babin, B., Anderson, R., and Tatham, R. (2006). Multivariate data analysis, 6th Ed., Pearson Education, Upper Saddle River, NJ, 169–269.
Halpin, D. W., and Riggs, L. S. (1992). Planning and analysis of construction operations, Wiley, New York.
Han, S., Hong, T., and Lee, S. (2008). “Production prediction of conventional and GPS-based earthmoving systems using a simulation methodology and multiple regression analysis.” Canadian J. Civ. Eng., 35(6), 574–587.
Han, S., Kim, D., and Kim, H. (2007). “Predicting profit performance for selecting candidate international construction project.” J. Constr. Eng. Manage., 133(6), 425–436.
Han, S., Lee, S., Hong, T., and Chang, H. (2006). “Simulation analysis of productivity variation by GPS implementation in earthmoving operations.” Canadian J. Civ. Eng., 33(9), 1105–1114.
Hong, T., and Hastak, M. (2007). “Simulation study on construction process of FRP bridge deck panels.” Autom. Constr., 16(5), 620–631.
Hyari, K., and El-Rayes, K. (2006). “Optimal planning and scheduling for repetitive construction projects.” J. Manage. Eng., 22(1), 11–19.
Kavanagh, D. P. (1985). “SIREN: A repetitive construction simulation model.” J. Constr. Eng. Manage., 111(3), 308–323.
Kim, T., Jin, L., Shin, Y., Cho, S., and Kang, K. (2007). “An analysis of application by formwork in concrete structural frame work for tall building in Korea.” Annual Conf. on the Korea Institute of Building Construction, Korea Institute of Building Construction, Seoul, Korea, 387–391.
Koo, S. H. (2003). “A decision-making process to select system form for core wall in high-rise building construction.” M.S. thesis, Hanyang Univ., Seoul, Korea.
Kook, K. H. (2004). “Study on constructability improvement core wall construction method of the high-rise building structure.” M.S. thesis, Hanyang Univ., Seoul, Korea.
Ling, S. Y., Pasha, M. F., Doun, C. D., Phoon, C. K., and Liaw, C. Y. (2001). “Determination of optimal and stable prediction parameters values in chaotic time series.” World Water Congress 221, ASCE, Reston, VA.
Liou, F., and Huang, C. (2008). “Automated approach to negotiations of BOT contracts with the consideration of project risk.” J. Constr. Eng. Manage., 134(1), 18–24.
Luo, R. Y., and Najafi, M. (2007). “Productivity study of microtunneling pipe installation using simulation.” J. Infrastruct. Syst., 13(3), 247–260.
Moder, J. J., Philips, C. R., and Davis, E. W. (1983). Project management with CPM, PERT and Precedence diagramming, 3rd Ed., Van Nostrand Reinhold, New York.
Moselhi, O., and El-Rayes, K. (1993). “Scheduling of repetitive projects with cost optimization.” J. Constr. Eng. Manage., 119(4), 681–697.
Nasir, D., McCabe, B., and Hartono, L. (2003). “Evaluating risk in construction-schedule model: Construction schedule risk model.” J. Constr. Eng. Manage., 129(5), 518–527.
Okmen, O., and Oztas, A. (2008). “Construction project network evaluation with correlated schedule risk analysis model.” J. Constr. Eng. Manage., 134(1), 49–63.
Reda, R. M. (1990). “RPM: Repetitive project modeling.” J. Constr. Eng. Manage., 116(2), 316–330.
Russell, A. D., and Caselton, W. F. (1988). “Extensions to linear scheduling optimization.” J. Constr. Eng. Manage., 114(1), 36–52.
Selinger, S. (1980). “Construction planning for linear projects.” J. Constr. Div., 106(2), 195–205.
Vanhoucke, M. (2006). “Work continuity constraints in project scheduling.” J. Constr. Eng. Manage., 132(1), 14–25.
Yamin, R. A., and Harmelink, D. J. (2001). “Comparison of linear scheduling model and critical path method.” J. Constr. Eng. Manage., 127(5), 374–381.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 137Issue 6June 2011
Pages: 393 - 402

History

Received: Aug 16, 2009
Accepted: Oct 6, 2010
Published online: May 16, 2011
Published in print: Jun 1, 2011

Permissions

Request permissions for this article.

Authors

Affiliations

Taehoon Hong, A.M.ASCE [email protected]
Assistant Professor, Dept. of Architectural Engineering, Yonsei Univ., Seoul, Korea (corresponding author). E-mail: [email protected]
Kyuman Cho
Visiting Scholar, Div. of Construction Engineering and Management, Purdue Univ., West Lafayette, IN.
Changtaek Hyun, M.ASCE
Professor, Dept. of Architectural Engineering, Univ. of Seoul, Seoul, Korea.
Seungwoo Han
Associate Professor, School of Architecture, Inha Univ., Incheon, Korea.

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share