Visualization of Work Flow to Support Lean Construction
Publication: Journal of Construction Engineering and Management
Volume 135, Issue 12
Abstract
Implementation of advanced production management techniques, such as lean construction concepts like filtering of work packages to stabilize work flows, pull flow of teams and materials, and in-process quality control, demands effective and timely flows of information both to and from the workface. The key requirement—making the process state transparent to all participants—is more difficult to achieve in construction than in manufacturing, because work crews move continuously within a physical environment that is itself changing. Novel computer-aided visualization tools can fulfill the needs that simpler tools, such as Kanban cards, fulfill in manufacturing. Two prototypes with user interfaces designed to facilitate process flow have been devised and implemented within the context of building information modeling (BIM) software systems. They demonstrate aspects of the synergy between BIM and lean construction. Given the dynamic and dispersed physical environments and the fractured contracting arrangements typical of construction, BIM-based visualization interfaces are important tools for providing process transparency.
Get full access to this article
View all available purchase options and get full access to this article.
Acknowledgments
The writers gratefully acknowledge the support of ECE Projektmanagement G.m.b.H. and Co. KG and Danya Cebus Ltd., who collaborated with and/or funded aspects of the reported research.
References
Akinci, B., Fischer, M., and Kunz, J. (2002). “Automated generation of work spaces required by construction activities.” J. Constr. Eng. Manage., 128(4), 306–315.
Aspin, R. (2007). “Supporting collaboration, in colocated 3D visualization, through the use of remote personal interfaces.” J. Comput. Civ. Eng., 21(6), 393–401.
Ballard, G. (2000). “Lean project delivery system.” ⟨http://www.leanconstruction.org/⟩ (Sept. 25, 2009).
Ballard, G. (2008). “The lean project delivery system: An update.” Lean Construction J., 2008, 1–19.
Behzadan, A. H., and Kamat, V. R. (2007). “Georeferenced registration of construction graphics in mobile outdoor augmented reality.” J. Comput. Civ. Eng., 21(4), 247–258.
Berg, K. (2005). “Safety planning for projects.” Proc., Environmental, Safety, and Health Conf., Society for Technical Communication, Seattle.
Chantawit, D., Hadikusumo, B. H. W., Charoenngam, C., and Rowlinson, S. (2005). “4DCAD-Safety: Visualizing project scheduling and safety planning.” Constr. Innovation, 5(2), 99–114.
Chau, K. W., Anson, M., and Zhang, J. P. (2004). “Four-dimensional visualization of construction scheduling and site utilization.” J. Constr. Eng. Manage., 130(4), 598–606.
Choo, H. J., Tommelein, I. D., Ballard, G., and Zabelle, T. R. (1999). “WorkPlan: Constraint-based database for work package scheduling.” J. Constr. Eng. Manage., 125(3), 151–160.
ConstructSim. (2009). “Planning, sequencing, execution, and monitoring of construction activities” Bentley Systems Inc., ⟨http://www.bentley.com/en-US/Products/ConstructSim/⟩ (Sept. 25, 2009).
Eastman, C. M., Teicholz, P., Sacks, R., and Liston, K. (2008). BIM handbook: A guide to building information modeling for owners, managers, architects, engineers, contractors, and fabricators, Wiley, New York.
Fard, M. G., and Pena-Mora, F. (2007). “Application of visualization techniques for construction progress monitoring.” Computing in civil engineering 2007, L. Soibelman and B. Akinci, eds., ASCE, Reston, Va., 27.
Formoso, C. T., Santos, A. D., and Powell, J. A. (2002). “An exploratory study on the applicability of process transparency in construction sites.” J. Constr. Res., 3(1), 35–54.
Greif, M. (1991). The visual factory: Building participation through shared information, L. Lockwood, translator, Productivity, Portland, Ore.
Hopp, W. J., and Spearman, M. L. (1996). Factory physics, IRWIN, Chicago.
ILO. (2003). “Safety in numbers.” Rep. No. 061, International Labor Organization, Geneva.
Jongeling, R., Kim, J., Fischer, M., Mourgues, C., and Olofsson, T. (2008). “Quantitative analysis of workflow, temporary structure usage, and productivity using 4D models.” Autom. Constr., 17(6), 780–791.
Kamat, V. R., and Martinez, J. C. (2001). “Visualizing simulated construction operations in 3D.” J. Comput. Civ. Eng., 15(4), 329–337.
Kang, J. H., Anderson, S. D., and Clayton, M. J. (2007). “Empirical study on the merit of web-based 4D visualization in collaborative construction planning and scheduling.” J. Constr. Eng. Manage., 133(6), 447–461.
Khanzode, A., Fischer, M., and Reed, D. (2005). “Case study of the implementation of the lean project delivery system (LPDS) using virtual building technologies on a large healthcare project.” Proc., 13th Conf. of the Int. Group for Lean Construction, R. Kenley, ed., UNSW, Sydney, Australia, 153–160.
Koerckel, A., and Ballard, G. (2005). “Return on investment in construction innovation—A lean construction case study.” Proc., 13th Annual Conf. on Lean Construction, R. Kenley, ed., UNSW, Sydney, Australia.
Koskela, L. (1992). “Application of the new production philosophy to construction.” Technical Rep. No. 72, Center for Integrated Facility Engineering, Dept. of Civil Engineering, Stanford Univ., Stanford, Calif.
Koskela, L. (2000). “An exploration towards a production theory and its application to construction.” D.Tech. thesis, Helsinki Univ. of Technology, Espoo, Finland, ⟨http://www.vtt.fi/inf/pdf/publications/2000/P408.pdf⟩ (Sept. 25, 2009).
Liker, J. E. (2003). The Toyota way, McGraw-Hill, New York.
McKinney, K., and Fischer, M. (1998). “Generating, evaluating, and visualizing construction schedules with CAD tools.” Autom. Constr., 7(6), 433–447.
Navon, R., and Sacks, R. (2007). “Assessing research issues in automated project performance control (APPC).” Autom. Constr., 16(4), 474–484.
Pereira, P. (1998). “Just in time and autonomation: Applying TPS in vertical housing.” Proc., 6th Annual LCI Congress, G. Ballard and G. Howell, eds., Lean Construction Institute, Park City, Utah.
Retik, A., and Shapira, A. (1999). “VR-based planning of construction site activities.” Autom. Constr., 8(6), 671–680.
Sacks, R., and Derin, Z. (2006). “WORKMANAGER—An online interface for lean flow control in apartment building construction.” Proc., Joint Int. Conf. on Computing and Decision Making in Civil and Building Engineering, H. Rivard and E. Miresco, eds., ASCE, Reston, Va., 1176–1185.
Sacks, R., and Goldin, M. (2007). “Lean management model for construction of high-rise apartment buildings.” J. Constr. Eng. Manage., 133(5), 374–384.
Sacks, R., Goldin, M., and Derin, Z. (2005). “Pull-driven construction of high-rise apartment buildings.” Proc., 13th Conf. of the Int. Group for Lean Construction, R. Kenley, ed., UNSW, Sydney, Australia, 217–226.
Sacks, R., Rozenfeld, O., and Rosenfeld, Y. (2009). “Spatial and temporal exposure to safety hazards in construction.” J. Constr. Eng. Manage., 135(8), 726–736.
Santos, A. D. (1999). “Application of production management flow principles in construction sites,” Ph.D. thesis, Univ. of Salford, Salford, U.K.
Strategic Project Solutions (SPS). (2007). “Strategic projectsolutions.” Strategic Project Solutions, Inc., ⟨http://www.strategicprojectsolutions.com/⟩ (Sept. 25, 2009).
Synchro. (2007). “Synchro.” Synchro Ltd., ⟨www.synchroltd.com/⟩ (Sept. 25, 2009).
Tang, S. L., Lee, H. K., and Wong, K. (1997). “Safety cost optimization of building projects in Hong Kong.” Constr. Manage. Econom., 15(2), 177–186.
VICO. (2007). “Virtual construction 2007.” Vico Software, Inc., ⟨http://www.vicosoftware.com/⟩ (Sept. 25, 2009).
Womack, J. P., and Jones, D. T. (2003). Lean thinking: Banish waste and create wealth in your corporation, Simon and Schuster, New York.
Information & Authors
Information
Published In
Copyright
© 2009 ASCE.
History
Received: Aug 15, 2008
Accepted: Jun 2, 2009
Published online: Jun 4, 2009
Published in print: Dec 2009
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.