A nationwide survey of state Departments of Transportation (DOTs) found that 15 states are using design-build (DB) to procure highway construction projects. Analysis of their methods yielded three different systems to advertise and award DB highway projects. The methods are low-bid DB, adjusted score DB, and best value DB. The paper details the three methods and compares their strengths and weaknesses. It is concluded that each method is a valid system for procuring highway construction projects and that each method can be matched with certain project characteristics to optimize the project delivery method with respect to the salient aspects of the project.
Get full access to this article
View all available purchase options and get full access to this article.
References
1.
“Colorado Department of Transportation design-build guidelines.” (1997). Draft issued February 1, 1997, for review and comment, State government, Denver, Colo.
2.
“Design Build Procurement and Administration.” (1996). Agenda Request, Procedure No. 625-020-010-a, Executive Committee, Dept. of Transportation, Tallahassee, Fla.
3.
Engineer Regulation 1180-1-173, Design-build Instructions (DBI) for Military Construction. (1994). U.S. Army Corps of Engineers, Washington, D.C.
4.
Ellis, R. D., Herbsman, Z., and Kumar, A. (1991). “Evaluation of the FDOT design/build program.” Final Rep., No. 99700-7435-010, submitted to the Florida Department of Transportation; Dept. of Civil Engineering, University of Florida, Gainesville, Fla.
5.
Federal Acquisition Regulation (FAR). (1996). U.S. Government Printing Office, Washington, D.C.
6.
Federal Highway Administration (FWHA). (1996). “Design-build: FWHA's role in the design-build program under special experimental projects No. 14 (SEP-14).” Washington, D.C.
7.
Re: Authority of a Commissioners Court to award “design/build” contracts for construction of public buildings on the basis of competitive bids, and related questions. (1990). Attorney General of Texas, TPO, Austin, Tex.
8.
“Request for design-build proposals: Phoenix-Tucson Highway (Interstate 10), (Cortaro Road Interchange).” (1997). REP 010 PM 246 H415601C, NH-10-4(160), Contracts and Specifications Sect., State government, Phoenix, Ariz.
9.
Survey of state engineering and architecture boards on design-build (combined design and construction contracting). (1997). Design-Build Institute of America (DBIA), Washington, D.C., 6–35.
10.
“The consolidated modified turnkey project procedure.” (1995). Attachment to letter dated October 11, 1995, Department of Transportation, Commonwealth of Pennsylvania, Harrisburg, Pa.
11.
“Two phase design build selection.” (1997). Federal Register, 62(1), 62 FR 271.
Information & Authors
Information
Published In
History
Received: Apr 21, 1998
Published online: Nov 1, 1999
Published in print: Nov 1999
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.