Measuring the Impact of Rework on Construction Cost Performance
Publication: Journal of Construction Engineering and Management
Volume 135, Issue 3
Abstract
Rework continues to affect both cost and schedule performance throughout the construction industry. The direct costs alone often tally to 5% of the total construction costs. Using the data obtained from 359 construction projects in the Construction Industry Institute database, this paper assesses the impacts of rework on construction cost performance for projects in various categories. In addition, it identifies the sources of this rework, permitting further analyses and the development of rework reduction initiatives. The results of this study establish that the impacts of rework differ according to project characteristics and that the sources of rework having the greatest impact are not significantly different among project categories. By recognizing the impacts of rework and its sources, the construction industry can reduce rework and ultimately improve project cost performance.
Get full access to this article
View all available purchase options and get full access to this article.
References
Abdul-Rahman, H. (1995). “The cost of non-conformance during a highway project: A case study.” Constr. Manage. Econom., 13(1), 23–32.
Ashford, J. L. (1992). The management of quality in construction, E & F Spon, London.
Barber, P., Graves, A., Hall, M., Sheath, D., and Tomkins, C. (2000). “Quality failure costs in civil engineering projects.” Int. J. Qual. Reliab. Manage., 17(4/5), 479–492.
Burati, J. L., Farrington, J. J., and Ledbetter, W. B. (1992). “Causes of quality deviations in design and construction.” J. Constr. Eng. Manage., 118(1), 34–49.
Bureau of Economic Analysis (BEA). (2006). “Gross domestic product by industry in current dollars.” ⟨http://bea.gov/bea/dn2/gdpbyind_data.htm⟩ (Oct. 20, 2006).
Construction Industry Development Agency and Masters Builders Australia (CIDA). (1995). Measuring up or muddling through: Best practice in the Australian non-residential construction industry, Sydney, Australia, 59–63.
Construction Industry Institute (CII). (1989). “Costs of quality deviations in design and construction.” RS 10-1 (Jan.), The Univ. of Texas at Austin, Austin, Tex.
Construction Industry Institute (CII). (2001). “The field rework index: Early warning for field rework and cost growth.” RS 153-1 (May), The Univ. of Texas at Austin, Austin, Tex.
Construction Industry Institute (CII). (2002). “CII best practices guide.” IR 166-3 (July), The Univ. of Texas at Austin, Austin, Tex.
Construction Industry Institute (CII). (2003). “Benchmarking and metrics value of best practices report.” BMM 2003-4, CII, The Univ. of Texas at Austin, Austin, Tex.
Construction Industry Institute (CII). (2005). “Making zero rework A reality.” RS 203-1 (Nov.), The Univ. of Texas at Austin, Austin, Tex.
Davis, K., Ledbetter, W. B., and Burati, J. L. (1989). “Measuring design and construction quality costs.” J. Constr. Eng. Manage., 115(3), 385–400.
Fayek, A. R., Dissanayake, M., and Campero, O. (2003). “Measuring and classifying construction field rework: A pilot study.” Research Rep. (May), Construction Owners Association of Alberta (COAA), The University of Alberta, Edmonton, Al., Canada.
Josephson, P. E., and Hammarlund, Y. (1999). “The causes and costs of defects in construction: A study of seven building projects.” Autom. Constr., 8(6), 681–687.
Love, P. E. D. (2002a). “Auditing the indirect consequences of rework in construction: A case based approach.” Manage. Audit. J., 17(3), 138–46.
Love, P. E. D. (2002b). “Influence of project type and procurement method on rework costs in building construction projects.” J. Constr. Eng. Manage., 128(1), 18–29.
Love, P. E. D., and Edwards, D. (2004). “Forensic project management: The underlying causes of rework in construction projects.” Civ. Eng. Environ. Syst., 12(3), 207–228.
Love, P. E. D., Irani, Z., and Edwards, D. (2003). “Learning to reduce rework in projects: Analysis of firms learning and quality practices.” Proj. Manage. J., 34(3), 13–25.
Love, P. E. D., and Li, H. (2000). “Quantifying the causes and costs of rework in construction.” Constr. Manage. Econom., 18(4), 479–490.
Love, P. E. D., Li, H., and Mandal, P. (1999a). “Rework: A symptom of a dysfunctional supply-chain.” Eur. J. Purch. Supply Manage., 5(1), 1–11.
Love, P. E. D., Mandal, P., and Li, H. (1999b). “Determining the casual structure of rework influences in construction.” Constr. Manage. Econom., 17(4), 505–517.
Love, P. E. D., Mandal, P., and Smith, J. (2000). “Modeling the dynamics of design error induced rework in construction.” Constr. Manage. Econom., 18(5), 567–574.
O’Conner, J. T., and Tucker, R. L. (1986). “Industrial project constructibility improvement.” J. Constr. Eng. Manage., 112(1), 69–82.
Information & Authors
Information
Published In
Copyright
© 2009 ASCE.
History
Received: Apr 2, 2007
Accepted: Sep 23, 2008
Published online: Mar 1, 2009
Published in print: Mar 2009
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.