Linear versus Network Scheduling: A Critical Path Comparison
Publication: Journal of Construction Engineering and Management
Volume 133, Issue 7
Abstract
Linear scheduling methods provide an alternative way of scheduling repetitive projects, to the commonly used network methods. Critical path identification is a major attribute for both methods; therefore, it is very important for practitioners to understand the function of the two methods in this area. The present paper compares the critical path of the recently developed Kallantzis-Lambropoulos repetitive project model against the network scheduling critical path method (CPM), aiming at delving into and pointing out the differences and similarities between them. Initially, the rules for transforming the linear project into an equivalent CPM network are proposed. Then, the rules are applied on a sample linear project. Due to the additional constraint for maintaining resource continuity that the linear method takes into account, the critical paths vary. The constraint is subsequently removed from selected activities and comparison is repeated; the critical paths then coincide. In order to validate the findings and ensure impartiality of results, a random linear project generator is developed. A group of twenty-five random linear projects and their equivalent networks is produced. Their critical paths are analyzed, compared and classified. Conclusions support that the proposed comparison could be beneficial to users of linear scheduling methods, while the random project generator can serve other related research.
Get full access to this article
View all available purchase options and get full access to this article.
References
Ammar, M. A., and Elbeltagi, E. (2001). “Algorithm for determining controlling path considering resource continuity.” J. Comput. Civ. Eng., 15(4), 292–298.
Birrell, G. S. (1980). “Construction planning—Beyond the critical path.” J. Constr. Div., 106(3), 389–407.
El-Rayes, K., and Moselhi, O. (1998). “Resource-driven scheduling of repetitive activities on construction projects.” J. Constr. Management & Economics, 16(4), 433–466.
El-Rayes, K., and Moselhi, O. (2001). “Optimizing resource utilization for repetitive construction projects.” J. Constr. Eng. Manage., 127(1), 18–27.
Harmelink, D. J., and Rowings, E. J. (1998). “Linear scheduling model: Development of controlling activity path.” J. Constr. Eng. Manage., 124(4), 263–268.
Harris, R. B., and Ioannou, P. G. (1998). “Scheduling projects with repeating activities.” J. Constr. Eng. Manage., 124(4), 269–278.
Hegazy, T., and Wassef (2001). “Cost optimization in projects with repetitive nonserial activities.” J. Constr. Eng. Manage., 127(3), 183–191.
Ioannou, P. G., and Yang, I.-T. (2004). “Discussion of ‘Comparison of linear scheduling model and repetitive scheduling method.’ ” J. Compos. Constr., 8(3), 461–463.
Kallantzis, A., and Lambropoulos, S. (2004a). “Linear scheduling and critical path determination using minimum and maximum constraints.” Eng., Constr., Archit. Manage., 11(3), 211–222.
Kallantzis, A., and Lambropoulos, S. (2004b). “Discussion of ‘Comparison of linear scheduling model and repetitive scheduling model.’” J. Compos. Constr., 8(3), 463–467.
Kallantzis, A., and Lambropoulos, S. (2005). “Linear project acceleration without increasing production rates.” Tech. Chron. Sci. J. TCG, I, 25(1), 53–63.
Mattila, K. G., and Park, A. (2003). “Comparison of linear scheduling model and repetitive scheduling method.” J. Constr. Eng. Manage., 129(1), 56–64.
Reda, R. M. (1990). “RPM: repetitive project modeling.” J. Constr. Eng. Manage., 116(2), 316–330.
Yamin, R. A., and Harmelink, D. J. (2001). “Comparison of linear scheduling model (LSM) and critical path method (CPM).” J. Constr. Eng. Manage., 127(5), 374–381.
Yang, I., and Ioannou, P. G. (2004). “Scheduling system with focus on practical concerns in repetitive projects.” Construction Management and Economics, 22(6), 619–630.
Information & Authors
Information
Published In
Copyright
© 2007 ASCE.
History
Received: Jul 13, 2005
Accepted: Dec 19, 2006
Published online: Jul 1, 2007
Published in print: Jul 2007
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.