Probability of Project Completion Using Stochastic Project Scheduling Simulation

Publication: Journal of Construction Engineering and Management
Volume 131, Issue 3

Abstract

This paper introduces a software, Stochastic Project Scheduling Simulation (SPSS), developed to measure the probability to complete a project in a certain time specified by the user. To deliver a project by a completion date committed to in a contract, a number of activities need to be carried out. The time that an entire project takes to complete and the activities that determine total project duration are always questionable because of the randomness and stochastic nature of the activities’ durations. Predicting a project completion probability is valuable, particularly at the time of bidding. The SPSS finds the longest path in a network and runs the network a number of times specified by the user and calculates the stochastic probability to complete the project in the specified time. The SPSS can be used by a contractor: (1) to predict the probability to deliver the project in a given time frame and (2) to assess its capabilities to meet the contractual requirement before bidding. The SPSS can also be used by a construction owner to quantify and analyze the risks involved in the schedule. The benefits of the tool to researchers are: (1) to solve program evaluation and review technique problems; (2) to complement Monte Carlo simulation by applying the concept of project network modeling and scheduling with probabilistic and stochastic activities via a web based Java Simulation which is operateable over the Internet, and (3) to open a way to compare a project network having different distribution functions.

Get full access to this article

View all available purchase options and get full access to this article.

References

AbouRizk, S. M., and Halpin, D. W. (1992). “Statistical properties of construction duration data.” J. Constr. Eng. Manage., 118(3), 525–544.
Ahuja, N. T. H., and Nandakumar, V. (1985). “Simulation model to forecast project completion time.” J. Constr. Eng. Manage., 111(4), 325–342.
Ang, A. H-S., and Tang, W. H. (1975). “Probability concepts in engineering planning and design.” Analytical models of random phenomena, Vol. 1, Wiley, New York, 80–169.
Barrie, D. S., and Paulson, B. C. (1992). “Professional construction management including CM, design-contract and general contracting.” Planning and controlling of operations and resources, 3rd Ed., McGraw–Hill, New York, 252–303.
Chang, D. (1987). “RESQUE.” PhD thesis, Univ. of Michigan, Ann Arbor, Mich.
Cliff, R. T. (2001). “Spreadsheet modeling and decision analysis: Apractical introduction to management science.” Introduction to simulation using Crystal Ball, 3rd Ed., South-Western College Publishers, Cincinnati.
Crandall, C. K. (1977). “Analysis of schedule simulations.” J. Constr. Div., Am. Soc. Civ. Eng., 103(3), 387–394.
Fataneh, T.-D. (2002). “Lecture note: Designing with uncertain activity.” ⟨http://som.umflint.edu/fataneh/bus313/Lecture%20Notes/pert.ppt⟩ (Feb. 5, 2003).
Fente, J., Knutson, K., and Schexnayder, C. (1999). “Defining a Beta distribution function for construction simulation.” Proc., 1999 Winter Simulation Conf., P. A. Farrington, H. B. Nembhard, D. T. Sturrock, and G. W. Evans, eds., IEEE, Piscataway, N.J., 1010–1015.
Hajjar, D., and AbouRizk, S. M. (1999). “Simphony: An environment for building special purpose construction simulation tools.” Proc., 1999 Winter Simulation Conf., IEEE, Piscataway, N.J., 998–1006.
Halpin, D. W. (1977). “CYCLONE—A method for modeling job site processes.” J. Constr. Div., Am. Soc. Civ. Eng., 103(3), 489–499.
Hillier, F. S., and Lieberman, G. J. (1986). ”Introduction to operations research.” Project management with PERT/CPM: Simulation, 4th Ed., Holden-Day, Oakland, Calif., 468–527, 1084–1153.
Hoyle, D. (1998). ISO 9000 quality systems handbook, 3rd Ed., Utterworth Einemann Ltd, Boston.
Huang, R., Grigoriadis, A. M., and Halpin, D. W. (1994). “Simulation of cable-stayed bridges using DISCO.” Proc., 1994 Winter Simulation Conf., IEEE, Piscataway, N.J., 1130–1136.
Ioannou, P. G. (1989). UM_CYCLONE user’s guide, Dept. of Civil Engineering, The University of Michigan Press, Ann Arbor, Mich.
Khisty, C. J., and Mohammadi, J. (2001). “Fundamentals of system engineering with economics, probability, and statistics.” Principles of probability, Prentice Hall, Upper Saddle River, N.J., 131–150, 294–313.
MacCrimmon, K. R., and Ryavec, C. A. (1962). “An analytical study of the PERT assumptions. Memorandum.” RM-3408-PR, Rand Corp., Santa Monica, Calif.
Martinez, J. C., and Ioannou, P. G. (1999). “General purpose systems for effective construction simulation.” J. Constr. Eng. Manage., 125(4), 265–276.
Paulson, B. C. (1978). “Interactive graphics for simulating construction operations.” J. Constr. Div., Am. Soc. Civ. Eng., 104(1), 69–76.
Sawhney, A. (1997). “Petri Net based simulation of construction schedules.” Proc., 1997 Winter Simulation Conf., S. Andradottir, K. J. Healy, D. H Withers, and B. L. Nelson, eds., Atlanta, 1111–1118.
Shi, J. (1999). “Activity-based construction (ABC) modeling and simulation method.” J. Constr. Eng. Manage., 125(5), 354–360.
Suhanic, G. (1980). “Change orders impact on construction cost and schedule.” Proc., Transactions of the American Association of Cost Engineers, 24th Annual Meeting, Washington, D.C.
Teicholz, P. (1963). “A simulation approach to the selection of construction equipment.” Technical Rep. No.26, The Construction Institute, Stanford Univ., Stanford, Calif.
Tommelein, I. D., Carr, R. I., and Odeh, A. M. (1994). “Knowledge-based assembly of simulation networks using construction designs, plans, and methods.” Proc., 1994 Winter Simulation Conf., IEEE, Piscataway, N.J., 1145–1152.
Van Slyke, M. R. (1963). “Monte Carlo methods and the PERT problem.” Oper. Res., 11, 839–860.
Winston, W. L., and Albright, C. S. (1997). Practical management science: Spreadsheet modeling and applications, Duxbury, Belmont, Calif.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 131Issue 3March 2005
Pages: 310 - 318

History

Received: Sep 11, 2003
Accepted: May 11, 2004
Published online: Mar 1, 2005
Published in print: Mar 2005

Permissions

Request permissions for this article.

Authors

Affiliations

Dong-Eun Lee [email protected]
PhD Candidate, Construction Engineering and Management Program, Dept. of Civil and Architectural Engineering, Illinois Institute of Technology, 3201 S. Dearborn St., Chicago, IL 60616-3793. E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share