Robustness Analysis of Total Project Cost and Schedule Delay and Overrun Indicators of Heavy Industrial Projects
Publication: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 15, Issue 2
Abstract
Barriers such as cost overruns and schedule delays make it challenging to achieve successful project outcomes. Their early detection, however, allows mitigation strategies to be implemented before too much delay has occurred; therefore, the objective of this study was to identify the total project cost and schedule overrun indicators and evaluate their reliability for large-scale heavy industrial projects. To accomplish the study’s goals, a structured survey was developed and disseminated to construction industry professionals to gain their input on the most important cost overrun indicators (COIs) and schedule overrun indicators (SOIs). The collected data were analyzed by applying various statistical tests, and a list of the significant COIs and SOIs was compiled utilizing all-possible regression. The extreme bound analysis (EBA) method was adopted to determine the robustness of the identified indicators. The results revealed the nine COIs are design phase contract type, change management approach, degree of internal stakeholders’ alignment, delay in the delivery of long-term facility machinery, proportion of artisanal labor sourced locally, proportion of design completion before the budget approval of the project, preparing for startup deployment, agreement including delayed completion charges, and number of design organizations; two of these were fragile indicators. The results also demonstrated the nine influential indicators for total schedule overrun are implementation of front-end planning, efficacy of the change management process, project population density, average number of project management (PM) team participants in the procurement phase, prior designer and contractor partnership, delay in the delivery of long-term facility machinery, average size of PM team design phase, efficacy of designers group interaction, and number of subcontracting firms; six of these were robustly related to the model. The findings of this study can help construction project decision makers focus on the most reliable indicators and reduce the number of revisions required throughout the execution of a project.
Get full access to this article
View all available purchase options and get full access to this article.
Data Availability Statement
All data generated or analyzed during the study are available from the corresponding author by request.
References
Works Cited
Abbas, M. I. 2006. Causes and effects of delays in Aceh construction industry. Johor, Malaysia: Universiti Teknologi Malaysia.
Abd El-Razek, M. E., H. A. Bassoioni, and A. M. Mobarak. 2008. “Causes of delay in building construction projects in Egypt.” J. Constr. Eng. Manage. 134 (11): 831–841. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:11(831).
Abdou, S. M., K. Yong, and M. Othman. 2016. “Project complexity influence on project management performance—The Malaysian perspective.” In Vol. 66 of Proc., MATEC Web Conf., 00065. Les Ulis, France: EDP Sciences.
Al-Tmeemy, S. M. H. M., H. Abdul-Rahman, and Z. Harun. 2011. “Future criteria for success of building projects in Malaysia.” Int. J. Project Manage. 29 (3): 337–348. https://doi.org/10.1016/j.ijproman.2010.03.003.
Anderson, S., C. Quiroga, J. Overman, K. Choi, J. Sahu, S. Kermanshachi, P. Goodrum, T. Taylor, and Y. Li. 2016. Effective project scoping practices to improve on-time and on-budget delivery of highway projects. Washington, DC: Transportation Research Board.
Assaf, S. A., and S. Al-Hejji. 2006. “Causes of delay in large construction projects.” Int. J. Project Manage. 24 (5): 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010.
Azhar, N. F. 2008. “Cost overrun factors in the construction industry in Pakistan.” In Proc., 1st Int. Conf. on Construction in Developing Countries: Advancing and Integrating Construction Education. Karachi, Pakistan: Research and Practice.
Bubshait, A. A., and Y. A. Al-Juwait. 2002. “Factors contributing to construction costs in Saudi Arabia.” Cost Eng. 44 (5): 30–33.
Cantarelli, C., B. Van Wee, E. Molin, and E. Flyvbjerg. 2012. “Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases.” Transp. Policy 22 (4): 49–56. https://doi.org/10.1016/j.tranpol.2012.04.001.
Datta, B. 2002. “Management of infrastructure projects in urban local bodies: Case study of Kanpur development authority.” India infrastructure report, 207–211. Mumbai, India: IDFC Institute.
Flyvbjerg, B., M. K. S. Holm, and S. L. Buhl. 2002. “Cost underestimation in public works projects: Error or lie?” J. Am. Plann. Assoc. 68 (3): 279–295. https://doi.org/10.1080/01944360208976273.
Ghribi, S., P. A. Hudon, and B. Mazouz. 2019. “Risk factors in IT public–private partnership projects.” Public Works Manage. Policy 24 (4): 321–343. https://doi.org/10.1177/1087724X18823009.
Habibi, M., S. Kermanshachi, and E. Safapour. 2018. “Engineering, procurement, and construction cost and schedule performance leading indicators: State-of-the-art review.” In Proc., Construction Research Congress. Reston, VA: ASCE.
Imran, S. M. J. I., M. S. Nawaz, S. H. Siddiqui, and M. Kashif. 2019. “Does project teamwork matter? Investigating the relationship between transformational leadership and project success.” J. Manage. Sci. 6 (1): 79–95. https://doi.org/10.20547/jms.2014.1906106.
Iyer, K. C., N. B. Chaphalkar, and G. A. Joshi. 2008. “Understanding time delay disputes in construction contracts.” Int. J. Project Manage. 26 (5): 174–184. https://doi.org/10.1016/j.ijproman.2007.05.002.
Kaliba, C., M. Muya, and K. Mumba. 2009. “Cost escalation and schedule delay in road construction projects in Zambia.” Int. J. Project Manage. Sci. 27 (5): 522–531. https://doi.org/10.1016/j.ijproman.2008.07.003.
Kermanshachi, S., B. Dao, J. Shane, and S. Anderson. 2017. “Uncertainty analysis of procurement phase performance indicators using extreme bounds analysis (EBA).” In Proc., 6th CSCE Int. Construction Specialty Conf. Vancouver, BC, Canada: Canadian Society for Civil Engineering.
Kermanshachi, S., and B. Rouhanizadeh. 2019. “Robustness analysis of design phase performance predictors using extreme bound analysis (EBA).” In Proc., ASCE Int. Conf. on Computing in Civil Engineering. Reston, VA: ASCE.
Khosravi, S., and H. Afshari. 2011. “A success measurement model for construction projects.” In Vol. 11 of Proc., Int. Conf. on Financial Management and Economics IPEDR, 186–190. Singapore: IACSIT Press.
Kissi, E., K. Agyekum, B. K. Baiden, R. A. Tannor, G. E. Asamoah, and E. T. Andam. 2019. “Impact of project monitoring and evaluation practices on construction project success criteria in Ghana.” Built Environ. Project Asset Manage. 2019 (May): 7. https://doi.org/10.1108/bepam-11-2018-0135.
Kouskili, P. A., and N. Kartan. 2004. “Impact of construction materials on project time and cost in Kuwait.” J. Constr. Archit. Manage. 11 (2): 126–132. https://doi.org/10.1108/09699980410527867.
Leamer, E. E. 1983. “Sensitivity analysis would help.” Am. Econ. Rev. 57 (3): 308–313.
Leamer, E. E. 1985. “Sensitivity analysis would help.” Am. Econ. Rev., Am. Econ. Assoc. 57 (3): 308–313.
Le-Hoai, L., Y. D. Lee, and J. Y. Lee. 2008. “Delay and cost overrun in Vietnam large construction projects: A comparison with other selected countries.” J. Civ. Eng. 12 (6): 367–377. https://doi.org/10.1007/s12205-008-0367-7.
Levine, R., and D. Renelt. 1992. “A sensitivity analysis of cross-country growth regressions.” Am. Econ. Rev. 82 (4): 942–963.
Manavazhi, M. R., and Z. Xunzhi. 2011. “Productivity oriented analysis of design revisions.” Construct. Manage. Econ. 2011 (19): 379–391. https://doi.org/10.1080/01446190010017141.
Moosa, I. A., and B. A. Cardak. 2006. “The determinants of foreign direct investment: An extreme bounds analysis.” J. Multi. Financial Manage. 16 (7): 199–211. https://doi.org/10.1016/j.mulfin.2005.07.002.
Narayan, S., and H. C. Tan. 2019. “Adopting big data to forecast success of construction projects: A review.” Malaysian Constr. Res. J. 6 (1): 132–143.
Sala-i-Martin, X. 1997. “I just ran two million regressions.” Am. Econ. Rev. 87 (2): 178–183.
Sambasivan, M., and Y. W. Soon. 2007. “Causes and effects of delays in Malaysian construction industry.” Int. J. Project Manage. 25 (5): 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007.
Sohail, M., and A. N. Baldwin. 2004. “Performance indicators for ‘micro-projects’ in developing countries.” Construct. Manage. Econ. 22 (1): 11–23. https://doi.org/10.1080/0144619042000186022.
Tummalapudi, M., M. Harper, C. Taylor, T. R. Waddle, and R. Catchings. 2022. “Causes, implications, and strategies for project closeout delays in highway construction.” Transp. Res. Rec. 2022 (1): 03611981221087229. https://doi.org/10.1177/03611981221087229.
Tummalapudi, M., J. Killingsworth, C. Harper, and M. Mehaney. 2021. “US construction industry managerial strategies for economic recession and recovery: A Delphi study.” J. Constr. Eng. Manage. 147 (11): 04021146. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002175.
Wang, J., Z. Li, V. W. Tam, and M. I. Abbas. 2015. “Identifying best design strategies for construction waste minimization causes and effects of delays in Aceh construction industry.” J. Cleaner Prod. 92 (5): 237–247. https://doi.org/10.1080/0144619042000186022.
Information & Authors
Information
Published In
Copyright
© 2023 American Society of Civil Engineers.
History
Received: Aug 5, 2022
Accepted: Dec 5, 2022
Published online: Jan 23, 2023
Published in print: May 1, 2023
Discussion open until: Jun 23, 2023
Authors
Metrics & Citations
Metrics
Citations
Download citation
If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.