Application of Linguistic Clustering to Define Sources of Risks in Technical Projects

Publication: ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
Volume 4, Issue 1

Abstract

Risk identification is adversely affected by the still existing definitional and applicational discrepancy regarding risks and other related notions, such as hazards and impacts. A paradigm shift is beginning to be in effect, proposing the preliminary identification of risk sources to ameliorate the aforementioned adversities. However, apart from identifying risk sources from the outset, the bulk of the already conducted project risk-related research, from which risk sources could be derived, is still not free of discrepancies and is falling short of use. In this paper, a new linguistic clustering algorithm, using the k-means++ procedure in addition to the semantics tools of stop world removal and word stemming is developed and codified. Then, the algorithm is applied on a vast risk notions set, emanated from an exhaustive review of the relative literature. The clustered and semantically processed results of the application are then used for the deduction of risk sources. Thus, this paper provides a compact, general, and encompassing master set of risk sources, discretized among distinct overhead categories.

Get full access to this article

View all available purchase options and get full access to this article.

Acknowledgments

The authors wish to warmly acknowledge the advice of Savvas Karagiannidis on the robustification and codification of the algorithm.

References

Acharya, N. K., Lee, Y. D., and Im, H. M. (2006). “Conflicting factors in construction projects: Korean perspective.” Eng. Constr. Archit. Manage., 13(6), 543–566.
Ahmed, H. (2011). “Analysis of building sector construction productivity trends in North America between 1995 and 2009.” M.Sc. dissertation, Univ. of Waterloo, Waterloo, Canada.
Ahmed, S. M., Ahmad, R., and Saram, D. D. (1999). “Risk management trends in the Hong Kong construction industry: A comparison of contractors and owners perceptions.” Eng. Constr. Archit. Manage., 6(3), 225–234.
Aina, O. O., and Wahab, A. B. (2011). “An assessment of buildability problems in the Nigerian construction industry.” Global J. Res. Eng., 11(2), 43–52.
Ajayi, O. M., Ogunsanmi, O. E., Salako, O. A., and Mafimidiwo, B. A. (2012). “Impact of risk on performance of design and build projects in Lagos State, Nigeria.” Proc., 4th West Africa Built Environment Research (WABER) Conf., Univ. of Reading, Reading, U.K.
Akpan, E. O. P., Amade, B., Okangba, S. E., and Ekweozor, C. O. (2014). “Constructability practice and project delivery practices in the Nigerian construction industry.” J. Build. Perform., 5(1), 10–21.
Aldenderfer, M. S., and Blashfield, R. K. (1985). Cluster analysis, Sage, Los Angeles.
Alinaitwe, H. M., Mwakali, J. A., and Hansson, B. (2007). “Factors affecting the productivity of building craftsmen—Studies of Uganda.” J. Civil Eng. Manage., 13(3), 169–176.
Ameh, O. J., and Osegbo, E. E. (2011). “Study of relationship between time overrun and productivity on construction sites.” Int. J. Constr. Supply Chain Manage., 1(1), 56–67.
Amiri, M., Ardeshir, R., and Zarandi, M. H. F. (2017). “Fuzzy probabilistic expert system for occupational hazard assessment in construction.” Saf. Sci., 93, 16–28.
Andi, A. (2006). “The importance and allocation of risks in Indonesian construction projects.” Constr. Manage. Econ., 24(1), 69–80.
Andi, A., and Minato, T. (2003). “Design documents quality in the Japanese construction industry: Factors influencing and impacts on construction process.” Int. J. Project Manage., 21(7), 537–546.
Arthur, D., and Vassilvitskii, S. (2006). “k-means++: The advantages of careful seeding.”, Stanford InfoLab, Stanford, CA.
Attar, A. A., Gupta, A. K., and Desai, D. B. (2012). “A study of various factors affecting labour productivity and methods to improve it.” IOSR J. Mech. Civil Eng., 1(3), 11–14.
Bachem, O., Lucic, M., Hassani, S. H., and Krause, A. (2016). “Fast and provably good seeding for k-means.” Proc., 30th Conf. on Neural Information Processing Systems, NIPS Proceedings, Barcelona, Spain.
Baloi, D., and Price, A. D. F. (2003). “Modelling global risk factors affecting construction cost performance.” Int. J. Project Manage., 21(4), 261–269.
Bernstein, H. M., Russo, M. A., and Laquidara-Carr D., eds. (2011). Mitigation of risk in construction: Strategies for reducing risk and maximizing profitability, McGraw-Hill Construction, Bedford, MA.
Bing, L., Akintoye, A., Edwards, P. J., and Hardcastle, C. (2005). “The allocation of risk in PPP/PFI construction projects in the UK.” Int. J. Project Manage., 23(1), 25–35.
Bosher, L., Dainty, A., Carrillo, P., And, J. G., and Price, A. (2007). “Integrating disaster risk management into construction: A UK perspective.” Build. Res. Inf., 35(2), 163–177.
BSI (British Standard Institution). (2010). “Project management. Principles and guidelines for the management of projects.” BS 6079-1:2010, London.
Chan, D. W. M., Chan, A. P. C., Lam, P. T. I., and Chan, J. H. L. (2010). “Exploring the key risks and risk mitigation measures for guaranteed maximum price and target cost contracts in construction.” Constr. Law J., 26(5), 364–378.
Chan, D. W. M., Chan, A. P. C., Lam, P. T. I., Yeung, J. F. Y., and Chan, J. H. L. (2011). “Risk ranking and analysis in target cost contracts: Empirical evidence from the construction industry.” Int. J. Project Manage., 29(6), 751–763.
Chapman, R. J. (2001). “The controlling influences on effective risk identification and assessment for construction design management.” Int. J. Project Manage., 19(3), 147–160.
Charoenngam, C., and Yeh, C. Y. (1999). “Contractual risk and liability sharing in hydropower construction.” Int. J. Project Manage., 17(1), 29–37.
Chiarini, A. (2017). “Risk-based thinking according to ISO 9001:2015 standard and the risk sources European manufacturing SMEs intend to manage.” TQM J., 29(2), 310–323.
Chien, K. F., Wu, Z. H., and Huang, S. C. (2014). “Identifying and assessing critical risk factors for BIM projects: Empirical study.” Autom. Constr., 45, 1–15.
Chileshe, N., and Yirenkyi-Fianko, A. B. (2012). “An evaluation of risk factors impacting construction projects in Ghana.” J. Eng. Des. Technol., 10(3), 306–329.
CII (Construction Industry Institute). (1987). Constructability concepts file, Austin, TX.
Dang, C. N., Hoai, L. L., Kim, S. Y., Nguyen, C. V., Lee, Y. D., and Lee, S. H. (2017). “Identification of risk patterns in Vietnamese road and bridge construction: Contractor’s perspective.” Built Environ. Project Asset Manage., 7(1), 59–72.
De Silva, N., Ranasinghe, M., De Silva, C. R., and Thurairajah, N. (2012). “Architecture of ensemble neural networks for risk analysis.” Proc., 48th ASC Annual Int. Conf., Associated Schools of Construction, Birmingham, U.K.
Deza, M. M., and Deza, E. (2009). Encyclopedia of distances, Springer, Heidelberg, Germany.
Dikmen, I., Birgonul, M. T., and Han, S. (2007). “Using fuzzy risk assessment to rate cost overrun risk in international construction projects.” Int. J. Project Manage., 25(5), 494–505.
Ding, L. Y., Yu, H. L., Li, H., Zhou, C., Wu, X. G., and Yu, M. H. (2012). “Safety risk identification system for metro construction on the basis of construction drawings.” Autom. Constr., 27, 120–137.
Divjak, D., and Fieller, N. (2014). “Cluster analysis: Finding structure in linguistic data.” Corpus methods for semantics: Quantitative studies in polysemy and synonymy, D. Glynn and J. A. Robinson, eds., John Benjamin Publishing, Amsterdam, Netherlands.
Edwards, P. J., and Bowen, P. A. (2002). “Risk management trends in the construction industry: Moving towards joint risk management.” Eng. Constr. Archit. Manage., 9(2), 131–151.
Ellis, L. (2014). “Factors affecting construction labour productivity in Trinidad and Tobago.” J. Assoc. Prof. Eng. Trinidad Tobago, 42(1), 4–11.
El-Sayegh, S. M. (2008). “Risk assessment and allocation in the UAE construction industry.” Int. J. Project Manage., 26(4), 431–438.
Flanagan, R., and Norman, G. (1993). Risk management and construction, Blackwell Science, Hoboken, NJ.
Flaus, J. M. (2013). Risk analysis. Socio-technical and industrial systems, Wiley, Hoboken, NJ.
Flores, F. N., and Moreira, V. P. (2016). “Assessing the impact of stemming accuracy on information retrieval—A multilingual perspective.” Inf. Process. Manage., 52(5), 1–15.
Gallay, L., and Šimko, M. (2016). “Utilizing vector models for automatic text lemmatization.” Proc., 42nd Int. Conf. on Current Trends in Theory and Practice of Informatics SOFSEM 2016, Springer, Heidelberg.
Georgy, M. E., Kadry, M. O., and Osman, H. M. (2013). “Analogy-based ranking of delay causes: An outlook for future projects.” Proc., 19th CIB World Building Congress, QUT Publications, Queensland Univ. of Technology, Brisbane, Australia.
Gibson, R. (2015). Practical guide to disruption and productivity loss on construction and engineering projects, Wiley, West Sussex, U.K.
Goddard, C. (2013). Semantic analysis: An introduction, 2nd Ed., Oxford University Press, New York.
Gopal, T. G. S. R., and Murali, K. (2015). “A critical review on factors influencing labour productivity in construction.” IOSR J. Mech. Civil Eng., 12(5), 47–51.
Gransberg, D. D., and Douglas, E. E. (2005). “Implementing project constructability.” Proc., 2005 AACE Int. Transactions: 49th AACE Int. Annual Meeting, AACE International, Morgantown, WV.
Gruneberg, S., Hughes, W., and Ancell, D. (2007). “Risk under performance-based contracting in the UK construction sector.” Constr. Manage. Econ., 25(7), 691–699.
Han, S. H., and Diekmann, J. E. (2001). “Making a risk-based bid decision for overseas construction projects.” Constr. Manage. Econ., 19(8), 765–776.
Hassanein, A. A., and Afify, H. M. F. (2007). “A risk identification procedure for construction contracts—A case study of power station projects in Egypt.” Civil Eng. Environ. Syst., 24(1), 3–14.
Hassim, S., Jaafar, M. S., and Sazalli, S. A. A. H. (2009). “The contractor perception towers industrialised building system risk in construction projects in Malaysia.” Am. J. Appl. Sci., 6(5), 937–942.
Hoffman, A. J., and Henn, R. (2008). “Overcoming the social and psychological barriers to green building.” Organiz. Environ., 21(4), 390–419.
Hong, E. S., Lee, I. M., Shin, H. S., Nam, S. W., and Kong, J. S. (2009). “Quantitative risk evaluation based on event tree analysis technique: Application to the design of shield TBM.” Tunnelling Underground Space Technol., 24(3), 269–277.
Hsueh, S. L., Perng, Y. H., Yan, M. R., and Lee, J. R. (2007). “On-line multi-criterion risk assessment model for construction joint ventures in China.” Autom. Constr., 16(5), 607–619.
Ibbs, W., and Sun, X. (2016). “Proposed improvements to the MCAA method for quantifying construction loss of productivity.” Ph.D. dissertation, Univ. of California, Berkeley, CA.
Islam, M. A., and Khadem, M. M. R. K. (2013). “Productivity determinants in Oman construction industry.” Int. J. Productivity Qual. Manage., 12(4), 426–448.
ISO. (2015). “Quality management systems-requirements.” ISO 9001:2015, Geneva.
Kadir, M. R. A., Lee, W. P., Jaafar, M. S., Sapuan, S. M., and Ali, A. A. A. (2005). “Factors affecting construction labour productivity for Malaysian residential projects.” Struct. Survey, 23(1), 42–54.
Kangari, R. (1988). “Construction risk management.” Civil Eng. Syst., 5(3), 114–120.
Karimi, S., and Gidado, K. (2012). “Factors influencing construction productivity in Afghanistan.” Proc., 3rd Int. Conf. on Engineering, Project, and Production Management, Brighton, U.K.
Kartam, N. A., and Kartam, S. A. (2001). “Risk and its management in the Kuwaiti construction industry: A contractor’s perspective.” Int. J. Project Manage., 19(6), 325–335.
Khumpaisal, Z. C. S. (2009). “An analytic network process for risks assessment in commercial real estate development.” J. Property Investment Finance, 27(3), 238–258.
Kriel, J. J. (2013). “A process to assist technology investment decisions in construction—A case study in labour productivity.” M.Sc. dissertation, Stellenbosch Univ., Stellenbosch, South Africa.
Kuo, Y. C., and Lu, S. T. (2013). “Using fuzzy multiple criteria decision making approach to enhance risk assessment for metropolitan construction projects.” Int. J. Project Manage., 31(4), 602–614.
Kuykendall, C. J. (2007). “Key factors affecting labor productivity in the construction industry.” M.Sc. dissertation, Univ. of Florida, Gainesville, FL.
Lee, S. H. (2003). “A process model for controlling project productivity of highway construction operations.” Ph.D. thesis, Univ. of Florida, Gainesville, FL.
Leskovec, J., Rajaraman, A., and Ullman, J. D. (2014). Mining of massive datasets, Cambridge University Press, Cambridge, U.K.
Ling, F. Y. Y., and Hoi, L. (2006). “Risks faced by Singapore firms when undertaking construction projects in India.” Int. J. Project Manage., 24(3), 261–270.
Liu, J., Jin, F., Xie, Q., and Skitmore, M. (2017). “Improving risk assessment in financial feasibility of international engineering projects: A risk driver perspective.” Int. J. Project Manage., 35(2), 204–211.
Lloyd, S. P. (1982). “Least squares quantization in pcm.” IEEE Transactions on Information Theory, 28(2), 129–137.
Love, P. E., Niedzweicki, M., Bullen, P. A., and Edwards, D. J. (2012). “Achieving the Green Building Council of Australia’s World Leadership Rating in an office building in Perth.” J. Constr. Eng. Manage., 652–660.
Lovins, J. B. (1968). “Development of a stemming algorithm.” Mech. Transl. Comput. Ling., 11(1–2), 22–31.
Low, S. P., Liu, J., and He, S. (2009). “External risk management practices of Chinese construction firms in Singapore.” KSCE J. Civil Eng., 13(2), 85–95.
Luu, V. T., Kim, S. Y., Tuan, N. V., and Ogunlana, S. O. (2009). “Quantifying schedule risk in construction projects using Bayesian belief networks.” Int. J. Project Manage., 27(1), 39–50.
MacQueen, J. B. (1967). “Some methods for classification and analysis of multivariate observations.” Proc., 5th Berkeley Symp. on Mathematical Statistics and Probability, University of California Press, Berkeley, CA.
Mahamid, I. (2011). “Risk matrix for factors affecting time delay in road construction projects: Owners’ perspective.” Eng. Constr. Archit. Manage., 18(6), 609–617.
Mahamid, I., Al-Ghonamy, A., and Aichouni, M. (2013). “Major factors influencing employee productivity in the KSA public construction projects.” Int. J. Civil Environ. Eng., 14(1), 1–5.
Makulsawatudom, A., and Emsley, M. (2001). “Factors affecting the productivity of the construction industry in Thailand: The project managers’ perception.” Proc., 17th Annual ARCOM Conf., Univ. of Salford, Salford, U.K.
Mañelele, I., and Muya, M. (2008). “Risk identification on community-based construction projects in Zambia.” J. Eng. Des. Technol., 6(2), 145–161.
McCune, B., Grace, J. B., and Urban, D. L. (2002). Analysis of ecological communities, MjM Software Design, Gleneden Beach, OR.
Mehdizadeh, R. (2012). “Dynamic and multi-perspective risk management of construction projects using tailor-made risk breakdown structures.” Ph.D. thesis, Université de Bordeaux, Bordeaux, France.
Mezher, T. M., and Tawil, W. (1998). “Causes of delays in the construction industry in Lebanon.” Eng. Constr. Archit. Manage., 5(3), 252–260.
Mills, A. (2001). “A systematic approach to risk management for construction.” Struct. Survey, 19(5), 245–252.
Mojtahedi, S. M. H., Mousavi, S. M., and Makui, A. (2010). “Project risk identification and assessment simultaneously using multi-attribute group decision making technique.” Saf. Sci., 48(4), 499–507.
Mydin, S. H., Zin, R. M., Majid, M. Z. A., and Zahidi, M. (2011). “Buildability problems in the Malaysian building construction.” Proc., 2011 IEEE Symp. on Business, Engineering and Industrial Applications, Langkawi, Malaysia.
Nasirzadeh, F., Afshar, A., and Khanzadi, M. (2008a). “System dynamics approach for construction risk analysis.” Int. J. Civil Eng., 6(2), 120–131.
Nasirzadeh, F., Afshar, A., Khanzadi, M., and Howick, S. (2008b). “Integrating system dynamics and fuzzy logic modelling for construction risk management.” Constr. Manage. Econ., 26(11), 1197–1212.
National Research Council of the National Academies. (2009). Advancing the competitiveness and efficiency of the U.S. construction industry, National Academy Press, Washington, DC.
NetBeans IDE 8.2 [Computer software]. Sun Microsystems, Menlo Park, CA.
O’Connor, J. T., and Miller, S. J. (1994). “Barriers to constructability implementation.” J. Perform. Constr. Facil., 110–128.
Odesola, I. A. (2015). “Assessment of management-related factors affecting construction labour productivity in Cross River State of Nigeria.” Covenant J. Res. Built Environ., 3(2), 13–29.
Ökmen, Ö., and Öztaş, A. (2010). “Construction cost analysis under uncertainty with correlated cost risk analysis model.” Constr. Manage. Econ., 28(2), 203–212.
Oladapo, A. A. (2007). “A quantitative assessment of the cost and time impact of variation orders on construction projects.” J. Eng. Des. Technol., 5(1), 35–48.
Onix Text Retrieval Toolkit API Reference. (2016). “Stop word list 1.” ⟨http://www.lextek.com/manuals/onix/stopwords1.html⟩ (Aug. 13, 2016).
Othman, A. A. E. (2011). “Constructability for reducing construction waste and improving building.” Built Environ. J., 8(2), 31–54.
Öztaş, A., and Ökmen, O. (2005). “Judgmental risk analysis process development in construction projects.” Build. Environ., 40(9), 1244–1254.
Panneton, F., L’Ecuyer, P., and Matsumoto, M. (2006). “Improved long-period generators based on linear recurrences Modulo 2.” ACM Trans. Math. Software, 32(1), 1–16.
Perera, B. A. K. S., Dhanasinghe, I., and Rameezdeen, R. (2009). “Risk management in road construction: The case of Sri Lanka.” Int. J. Strategic Property Manage., 13(2), 87–102.
Porter, M. F. (1980). “An algorithm for suffix stripping.” Program, 14(3), 130–137.
Project Management Institute. (2013). A guide to the project management body of knowledge (PMBOK guide), 5th Ed., Newtown Square, PA.
Rahman, M. M., and Kumaraswamy, M. M. (2002a). “Joint risk management through transactionally efficient relational contracting.” Constr. Manage. Econ., 20(1), 45–54.
Rahman, M. M., and Kumaraswamy, M. M. (2002b). “Risk management trends in the construction industry: Moving towards joint risk management.” Eng. Constr. Archit. Manage., 9(2), 131–151.
Ren, H. (1994). “Risk lifecycle and risk relationships on construction projects.” Int. J. Project Manage., 12(2), 68–74.
Roumboutsos, A., and Anagnostopoulos, K. P. (2008). “Public-private partnership projects in Greece: Risk ranking and preferred risk allocation.” Constr. Manage. Econ., 26(7), 751–763.
Saghatforoush, E., Trigunarsyah, B., and Too, E. G. (2012). “Assessment of operability and maintainability success factors in provision of extended constructability principles.” Proc., 9th Int. Congress on Civil Engineering, Civilica Encyclopedia of Civil Engineering, Isfahan, Iran.
Santoso, D. S., Ogunlana, S. O., and Minato, T. (2003). “Assessment of risks in high rise building construction in Jakarta.” Eng. Constr. Archit. Manage., 10(1), 43–55.
Schieg, M. (2006). “Risk management in construction project management.” J. Bus. Econ. Manage., 7(2), 77–83.
Schonlau, M., and Guenther, N. (2016). “Text mining using n-grams.” ⟨http://ssrn.com/abstract=2759033⟩ (Jul. 1, 2016).
Selberherr, J., and Girmscheid, G. (2013). “An interdisciplinary cooperation network for the optimisation of sustainable life cycle buildings.” Proc., 19th CIB World Building Congress, QUT Publications, Queensland Univ. of Technology, Brisbane, Australia.
Shevchenko, G., Ustinovichius, L., and Andruškevičius, A. (2008). “Multi-attribute analysis of investments risk alternatives in construction.” Ukio Technologinis ir Ekonominis Vystymas, 14(3), 428–443.
Shi, Q., Zuo, J., Huang, R., Huang, J., and Pullen, S. (2013). “Identifying the critical factors for green construction—An empirical study in China.” Habitat Int., 40, 1–8.
Sidorov, G., Gelbukh, A., Gomez-Adorno, H., and Pinto, D. (2014). “Soft similarity and soft cosine measure: Similarity of features in vector space model.” Computación y Sistemas, 18(3), 491–504.
Smith, N. J. (1999). Managing risk in construction projects, Blackwell, Oxford, U.K.
Stanford Huguenard Lab. (2017). “Error sum of squares (SSE).” ⟨https://hlab.stanford.edu/brian/error_sum_of_squares.html⟩ (May 22, 2017).
Subramani, T., and Rajiv, S. R. (2016). “Improving construction efficiency and productivity of industry using SPSS.” Int. J. Appl. Innov. Eng. Manage., 5(5), 239–250.
Tan, P. N., Steinbach, M., and Kumar, V. (2005). Introduction to data mining, Addison-Wesley, Boston.
Taylan, O., Bafail, A. O., Abdulaal, R. M. S., and Kabli, M. R. (2014). “Construction projects selection and risk assessment by fuzzy AHP and fuzzy TOPSIS methodologies.” Appl. Soft Comput., 17, 105–116.
Tesfamariam, S., and Goda, K., eds. (2013). Handbook of seismic risk analysis and management of civil infrastructure systems, Woodhead Publishing, Cambridge, U.K.
Thuyet, N. V., Ogunlana, S. O., and Dey, P. K. (2007). “Risk management in oil and gas construction projects in Vietnam.” Int. J. Energy Sector Manage., 1(2), 175–194.
Tran, D. Q. (2014). “Exploring critical delivery selection risk factors for transportation design and construction projects.” Eng. Constr. Archit. Manage., 21(6), 631–647.
Trigunarsyah, B. (2004). “A review of current practice in constructability improvement: Case studies on construction projects in Indonesia.” Constr. Manage. Econ., 22(6), 567–580.
Tsai, T. C., and Yang, M. L. (2010). “Risk assessment of design-bid-build and design-build building projects.” J. Oper. Res. Soc. Jpn., 53(1), 20–39.
Valverde-Gascueña, N., Navarro-Astor, E., Fuentes-del-Burgo, J., and Ruiz-Fernandez, J. P. (2011). “Factors that affect the productivity of construction projects in small and medium companies: Analysis of its impact on planning.” Proc., 27th Annual ARCOM Conf., Association of Researchers in Construction Management, Bristol, U.K.
Van Dongen, S., and Enright, A. J. (2012). “Metric distances derived from cosine similarity and Pearson and Spearman correlations.” arXiv:1208.3145. [stat.ME].
Vasudevan, I., Sharmila, V., and Arasu, G. T. (2016). “A supervised clustering algorithm for text classification in pattern mining.” Int. J. Math. Sci. Eng., 2(1), 51–60.
Wang, S. Q., Dulaimi, M. F., and Aguria, M. Y. (2004). “Risk management framework for construction projects in developing countries.” Constr. Manage. Econ., 22(3), 237–252.
Wiguna, I. P. A., and Scott, S. (2006). “Relating risk to project performance in Indonesian building contracts.” Constr. Manage. Econ., 24(11), 1125–1135.
Xenidis, Y., and Angelides, D. (2005a). “The financial risks in build-operate-transfer projects.” Constr. Manage. Econ., 23(4), 431–441.
Xenidis, Y., and Angelides, D. (2005b). “The legal risks in build-operate-transfer projects.” J. Constr. Res., 6(2), 273–292.
Xu, Y., Yeung, J. F. Y., Chan, A. P. C., Chan, D. M. W., Wang, S. Q., and Ke, Y. (2010). “Developing a risk assessment model for PPP projects in China—A fuzzy synthetic evaluation approach.” Autom. Constr., 19(7), 929–943.
Yang, J. B., Huang, K. M., and Lee, C. H. (2010). “Evaluation of delay analysis methodologies on lost productivity in construction projects.” Proc., 27th Int. Symp. on Automation and Robotics in Construction, International Association for Automation and Robotics in Construction, Montreal.
Yates, J. K. (2014). Productivity improvement for construction and engineering: Implementing programs that save money and time, ASCE, Reston, VA.
Zaneldin, E. K. (2006). “Construction claims in United Arab Emirates: Types, causes, and frequency.” Int. J. Project Manage., 24(5), 453–459.
Zhao, X., Hwang, B. G., and Yu, G. S. (2013). “Identifying the critical risks in underground rail international construction joint ventures: Case study of Singapore.” Int. J. Project Manage., 31(4), 554–566.
Zhi, H. (1995). “Risk management for overseas construction projects.” Int. J. Project Manage., 13(4), 231–237.
Zou, P. X. W., and Li, J. (2010). “Risk identification and assessment in subway projects: Case study of Nanjing Subway Line 2.” Constr. Manage. Econ., 28(12), 1219–1238.
Zou, P. X. W., Zhang, G., and Wang, J. (2007). “Understanding the key risks in construction projects in China.” Int. J. Project Manage., 25(6), 601–614.
Zou, P. X. W., Zhang, G., and Wang, J. Y. (2006). “Identifying key risks in construction projects: Life cycle and stakeholder perspectives.” Proc., Pacific Rim Real Estate Society Conf., Auckland, New Zealand.

Information & Authors

Information

Published In

Go to ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
Volume 4Issue 1March 2018

History

Received: Apr 14, 2017
Accepted: Jul 3, 2017
Published online: Nov 15, 2017
Published in print: Mar 1, 2018
Discussion open until: Apr 15, 2018

Permissions

Request permissions for this article.

Authors

Affiliations

Dimosthenis Kifokeris [email protected]
Ph.D. Candidate, School of Civil Engineering, Faculty of Engineering, Aristotle Univ. of Thessaloniki, University Campus, 54124 Thessaloniki, Greece. E-mail: [email protected]
Assistant Professor, School of Civil Engineering, Faculty of Engineering, Aristotle Univ. of Thessaloniki, University Campus, 54124 Thessaloniki, Greece (corresponding author). ORCID: https://orcid.org/0000-0002-1415-2051. E-mail: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share