Critical Risks Inherent to the Transfer Phase of Public–Private Partnership Water Projects in China

Publication: Journal of Management in Engineering
Volume 38, Issue 3

Abstract

Public–private partnership (PPP) infrastructure projects progress through separate phases, with each phase subject to unique risks, thereby requiring a phase-based strategy for managing risks. To date, most research on PPP risk has emphasized phases, with an obvious neglect of the final, transfer phase (TP) of PPP projects, in which the project ownership reverts to government. This study identified and evaluated critical risk categories of the TP, using China’s PPP water sector as the context of analysis. A two-stage approach was adopted, including both qualitative and quantitative research methods. Seven critical transfer risk categories (CTRCs) were identified, namely overhaul risks, contract risks, posttransfer operation risks, residual value risks, political risks, information risks, and succeeding operator risks, of which three are unique to the TP. Expert recommendations were presented for the facilitation of a smooth transfer of water PPPs in China. The findings of this study contribute to the body of knowledge in PPP risk management, and the specialized research approach employed may be utilized in similar exploratory studies.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All data, models, and code generated or used during the study appear in the published article.

Acknowledgments

This study is supported by the Regional Innovation Cooperation Programs of Sichuan province, China (2021YFQ0050).

References

Abu-Bader, S. H. 2011. Using statistical methods in social science research: With a complete SPSS guide. Oxford: Oxford University Press.
Alkaf, N., and A. Karim. 2011. “Risk allocation in public-private partnership (PPP) project: A review on risk factors.” Int. J. Sustainable Constr. Eng. Technol. 2 (2): 8–16.
Ameyaw, E. E., and A. P. C. Chan. 2013. “Identifying public-private partnership (PPP) risks in managing water supply projects in Ghana.” J. Facil. Manage. 11 (2): 152–182. https://doi.org/10.1108/14725961311314651.
Babatunde, S. O., A. Opawole, and O. E. Akinsiku. 2012. “Critical success factors in public-private partnership (PPP) on infrastructure delivery in Nigeria.” J. Facil. Manage. 10 (3): 212–225. https://doi.org/10.1108/14725961211246018.
Bao, F., A. P. C. Chan, C. Chen, and A. Darko. 2018a. “Review of public–private partnership literature from a project lifecycle perspective.” J. Infrastruct. Syst. 24 (3): 04018008. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000424.
Bao, F., C. Chen, A. P. C. Chan, I. Martek, and A. Shrestha. 2019. “Dynamic framework transfer model for public–private partnerships: Lessons from a China water sector case study.” Eng. Constr. Archit. Manage. 26 (7): 1218–1239. https://doi.org/10.1108/ECAM-01-2018-0028.
Bao, F., I. Martek, C. Chen, A. P. C. Chan, and Y. Yu. 2018b. “Lifecycle performance measurement of public-private partnerships: A case study in China’s water sector.” Int. J. Strategic Prop. Manage. 22 (6): 516–531. https://doi.org/10.3846/ijspm.2018.6048.
Chan, A. P. C., A. Darko, and E. E. Ameyaw. 2017. “Strategies for promoting green building technologies adoption in the construction industry—An international study.” Sustainability 9 (6): 969. https://doi.org/10.3390/su9060969.
Chan, A. P. C., P. T. I. Lam, D. W. M. Chan, E. Cheung, and Y. Ke. 2009. “Drivers for adopting public private partnerships—Empirical comparison between China and Hong Kong Special Administrative Region.” J. Constr. Eng. Manage. 135 (11): 1115–1124. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000088.
Chan, A. P. C., P. T. I. Lam, D. W. M. Chan, E. Cheung, and Y. Ke. 2010. “Potential obstacles to successful implementation of public-private partnerships in Beijing and the Hong Kong Special Administrative Region.” J. Manage. Eng. 26 (1): 30–40. https://doi.org/10.1061/(ASCE)0742-597X(2010)26:1(30).
Chan, A. P. C., P. T. I. Lam, Y. Wen, E. E. Ameyaw, S. Q. Wang, and Y. J. Ke. 2015. “Cross-sectional analysis of critical risk factors for PPP water projects in China.” J. Infrastruct. Syst. 21 (1): 04014031. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000214.
Chan, A. P. C., J. F. Y. Yeung, C. C. P. Yu, S. Q. Wang, and Y. Ke. 2011. “Empirical study of risk assessment and allocation of public-private partnership projects in China.” J. Manage. Eng. 27 (3): 136–148. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000049.
Chen, C. 2009. “Can the pilot BOT Project provide a template for future projects? A case study of the Chengdu No. 6 Water Plant B Project.” Int. J. Project Manage. 27 (6): 573–583. https://doi.org/10.1016/j.ijproman.2008.10.006.
Cheng, Z., Y. Ke, J. Lin, Z. Yang, and J. Cai. 2016. “Spatio-temporal dynamics of public private partnership projects in China.” Int. J. Project Manage. 34 (7): 1242–1251. https://doi.org/10.1016/j.ijproman.2016.05.006.
Cheung, E., and A. P. C. Chan. 2011. “Risk factors of public-private partnership projects in China: Comparison between the water, power, and transportation sectors.” J. Urban Plann. Dev. 137 (4): 409–415. https://doi.org/10.1061/(ASCE)UP.1943-5444.0000086.
Chou, J.-S., and D. Pramudawardhani. 2015. “Cross-country comparisons of key drivers, critical success factors and risk allocation for public-private partnership projects.” Int. J. Project Manage. 33 (5): 1136–1150. https://doi.org/10.1016/j.ijproman.2014.12.003.
De Schepper, S., M. Dooms, and E. Haezendonck. 2014. “Stakeholder dynamics and responsibilities in Public–Private Partnerships: A mixed experience.” Int. J. Project Manage. 32 (7): 1210–1222. https://doi.org/10.1016/j.ijproman.2014.01.006.
Grimsey, D. L., and K. Mervyn. 2002. “Evaluating the risks of public private partnerships for infrastructure projects.” Int. J. Project Manage. 20 (2): 107–118. https://doi.org/10.1016/S0263-7863(00)00040-5.
Hwang, B.-G., X. Zhao, and M. J. S. Gay. 2013. “Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors.” Int. J. Project Manage. 31 (3): 424–433. https://doi.org/10.1016/j.ijproman.2012.08.003.
Jin, X.-H. 2012. “Allocating risks in public-private partnerships using a transaction cost economic approach: A case study.” Australas. J. Constr. Econ. Build. 9 (1): 19. https://doi.org/10.5130/AJCEB.v9i1.3011.
Ke, Y., S. Wang, A. P. C. Chan, and P. T. I. Lam. 2010. “Preferred risk allocation in China’s public–private partnership (PPP) projects.” Int. J. Project Manage. 28 (5): 482–492. https://doi.org/10.1016/j.ijproman.2009.08.007.
Li, B., A. Akintoye, P. J. Edwards, and C. Hardcastle. 2005. “The allocation of risk in PPP/PFI construction projects in the UK.” Int. J. Project Manage. 23 (1): 25–35. https://doi.org/10.1016/j.ijproman.2004.04.006.
Likert, R. 1932. “A technique for the measurement of attitudes.” Arch. Psychol. 22: 140.
Lima, S., A. Brochado, and R. C. Marques. 2021. “Public-private partnerships in the water sector: A review.” Util. Policy 69 (Apr): 101182. https://doi.org/10.1016/j.jup.2021.101182.
Liu, T., Y. Wang, and S. Wilkinson. 2016. “Identifying critical factors affecting the effectiveness and efficiency of tendering processes in Public–Private Partnerships (PPPs): A comparative analysis of Australia and China.” Int. J. Project. Manage. 34 (4): 701–716. https://doi.org/10.1016/j.ijproman.2016.01.004.
Ng, A., and M. Loosemore. 2007. “Risk allocation in the private provision of public infrastructure.” Int. J. Project Manage. 25 (1): 66–76. https://doi.org/10.1016/j.ijproman.2006.06.005.
Osei-Kyei, R., A. P. C. Chan, A. A. Javed, and E. E. Ameyaw. 2017. “Critical success criteria for public-private partnership projects: International experts’ opinion.” Int. J. Strategic Prop. Manage. 21 (1): 87–100. https://doi.org/10.3846/1648715X.2016.1246388.
Rindfleisch, A., and J. B. Heide. 1997. “Transaction cost analysis: Past, present, and future applications.” J. Marketing 61 (4): 30–54. https://doi.org/10.1177/002224299706100403.
Robinson, H. S., and J. Scott. 2009. “Service delivery and performance monitoring in PFI/PPP projects.” Construct. Manage. Econ. 27 (2): 181–197. https://doi.org/10.1080/01446190802614163.
Rwelamila, P. D., P. Fewings, and C. Henjewele. 2015. “Addressing the missing link in PPP projects: What constitutes the public?” J. Manage. Eng. 31 (5): 04014085. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000330.
Saurí, D., J. Olcina, and A. Rico. 2007. “The march towards privatisation? Urban water supply and sanitation in Spain.” J. Comp. Soc. Welfare 23 (2): 131–139. https://doi.org/10.1080/17486830701494616.
Shrestha, A., T.-K. Chan, A. A. Aibinu, C. Chen, and I. Martek. 2017. “Risks in PPP water projects in China: Perspective of local governments.” J. Constr. Eng. Manage. 143 (7): 05017006. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001313.
Smith, N. J., T. Merna, and P. Jobling. 2006. Managing risk in construction projects. Oxford: Blackwell.
Van Ham, H., and J. Koppenjan. 2001. “Building public-private partnerships: Assessing and managing risks in port development.” Public Manage. Rev. 3 (4): 593–616. https://doi.org/10.1080/14616670110070622.
Wahdan, M. Y. 1995. An analysis framework for PPP. Vancouver, BC, Canada: Univ. of British Columbia.
Wang, Y., and J. Liu. 2015. “Evaluation of the excess revenue sharing ratio in PPP projects using principal–agent models.” Int. J. Project Manage. 33 (6): 1317–1324. https://doi.org/10.1016/j.ijproman.2015.03.002.
Wibowo, A., and S. Mohamed. 2010. “Risk criticality and allocation in privatised water supply projects in Indonesia.” Int. J. Project Manage. 28 (5): 504–513. https://doi.org/10.1016/j.ijproman.2009.08.003.
Williamson, O. E. 1999. “Public and private bureaucracies: A transaction cost economics perspective.” J. Law Econ. Organ. 15 (1): 306–342. https://doi.org/10.1093/jleo/15.1.306.
World Bank. 2016. The APMG PPP certification program guide. Washington, DC: World Bank Publications.
Xu, Y., Y. Lu, A. P. C. Chan, M. J. Skibniewski, and J. F. Y. Yeung. 2012a. “A computerized risk evaluation model for public-private partnership (PPP) projects and its application.” Int. J. Strategic Prop. Manage. 16 (3): 277–297. https://doi.org/10.3846/1648715X.2012.686928.
Xu, Y., C. Sun, M. J. Skibniewski, A. P. C. Chan, J. F. Y. Yeung, and H. Cheng. 2012b. “System dynamics (SD)-based concession pricing model for PPP highway projects.” Int. J. Project Manage. 30 (2): 240–251. https://doi.org/10.1016/j.ijproman.2011.06.001.
Xu, Y., Y. Yang, A. P. C. Chan, J. F. Y. Yeung, and H. Cheng. 2011. “Identification and allocation of risks associated with PPP water projects in China.” Int. J. Strategic Prop. Manage. 15 (3): 275–294. https://doi.org/10.3846/1648715X.2011.617867.
Xu, Y., J. F. Y. Yeung, A. P. C. Chan, D. W. M. Chan, S. Q. Wang, and Y. Ke. 2010. “Developing a risk assessment model for PPP projects in China—A fuzzy synthetic evaluation approach.” Autom. Constr. 19 (7): 929–943. https://doi.org/10.1016/j.autcon.2010.06.006.
Yescombe, E. R. 2007. Public private partnerships: Principles of policy and finance. Oxford: Butterworth-Heinemann.
Yuan, J., A. P. C. Chan, B. Xia, M. J. Skibniewski, W. Xiong, and C. Ji. 2016. “Cumulative effects on the change of residual value in PPP projects: A comparative case study.” J. Infrastruct. Syst. 22 (2): 05015006. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000272.
Yuan, J., A. P. C. Chan, W. Xiong, M. J. Skibniewski, and Q. Li. 2015. “Perception of residual value risk in public private partnership projects: Critical review.” J. Manage. Eng. 31 (3): 04014041. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000256.
Zhang, S., A. P. C. Chan, Y. Feng, H. Duan, and Y. Ke. 2016. “Critical review on PPP Research—A search from the Chinese and International Journals.” Int. J. Project Manage. 34 (4): 597–612. https://doi.org/10.1016/j.ijproman.2016.02.008.
Zhang, S., Y. Gao, Z. Feng, and W. Sun. 2015. “PPP application in infrastructure development in China: Institutional analysis and implications.” Int. J. Project Manage. 33 (3): 497–509. https://doi.org/10.1016/j.ijproman.2014.06.006.
Zhang, W. R., S. Q. Wang, R. L. K. Tiong, S. K. Ting, and D. Ashley. 1998. “Risk management of Shanghai’s privately financed Yan’an Donglu tunnels.” Eng. Constr. Archit. Manage. 5 (4): 399. https://doi.org/10.1108/eb021092.
Zhong, L., A. P. J. Mol, and T. Fu. 2008. “Public-private partnerships in China’s urban water sector.” Environ. Manage. 41 (6): 863–877. https://doi.org/10.1007/s00267-008-9070-1.
Zhou, L., T. Xianglai, K. Jiaojiao, S. Perera, and C. Udeaja. 2013. “PPP infrastructure development in China: Challenges and future trends.” In Proc., PPP13: PPP Int. Conf. in Preston. Newcastle upon Tyne, UK: Northumbria Univ.

Information & Authors

Information

Published In

Go to Journal of Management in Engineering
Journal of Management in Engineering
Volume 38Issue 3May 2022

History

Received: Aug 24, 2021
Accepted: Nov 29, 2021
Published online: Jan 31, 2022
Published in print: May 1, 2022
Discussion open until: Jun 30, 2022

Permissions

Request permissions for this article.

Authors

Affiliations

Lecturer, School of Architecture and Civil Engineering, Chengdu Univ., No. 2025, Chengluo Ave., Chengdu, Sichuan 610106, China (corresponding author). ORCID: https://orcid.org/0000-0002-1223-466X. Email: [email protected]
Managing Director, School of Architecture and Built Environment, Deakin Univ., Geelong, VIC 3220, Australia. ORCID: https://orcid.org/0000-0001-6573-1291. Email: [email protected]
Professor, Business School, Sichuan Univ., Chengdu, Sichuan 610065, China. Email: [email protected]
Professor, School of Architecture and Civil Engineering, Chengdu Univ., No. 2025, Chengluo Ave., Chengdu, Sichuan 610106, China. Email: [email protected]
Albert P. C. Chan [email protected]
Professor, Dept. of Building and Real Estate, Hong Kong Polytechnic Univ., Hung Hom, Kowloon, Hong Kong. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

Cited by

  • Role of Shapley Additive Explanations and Resampling Algorithms for Contract Failure Prediction of Public–Private Partnership Projects, Journal of Management in Engineering, 10.1061/JMENEA.MEENG-5492, 39, 5, (2023).
  • Dynamic Assessment of the Transfer Risks in China’s Public–Private Partnership Water Projects: A System Dynamics Approach, Journal of Infrastructure Systems, 10.1061/JITSE4.ISENG-2302, 29, 4, (2023).
  • Factors Underpinning the Successful Return of Public–Private Partnership Projects to Public Authority: Assessing the Critical Success Factors of the Transfer Phase of Chinese Water Projects, Journal of Infrastructure Systems, 10.1061/JITSE4.ISENG-2084, 29, 2, (2023).
  • The Dilemma of Operator Selection in Urban Rail Transit PPP Project Operations: A LASSO Approach, Journal of Construction Engineering and Management, 10.1061/JCEMD4.COENG-12378, 149, 7, (2023).
  • Assessing the public-private partnership handover: Experience from China's water sector, Utilities Policy, 10.1016/j.jup.2022.101469, 80, (101469), (2023).
  • Operational Risk Management of Public–Private Partnership Infrastructure Projects: A Bibliometric Literature Review, Buildings, 10.3390/buildings12111905, 12, 11, (1905), (2022).

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share