The Effect of Change-Order Management Factors on Construction Project Success: A Structural Equation Modeling Approach

Publication: Journal of Construction Engineering and Management
Volume 148, Issue 9

Abstract

Managing change order is a critical area of concern in the construction industry, owing to the resulting disputes, claims, productivity losses, delays, and cost repercussions. There have been various studies proposing both quantitative and qualitative approaches to tackle the effect of change orders on project performance and success. Previous studies have almost solely focused on specific organizational policies, procedures, causes, and recommendations with the goal of capturing the essence of change-order management (CHM) within an area, organization, or kind of contract. However, their contributions are context-specific, limited to simple statistical method and make no reference to an inclusive concept of CHM performance factors. Furthermore, the existing literature urges a need for a realistic strategy to managing change orders, as well as limiting their negative consequences. Therefore, to address the research gap in the literature, this study proposes an operational and systematic CHM framework based on multidimensional performance factors to enhance the overall project success (OPS) factors, utilizing a partial least squares structural equation modeling (PLS-SEM) approach to develop the model. For evaluating CHM’s performance in terms of OPS, a conceptual model was developed. A questionnaire survey was used to conduct an empirical analysis to test the conceptual model. The information was gathered from 334 construction specialists that work in the field. The result of the analysis found that the explanatory power (R2) value of the CHM model is 0.665, which revealed that CHM performance factors in projects is responsible for 66.5% of project performance, which has a significant impact and demonstrating a strong influence. Furthermore, the management of communication and relationships, dispute resolution, and financial issues have a significant impact on CHM based on outer loading values of (β) 0.433, 0.432, and 0.422, respectively. Documentation, procurement, design, and quality management come next in terms of influence on CHM effectiveness, with outer loading values of (β) 0.402, 0.367, 0.345, and 0.289, respectively. This study adds to the body of knowledge by providing new insights and assisting in the identification and better understanding of CHM performance factors in construction projects and their impact on OPS, as well as the use of an advanced statistical method, PLS-SEM. The outcomes of this study can be utilized as a starting point for implementing CHM in construction projects. The practical applications of the proposed quantitative approach model can be utilized by the client, the consultant, and the contractor to successfully plan, manage, evaluate, monitor, and control the CHM performance. The findings of this study will aid policymakers and decision makers around the world in focusing on the industry’s most critical difficulties and challenges.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

The data generated or analyzed during the study are available from the corresponding author upon request.

References

Abad, F., E. Eshtehardian, and K. Taghizade. 2019. “Framework for proactive change management: Assessing the risk of change in construction projects using fuzzy fault tree analysis.” J. Archit. Eng. 25 (2): 04019010. https://doi.org/10.1061/(ASCE)AE.1943-5568.0000358.
Alaryan, A., A. E. Emadelbeltagi, and M. Dawood. 2014. “Causes and effects of change orders on construction projects in Kuwait.” Int. J. Eng. Res. Appl. 4 (7): 1–8.
Al-Kofahi, Z., A. Mahdavian, and A. Oloufa. 2020. “System dynamics modeling approach to quantify change orders impact on labor productivity 1: Principles and model development comparative study.” Int. J. Constr. Manage. 2020 (Jan): 1–12. https://doi.org/10.1080/15623599.2020.1711494.
Alleman, D., A. L. Antoine, M. S. Stanford, and K. R. Molenaar. 2020. “Project delivery methods’ change-order types and magnitudes experienced in highway construction.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 12 (2): 04520006. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000380.
Alnuaimi, A., R. Taha, M. Al Mohsin, and A. Al-Harthi. 2010. “Causes, effects, benefits, and remedies of change orders on public construction projects in Oman.” J. Constr. Eng. Manage. 136 (5): 615–622. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000154.
Arain, F., A. Assaf, and S. Low. 2004. “Causes of discrepancies between design and construction.” Archit. Sci. Rev. 47 (3): 237–249. https://doi.org/10.1080/00038628.2000.9697530.
Arain, F., and L. Pheng. 2005a. “How design consultants perceive causes of variation orders for institutional buildings in Singapore.” Archit. Eng. Des. Manage. 1 (3): 181–196. https://doi.org/10.1080/17452007.2005.9684592.
Arain, F., and L. Pheng. 2005b. “Knowledge-based decision support system for management of variation orders for institutional building projects.” Autom. Constr. 15 (2006): 272–291. https://doi.org/10.1016/j.autcon.2005.06.005.
Arain, F., and L. Pheng. 2005c. “The potential effects of variation orders on institutional building projects.” Facilities 23 (11–12): 496–510. https://doi.org/10.1108/02632770510618462.
Arain, F., and L. Pheng. 2007. “Modeling for management of variations in building projects.” Eng. Constr. Archit. Manage. 14 (5): 420–433. https://doi.org/10.1108/09699980710780737.
Arcadis. 2019. “Global construction disputes report 2019: Laying the foundation for success.” Accessed May 20, 2020. file:///C:/Users/AN2190398/Downloads/ME%20Global%20Construction%20Disputes%20Report%202019.pdf.
Ardakani, S. S., and M. Nik-Bakht. 2021. “Functional evaluation of change order and invoice management processes under different procurement strategies: Social network analysis approach.” J. Constr. Eng. Manage. 147 (1): 04020155. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001974.
Assaad, R., I. H. El-Adaway, and I. S. Abotaleb. 2020. “Predicting project performance in the construction industry.” J. Constr. Eng. Manage. 146 (5): 04020030. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001797.
Blumberg, B. F., D. R. Cooper, and P. S. Schindler. 2014. Business research methods. New York: McGraw-Hill Education.
Cakit, E., A. J. Olak, W. Karwowski, T. Marek, I. Hejduk, and R. Taiar. 2020. “Assessing safety at work using an adaptive neuro-fuzzy inference system (ANFIS) approach aided by partial least squares structural equation modeling (PLS-SEM).” Int. J. Ind. Ergon. 76 (20): 102925. https://doi.org/10.1016/j.ergon.2020.102925.
Chua, D. K. H., Y. C. Kog, and P. K. Loh. 1999. “Critical success factors for different project objectives.” J. Constr. Eng. Manage. 125 (3): 142–150. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:3(142).
CII (Construction Industry Institute). 2012. “CII best practices guide, improving project performance.” Accessed June 12, 2020. https://www.sig.org/docs2/CII_Best_Practices_Guide_Improving_Project_Performance.pdf?docID=9415.
CII (Construction Industry Institute). 2017. “Change management.” Accessed October 2, 2017. https://www.construction-institute.org/resources/knowledgebase/best-practices/change-management.
Du, J., M. El-Gafy, and D. Zhao. 2016. “Optimization of change order management process with object-oriented discrete event simulation: Case study.” J. Constr. Eng. Manage. 142 (4): 05015018. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001092.
Du, J., H. Jing, D. Castro-Lacouture, and V. Sugumaran. 2019. “Multi-agent simulation for managing design changes in prefabricated construction projects.” Eng. Constr. Archit. Manage. 27 (1): 270–295. https://doi.org/10.1108/ECAM-11-2018-0524.
Durdyev, S., S. Ismail, A. Ihtiyar, N. F. S. A. Bakar, and A. Darko. 2018. “A partial least squares structural equation modeling (PLS-SEM) of barriers to sustainable construction in Malaysia.” J. Cleaner Prod. 204 (2): 564–572. https://doi.org/10.1016/j.jclepro.2018.08.304.
Gunduz, M., and M. Almuajebh. 2020. “Critical success factors for sustainable construction project management.” Sustainability 12 (5): 1990. https://doi.org/10.3390/su12051990.
Gunduz, M., and H. Elsherbeny. 2020. “Operational framework for managing construction-contract administration practitioners’ perspective through modified Delphi method.” J. Constr. Eng. Manage. 146 (3): 04019110. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001768.
Gunduz, M., and H. A. Elsherbeny. 2021. “Critical assessment of contract administration using multidimensional fuzzy logic approach.” J. Constr. Eng. Manage. 147 (2): 04020162. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001975.
Gunduz, M., and O. Khan. 2018. “Effective framework for change order management using analytical hierarchy process (AHP).” Gazi Univ. J. Sci. 31 (4): 1079–1091.
Gunduz, M., and K. Mohammad. 2020. “Assessment of change order impact factors on construction project performance using analytic hierarchy process (AHP).” Technol. Econ. Dev. Econ. 26 (1): 71–85. https://doi.org/10.3846/tede.2019.11262.
Gunduz, M., and S. Tehemar. 2020. “Assessment of delay factors in construction of sport facilities through multi criteria decision making.” Prod. Plann. Control 31 (15): 1291–1302. https://doi.org/10.1080/09537287.2019.1704903.
Hair, J. F., L. M. Matthews, R. L. Matthews, and M. Sarstedt. 2017. “PLS-SEM or CB-SEM: Updated guidelines on which method to use.” Int. J. Multivariate Data Anal. 1 (2): 107–123. https://doi.org/10.1504/IJMDA.2017.087624.
Hair, J. F., C. M. Ringle, and M. Sarstedt. 2011. “PLS-SEM: Indeed a silver bullet.” J. Marketing Theory Pract. 19 (2): 139–152. https://doi.org/10.2753/MTP1069-6679190202.
Hair, J. F., J. J. Risher, M. Sarstedt, and C. M. Ringle. 2019. “When to use and how to report the results of PLS-SEM.” Eur. Bus. Rev. 2019 (1): 14. https://doi.org/10.1108/EBR-11-2018-0203.
Hair, J. F., M. Sarstedt, C. M. Ringle, and S. P. Gudergan. 2018. Advanced issues in partial least squares structural equations modeling (PLS-SEM). Thousand Oaks, CA: SAGE.
Han, S., S. Lee, and F. Pena-Mora. 2012. “Identification and quantification of non-value-adding effort from errors and changes in design and construction projects.” J. Constr. Eng. Manage. 138 (1): 98–109. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000406.
Hanna, A., and K. Iskandar. 2017. “Quantifying and modelling the cumulative impact of change orders.” J. Constr. Eng. Manage. 143 (10): 04017076. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001385.
Henseler, J., C. M. Ringle, and M. Sarstedt. 2015. “A new criterion for assessing discriminant validity in variance-based structural equation modeling.” J. Acad. Marketing Sci. 43 (1): 115–135. https://doi.org/10.1007/s11747-014-0403-8.
Hosseini, M. R., J. Zuo, N. Chileshe, and B. Baroudi. 2015. “Evaluating virtuality in teams: A conceptual model.” Technol. Anal. Strategic Manage. 27 (4): 385–404. https://doi.org/10.1080/09537325.2014.1003206.
Ibrahim, M. W., A. Hanna, and D. Kievet. 2020. “Quantitative comparison of project performance between project delivery systems.” J. Manage. Eng. 36 (6): 04020082. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000837.
Ingle, P. V., and G. Mahesh. 2020. “Construction project performance areas for Indian construction projects.” Int. J. Constr. Manage. 2020 (1): 1–12. https://doi.org/10.1080/15623599.2020.1721177.
Jarkas, A., and S. Mubarak. 2016. “Causes of construction change orders in Qatar: Contractors’ perspective.” Int. J. Project Organization Manage. 8 (3): 13. https://doi.org/10.1504/IJPOM.2016.078273.
Kabirifar, K., M. Mojtahedi, C. C. Wang, and V. Y. Tam. 2021. “Effective construction and demolition waste management assessment through waste management hierarchy; a case of Australian large construction companies.” J. Cleaner Prod. 312 (1): 127790. https://doi.org/10.1016/j.jclepro.2021.127790.
Kermanshachi, S., R. Thakur, and P. Govan. 2018. “Discovering the impact of late change orders and rework on labor productivity: A water treatment case study analysis using system dynamics modeling.” In Proc., Construction Research Congress, 2–4. Reston, VA: ASCE.
Khalafallah, A., and Y. Shalaby. 2019. “Change orders: Automating comparative data analysis and controlling impacts in public projects.” J. Constr. Eng. Manage. 145 (11): 04019064. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001700.
Khanzadi, M., F. Nasirzadeh, and M. S. Dashti. 2018. “Fuzzy cognitive map approach to analyze causes of change orders in construction projects.” J. Constr. Eng. Manage. 144 (2): 04017111. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001430.
Kim, J., J. Miller, and S. Kim. 2020. “Cost impacts of change orders due to unforeseen existing conditions in building renovation projects.” J. Constr. Eng. Manage. 146 (8): 04020094. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001888.
Kineber, A., I. Othman, A. Oke, N. Chileshe, and M. Buniya. 2021. “Impact of value management on building projects success: Structural equation modeling approach.” J. Constr. Eng. Manage. 147 (4): 04021011. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002026.
Ko, T., H. D. Jeong, and G. Lee. 2021. “Natural language processing–Driven model to extract contract change reasons and altered work items for advanced retrieval of change orders.” J. Constr. Eng. Manage. 147 (11): 04021147. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002172.
Kock, N., and P. Hadaya. 2018. “Minimum sample size estimation in PLS-SEM: The inverse square root and gamma-exponential methods.” Inf. Syst. J. 28 (1): 227–261. https://doi.org/10.1111/isj.12131.
Lavikka, R., R. Kyrö, A. Peltokorpi, and A. Särkilahti. 2019. “Revealing change dynamics in hospital construction projects.” Eng. Constr. Archit. Manage. 26 (9): 1946–1961. https://doi.org/10.1108/ECAM-03-2018-0119.
Love, P. E., J. Matthews, and W. Fang. 2020. “Rework in construction: A focus on error and violation.” J. Constr. Eng. Manage. 146 (9): 06020001. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001901.
Low, W. W., H. Abdul-Rahman, and N. Zakaria. 2020. “Organizational culture of Malaysian international construction organizations.” Int. J. Constr. Manage. 20 (2): 105–121. https://doi.org/10.1080/15623599.2018.1484552.
Manoharan, K., P. Dissanayake, C. Pathirana, D. Deegahawature, and R. Silva. 2020. “Assessment of critical factors influencing the performance of labour in Sri Lankan construction industry.” Int. J. Constr. Manage. 2020 (Jan): 1–35. https://doi.org/10.1080/15623599.2020.1854042.
Mir, F. A., and A. H. Pinnington. 2014. “Exploring the value of project management: Linking project management performance and project success.” Int. J. Project Manage. 32 (2): 202–217. https://doi.org/10.1016/j.ijproman.2013.05.012.
Naji, K., M. Gunduz, and F. Salat. 2020a. “Assessment of preconstruction factors in sustainable project management performance.” Eng. Constr. Archit. Manage. 2020 (Dec): 25. https://doi.org/10.1108/ECAM-05-2020-0333.
Naji, K., M. Mansour, and M. Gunduz. 2020b. “Methods for modeling and evaluating construction disputes: A critical review.” IEEE Access 8 (Dec): 45641–45652. https://doi.org/10.1109/ACCESS.2020.2976109.
Oppong, G. D., A. P. Chan, E. E. Ameyaw, S. Frimpong, and A. Dansoh. 2021. “Fuzzy evaluation of the factors contributing to the success of external stakeholder management in construction.” J. Constr. Eng. Manage. 147 (11): 04021142. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002155.
Othman, N. I. 2015. “The impact of value management on project success in FELDA projects.” M.Sc. thesis, Faculty of Civil Engineering, Universiti Teknologi Malaysia.
Rahman, I. A., A. Hameed Mem, and A. T. Abd Karim. 2013. “Significant factors causing cost overruns in large construction projects in Malaysia.” J. Appl. Sci. 13 (2): 286. https://doi.org/10.3923/jas.2013.286.293.
Ramli, N. A., H. Latan, and G. V. Nartea. 2018. “Why should PLS-SEM be used rather than regression? Evidence from the capital structure perspective.” In Partial least squares structural equation modeling, 171–209. Berlin: Springer.
Rockart, J. F. 1980. “The changing role of the information systems executive: A critical success factors perspective.” Accessed January 29, 2020. https://dspace.mit.edu/bitstream/handle/1721.1/2010/SWP-1297-08770929-CISR-085.pdf.
Rossoni, L., R. Engelbert, and N. L. Bellegard. 2016. “Normal science and its tools: Reviewing the effects of exploratory factor analysis in management.” Revista de Administração 51 (2): 198–211. https://doi.org/10.5700/rausp1234.
Safapour, E., and S. Kermanshachi. 2018. “Identifying early indicators of manageable rework causes and selecting the mitigating construction best practices.” J. Manage. Eng. 35 (2): 04018060. https://doi.org/10.1061/(ASCE)ME.1943-5479.000069.
Safapour, E., S. Kermanshachi, and P. Taneja. 2019. “Investigation and analysis of the rework leading indicators in construction projects: State-of-the-art review.” In Proc., 7th CSCE Int. Construction Specialty Conf., 12–15. Point Claire, QC, Canada: Canadian Society for Civil Engineering.
Sarstedt, M., J. F. Hair, C. Ringle, and J. F. Hair. 2018. “Partial least squares structural equation modeling.” In Handbook of market research. Berlin: Springer.
Sarstedt, M., C. M. Ringle, and J. F. Hair. 2017. “Partial least squares structural equation modeling.” Handbook Market Res. 26 (1): 1–40. https://doi.org/10.1007/978-3-319-05542-8_15-1.
Senouci, A., A. Alsarraj, M. Gunduz, and N. Eldin. 2016. “Analysis of change orders in Qatari construction projects.” Int. J. Constr. Manage. 17 (4): 280–292. https://doi.org/10.1080/15623599.2016.1211973.
Shabani, A. S., and M. Nik-Bakht. 2021. “Functional evaluation of change order and invoice management processes under different procurement strategies: Social network analysis approach.” J. Constr. Eng. Manage. 147 (1): 04020155. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001974.
Shafaat, A., M. Alinizzi, T. Mahfouz, and A. Kandil. 2016. “Can contractors predict change orders? Investigating a historical allegation.” In Proc., Construction Research Congress 2016, 487–496. Reston, VA: ASCE.
Shipton, C., W. Hughes, and D. Tutt. 2014. “Change management in practice: An ethnographic study of changes to contract requirements on a hospital project.” Construct. Manage. Econ. 32 (7–8): 787–803. https://doi.org/10.1080/01446193.2014.915336.
Shrestha, K., and P. Shrestha. 2019. “Change orders on road maintenance contracts: Causes and preventive measures.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 11 (3): 04519009. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000299.
Shrestha, P., and R. Maharjan. 2018. “Effects of change orders on cost growth, schedule growth, and construction intensity of large highway projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 10 (3): 04518012. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000264.
Shrestha, P., K. Shrestha, and H. Zeleke. 2019. “Probability of change orders and the effect on cost and schedule for new public school buildings.” Eng. Constr. Archit. Manage. 26 (6): 1087–1104. https://doi.org/10.1108/ECAM-01-2018-0017.
Shrestha, P. P., and H. Zeleke. 2018. “Effect of change orders on cost and schedule overruns of school building renovation projects.” J. Leg. Aff. Dispute Resolut. Eng. Constr. 10 (4): 04518018. https://doi.org/10.1061/(ASCE)LA.1943-4170.0000271.
Solla, M., L. H. Ismail, and A. Milad. 2019. “Measuring the feasibility of using of BIM application to facilitate GBI assessment process.” J. Build. Eng. 25 (9): 100821. https://doi.org/10.1016/j.jobe.2019.100821.
Sun, M., and X. Meng. 2009. “Taxonomy for change causes and effects in construction projects.” Int. J. Project Manage. 27 (6): 560–572. https://doi.org/10.1016/j.ijproman.2008.10.005.
Svensson, G., C. Ferro, N. Høgevold, C. Padin, J. C. S. Varela, and M. Sarstedt. 2018. “Framing the triple bottom line approach: Direct and mediation effects between economic, social and environmental elements.” J. Cleaner Prod. 197 (2): 972–991. https://doi.org/10.1016/j.jclepro.2018.06.226.
Taylor, T., M. Uddin, P. Goodrum, A. McCoy, and Y. Shan. 2012. “Change orders and lessons learned: Knowledge from statistical analyses of engineering change orders on Kentucky highway projects.” J. Constr. Eng. Manage. 138 (Apr): 1360–1369. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000550.
Ullah, M., M. W. A. Khan, A. Hussain, F. Rana, and A. Khan. 2020. “A construct validation approach for exploring sustainability adoption in Pakistani construction projects.” Buildings 10 (11): 207. https://doi.org/10.3390/buildings10110207.
Wong, K. K. K. 2013. “Partial least squares structural equation modeling (PLS-SEM) techniques using SmartPLS.” Marketing Bull. 24 (1): 1–32.
Wuni, I. Y., and G. Q. Shen. 2020. “Critical success factors for management of the early stages of prefabricated prefinished volumetric construction project life cycle.” Eng. Constr. Archit. Manage. 27 (9): 2315–2333. https://doi.org/10.1108/ECAM-10-2019-0534.
Zeng, N., Y. Liu, P. Gong, M. Hertogh, and M. König. 2021. “Do right PLS and do PLS right: A critical review of the application of PLS-SEM in construction management research.” Front. Eng. Manage. 8 (3): 356–369. https://doi.org/10.1007/s42524-021-0153-5.
Zhang, D., C. Haas, P. Goodrum, C. Caldas, and R. Granger. 2012. “Construction small-projects rework reduction for capital facilities.” J. Constr. Eng. Manage. 138 (12): 1377–1385. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000552.
Zhao, Z., Q. Lv, J. Zuo, and G. Zillante. 2010. “Prediction system for change management in construction project.” J. Constr. Eng. Manage. 136 (6): 659–669. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000168.

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 148Issue 9September 2022

History

Received: Sep 14, 2021
Accepted: Apr 25, 2022
Published online: Jun 29, 2022
Published in print: Sep 1, 2022
Discussion open until: Nov 29, 2022

Permissions

Request permissions for this article.

Authors

Affiliations

Associate Professor, Dept. of Civil Engineering, Qatar Univ., Doha 2713, Qatar. ORCID: https://orcid.org/0000-0003-2050-3126. Email: [email protected]
Professor, Dept. of Civil Engineering, Qatar Univ., Doha 2713, Qatar (corresponding author). ORCID: https://orcid.org/0000-0003-2602-3318. Email: [email protected]
Ayman F. Naser, M.ASCE [email protected]
P.E.
Ph.D. Student, Engineering Management Program, College of Engineering, Qatar Univ., Doha 2713, Qatar. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share