Technical Papers
May 27, 2022

Prioritizing Construction Activities: Addressing the Flaws of Schedule-Based Indexes

Publication: Journal of Construction Engineering and Management
Volume 148, Issue 8

Abstract

Research on prioritizing construction activities that are critical to the timely completion of projects rests on a range of indexes that attempt to identify the critical path and capture uncertainty in the duration of project activities. However, these indexes have been shown to have major flaws. These flaws can be classified broadly into two categories: (1) incomplete representation of an activity’s importance; and (2) problems in the mathematical representation of an activity’s importance. This paper developed a new index that addresses the shortcomings of the available schedule-based indexes. The proposed index was applied to a real-life construction project to evaluate the significance of its activities. The results confirmed the substantive influence of the structural organization of the project network on the relative importance of project activities. The key contribution of this research is to offer a richer approach to measuring the importance of construction activities by paying simultaneous attention to uncertainty in completion time, the total float, and the topological characteristics of project activities.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

All data, models, and code generated or used during the study appear in the published paper.

References

Ansari, R., A. Makui, and P. Ghoddousi. 2018. “An algorithmic framework for improving the performance of the critical chain buffer sizing method.” Scientia Iranica 25 (1): 74–92. https://doi.org/10.24200/SCI.2017.4180.
Ballesteros-Pérez, P., A. Cerezo-Narváez, M. Otero-Mateo, A. Pastor-Fernández, and M. Vanhoucke. 2019. “Performance comparison of activity sensitivity metrics in schedule risk analysis.” Autom. Constr. 106 (2019): 1–11. https://doi.org/10.1016/j.autcon.2019.102906.
Bashir, H. A. 2010. “Removal of redundant relationships in an AON project network for evaluating schedule complexity.” J. Constr. Eng. Manage. 136 (7): 787–793. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000181.
Bi, L., B. Ren, D. Zhong, and L. Hu. 2015. “Real-time construction schedule analysis of long-distance diversion tunnels based on lithological predictions using a Markov process.” J. Constr. Eng. Manage. 141 (2): 04014076. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000935.
Bonacich, P. 2007. “Some unique properties of eigenvector centrality.” Social Networks 29 (4): 555–564. https://doi.org/10.1016/j.socnet.2007.04.002.
Bowman, R. A. 2007. “Efficient sensitivity analysis of PERT network performance measures to significant changes in activity time parameters.” J. Oper. Res. Soc. 58 (10): 1354–1360. https://doi.org/10.1057/palgrave.jors.2602297.
Chakrabortty, R. K., H. F. Rahman, and M. J. Ryan. 2020. “Efficient priority rules for project scheduling under dynamic environments: A heuristic approach.” Comput. Ind. Eng. 140 (106287): 1–18. https://doi.org/10.1016/j.cie.2020.106287.
Chen, Z., E. Demeulemeester, S. Bai, and Y. Guo. 2018. “Efficient priority rules for the stochastic resource-constrained project scheduling problem.” Eur. J. Oper. Res. 270 (3): 957–967. https://doi.org/10.1016/j.ejor.2018.04.025.
Chinowsky, P., J. E. Taylor, and M. Di Marco. 2011. “Project network interdependency alignment: New approach to assessing project effectiveness.” J. Manage. Eng. 27 (3): 170–178. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000048.
Cho, J. G., and B. J. Yum. 1997. “An uncertainty importance measure of activities in PERT networks.” Int. J. Prod. Res. 35 (10): 2737–2758. https://doi.org/10.1080/002075497194426.
Creemers, S., E. Demeulemeester, and S. Van de Vonder. 2014. “A new approach for quantitative risk analysis.” Ann. Oper. Res. 213 (1): 27–65. https://doi.org/10.1007/s10479-013-1355-y.
Cui, W., J. Qin, and C. Yue. 2006. “Criticality measurement in PERT networks.” In Proc., IEEE Int. Conf. on Systems, Man and Cybernetics, 703–706. Piscataway, NJ: IEEE.
de la Garza, J. M., A. Prateapusanond, and N. Ambani. 2007. “Preallocation of total float in the application of a critical path method based construction contract.” J. Constr. Eng. Manage. 133 (11): 836–845. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:11(836).
Dodin, B. M., and S. E. Elmaghraby. 1985. “Approximating the criticality indices of the activities in PERT networks.” Manage. Sci. 31 (2): 207–223. https://doi.org/10.1287/mnsc.31.2.207.
Elmaghraby, S. E. 2000. “On criticality and sensitivity in activity networks.” Eur. J. Oper. Res. 127 (2): 220–238. https://doi.org/10.1016/S0377-2217(99)00483-X.
Franco-Duran, D. M., and J. M. de la Garza. 2020. “Performance of resource-constrained scheduling heuristics.” J. Constr. Eng. Manage. 146 (4): 04020026. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001804.
Gunawan, I., F. Schultmann, and S. A. Zarghami. 2017. “The four Rs performance indicators of water distribution networks: A review of research literature.” Int. J. Q. Reliab. Manage. 34 (5): 720–732. https://doi.org/10.1108/IJQRM-11-2016-0203.
Hajdu, M., G. Lucko, and Y. Su. 2017. “Singularity functions for continuous precedence relations and nonlinear activity-time-production functions.” Autom. Constr. 79 (2017): 31–38. https://doi.org/10.1016/j.autcon.2017.01.012.
Huang, D. H., C. F. Huang, and Y. K. Lin. 2020. “Exact project reliability for a multi-state project network subject to time and budget constraints.” Reliab. Eng. Syst. Saf. 195: 106744. https://doi.org/10.1016/j.ress.2019.106744.
Kaplan, S., and B. J. Garrick. 1981. “On the quantitative definition of risk.” Risk Anal. 1 (1): 11–27. https://doi.org/10.1111/j.1539-6924.1981.tb01350.x.
Latva-Koivisto, A. M. 2001. Finding a complexity measure for business process models. Espoo, Finland: Helsinki Univ. of Technology.
Lee, C.-Y., H.-Y. Chong, P.-C. Liao, and X. Wang. 2018. “Critical review of social network analysis applications in complex project management.” J. Manage. Eng. 34 (2): 04017061. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000579.
Lee, J., and H. Hyun. 2019. “Multiple modular building construction project scheduling using genetic algorithms.” J. Constr. Eng. Manage. 145 (1): 04018116. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001585.
Lucko, G., and Y. Su. 2018. “Precedence permutation patterns creating criticality constellations: Exploring a conjecture on nonlinear activities with continuous links.” Organ. Technol. Manage. Constr. Int. J. 10 (1): 1674–1683. https://doi.org/10.1515/otmcj-2016-0023.
Lucko, G., Y. Su, and R. C. Thompson Jr. 2021. “Theoretical quantification of ripple effect of delays in network schedules via activity cruciality.” Autom. Constr. 129 (2021): 103789. https://doi.org/10.1016/j.autcon.2021.103789.
Luo, L., Q. He, E. J. Jaselskis, and J. Xie. 2017. “Construction project complexity: Research trends and implications.” J. Constr. Eng. Manage. 143 (7): 04017019. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001306.
Ma, G., A. Wang, N. Li, L. Gu, and Q. Ai. 2014. “Improved critical chain project management framework for scheduling construction projects.” J. Constr. Eng. Manage. 140 (12): 04014055. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000908.
Madadi, M., and H. Iranmanesh. 2012. “A management oriented approach to reduce a project duration and its risk (variability).” Eur. J. Oper. Res. 219 (3): 751–761. https://doi.org/10.1016/j.ejor.2012.01.006.
Martin, J. J. 1965. “Distribution of the time through a directed, acyclic network.” Oper. Res. 13 (1): 46–66. https://doi.org/10.1287/opre.13.1.46.
Nassar, K. M., and M. Y. Hegab. 2006. “Developing a complexity measure for project schedules.” J. Constr. Eng. Manage. 132 (6): 554–561. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:6(554).
O’Connor, J. T., and B. D. Mock. 2019. “Construction, commissioning, and startup execution: Problematic activities on capital projects.” J. Constr. Eng. Manage. 145 (4): 04019009. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001621.
She, B., B. Chen, and N. G. Hall. 2021. “Buffer sizing in critical chain project management by network decomposition.” Omega 102 (2021): 102382. https://doi.org/10.1016/j.omega.2020.102382.
Sinha, S., B. Kumar, and A. Thomson. 2006. “Measuring project complexity: A project manager’s tool.” Archit. Eng. Des. Manage. 2 (3): 187–202. https://doi.org/10.1080/17452007.2006.9684615.
Sonmez, R., and M. Gürel. 2016. “Hybrid optimization method for large-scale multimode resource-constrained project scheduling problem.” J. Manage. Eng. 32 (6): 04016020. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000468.
Su, Y., and G. Lucko. 2016. “Linear scheduling with multiple crews based on line-of-balance and productivity scheduling method with singularity functions.” Autom. Constr. 70 (2016): 38–50. https://doi.org/10.1016/j.autcon.2016.05.011.
Tavares, L. V., J. A. Ferreira, and J. S. Coelho. 1999. “The risk of delay of a project in terms of the morphology of its network.” Eur. J. Oper. Res. 119 (2): 510–537. https://doi.org/10.1016/S0377-2217(99)00150-2.
Tukel, O. I., W. O. Rom, and S. D. Eksioglu. 2006. “An investigation of buffer sizing techniques in critical chain scheduling.” Eur. J. Oper. Res. 172 (2): 401–416. https://doi.org/10.1016/j.ejor.2004.10.019.
Vanhoucke, M. 2010. “Using activity sensitivity and network topology information to monitor project time performance.” Omega 38 (5): 359–370. https://doi.org/10.1016/j.omega.2009.10.001.
Vanhoucke, M. 2015. “On the use of schedule risk analysis for project management.” J. Mod. Project Manage. 2 (3): 108–117.
Wang, C., S. C. Loo, J. B. H. Yap, and H. Abdul-Rahman. 2019. “Novel capability-based risk assessment calculator for construction contractors venturing overseas.” J. Constr. Eng. Manage. 145 (10): 04019059. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001696.
Williams, T. M. 1992. “Criticality in stochastic networks.” J. Oper. Res. Soc. 43 (4): 353–357. https://doi.org/10.1057/jors.1992.50.
Xiao, L., L. Bie, and X. Bai. 2021. “Controlling the schedule risk in green building projects: Buffer management framework with activity dependence.” J. Cleaner Prod. 278 (2021): 123852. https://doi.org/10.1016/j.jclepro.2020.123852.
Zarghami, S. A., and J. Dumrak. 2021a. “Aleatory uncertainty quantification of project resources and its application to project scheduling.” Reliab. Eng. Syst. Saf. 211 (107637): 1–15. https://doi.org/10.1016/j.ress.2021.107798.
Zarghami, S. A., and J. Dumrak. 2021b. “Unearthing vulnerability of supply provision in logistics networks to the black swan events: Applications of entropy theory and network analysis.” Reliab. Eng. Syst. Saf. 107798 (Jan): 1–15. https://doi.org/10.1016/j.ress.2021.107798.
Zarghami, S. A., and A. Gorod. 2019. “Scheduling toolset.” In Evolving toolbox for complex project management. London: CRC Press.
Zarghami, S. A., and I. Gunawan. 2020. “A domain-specific measure of centrality for water distribution networks.” Eng. Constr. Archit. Manage. 27 (2): 341–355. https://doi.org/10.1108/ECAM-03-2019-0176.
Zarghami, S. A., I. Gunawan, G. Corral de Zubielqui, and B. Baroudi. 2020. “Incorporation of resource reliability into critical chain project management buffer sizing.” Int. J. Prod. Res. 58 (20): 6130–6144. https://doi.org/10.1080/00207543.2019.1667041.
Zarghami, S. A., I. Gunawan, and F. Schultmann. 2018. “Integrating entropy theory and cospanning tree technique for redundancy analysis of water distribution networks.” Reliab. Eng. Syst. Saf. 176 (Sep): 102–112. https://doi.org/10.1016/j.ress.2018.04.003.
Zarghami, S. A., I. Gunawan, and F. Schultmann. 2019. “Entropy of centrality values for topological vulnerability analysis of water distribution networks.” Built Environ. Project Asset Manage. 9 (3): 412–425. https://doi.org/10.1108/BEPAM-02-2019-0014.
Zhong, D. H., and J. S. Zhang. 2003. “New method for calculating path float in program evaluation and review technique (PERT).” J. Constr. Eng. Manage. 129 (5): 501–506. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:5(501).

Information & Authors

Information

Published In

Go to Journal of Construction Engineering and Management
Journal of Construction Engineering and Management
Volume 148Issue 8August 2022

History

Received: Oct 12, 2021
Accepted: Apr 6, 2022
Published online: May 27, 2022
Published in print: Aug 1, 2022
Discussion open until: Oct 27, 2022

Permissions

Request permissions for this article.

Authors

Affiliations

Senior Lecturer, Research School of Management, Australian National Univ., 26 Kingsley St., Canberra 2601, Australia. ORCID: https://orcid.org/0000-0001-7839-2794. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share