Case Studies
May 3, 2024

Investigating the Contractor’s Financial Risk under a Fixed-Price Contract during Crisis Time: The Case of the COVID-19 Pandemic

Publication: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 16, Issue 3

Abstract

Fixed price contracts are common in construction. However, extreme turbulences within the construction sector due to the COVID-19 pandemic and other events over the last few years questioned the suitability of fixed price contracts during crisis times. This research investigated the financial loss experienced by construction contractors bounded by a fixed price contractual mechanism during the crisis induced by the COVID-19 pandemic. Financial implications of fixed and fluctuating price contracts were modeled using cost data from a typical construction project and two construction price and cost indices published by the BCIS UK. A total of 12 project scenarios were modeled to represent 3 projects that started a few months before the pandemic, agreed and started during the early phase of the pandemic and agreed and started during the exit phase. Findings show that fixed priced contracts agreed upon before the pandemic and ended in the early months of the pandemic were not in an adverse financial situation. Fixed priced contracts agreed before the pandemic and completed during the pandemic had a high chance of falling into a negative financial crisis, particularly if the project lasted longer. Fixed priced contracts agreed during the exit phase of the pandemic were in a significant adverse financial situation. Fluctuating price contracts could place contractors in a favorable position to avoid significant financial losses during crisis times. Other limitations associated with mechanisms that need to be considered and addressed through further research were also discussed. The finding highlighted the deficiencies in conventional practices of forecasting construction costs and market trends. It emphasized the need for investigating alternative cost modeling approaches that could consider multiple stressors and cascading impacts of such events during crisis times.

Practical Applications

Construction contracts could be agreed upon to include either fixed prices or fluctuating prices. In fixed-price contracts, contractors must estimate and agree on prices in advance by considering any possible fluctuation during the project. During the actual implementation of construction works, the contractor will absorb any unforeseen cost fluctuations. In fluctuating price contracts, contractors agree on prices based on the market conditions of a specified base date, and any fluctuation of prices due to the change of circumstance during the actual implementation of construction works will be paid to the contractor based on a preagreed formula and price index. This research investigated the financial risk of fixed-price construction contracts during extreme crisis periods taking the COVID-19 pandemic as an example. Authors found that fixed-price contracts agreed prior to a crisis period and ended during the early phase of a crisis may not be adversely affected. However, fixed-price contracts agreed during and later phases of a crisis period have a high chance of suffering significant financial losses beyond the profit margins.

Get full access to this article

View all available purchase options and get full access to this article.

Data Availability Statement

Some or all data, models, or code generated or used during the study are proprietary or confidential in nature and may only be provided with restrictions. Unavailable data includes actual BCSI TPI and BCIS GBCI index numbers. BCIS data is a subscribed service available at https://bcis.co.uk/product/bcis-online/. The data used for this research cannot be shared due to subscription conditions. Available data includes BCIS extraction criteria to extract BCSI TPI and BCIS GBCI index numbers coded in Table 2.

References

Works Cited

AECOM. 2022. Spon’s architects’ and builders’ price book 2022. Chennai, India: AECOM.
Akintoye, A. 2000. “Analysis of factors influencing project cost estimating practice.” Construct. Manage. Econ. 18 (1): 77–89. https://doi.org/10.1080/014461900370979.
Akintoye, S. A., and R. M. Skitmore. 1994. “A comparative analysis of three macro price forecasting models.” Construct. Manage. Econ. 12 (3): 257–270. https://doi.org/10.1080/01446199400000033.
ARCADIS. 2022. 2022 Global construction disputes report. Successfully navigating through turbulent times. Amsterdam, Netherlands: ARCADIS.
Ashuri, B., and J. Lu. 2010. “Time series analysis of ENR construction cost index.” J. Constr. Eng. Manage. 136 (11): 1227–1237. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000231.
Ashworth, A., and S. Perera. 2015. Cost studies of buildings. Abingdon, OX: Routledge.
Ayat, M., and C. W. Kang. 2023. “Effects of the COVID-19 pandemic on the construction sector: A systemized review.” Eng. Constr. Archit. Manage. 30 (2): 734–754. https://doi.org/10.1108/ECAM-08-2021-0704.
Bailey, J., N. Bouchardie, and I. Madalena. 2020. COVID-19: The current impact on construction and engineering projects. New York: White & Case Coronavirus Resource Center.
Baloi, D., and A. D. F. Price. 2003. “Modelling global risk factors affecting construction cost performance.” Int. J. Project Manage. 21 (4): 261–269. https://doi.org/10.1016/S0263-7863(02)00017-0.
BCIS (Building Cost Information Service). 2022. “BCIS tender price index panel.” Accessed November 14, 2022. https://bcis.co.uk/insight/bcis-tender-price-index-panel/.
BCIS (Building Cost Information Service). 2023a. “Are you using the right index? 6 golden rules to follow each time.” Accessed November 14, 2022. https://bcis.co.uk/insight/are-you-using-the-right-bcis-index/.
BCIS (Building Cost Information Service). 2023b. Indices. London: Royal Institution of Chartered Surveyors.
Best, R., and J. Meikle. 2015. Measuring construction: Prices, output and productivity. New York: Routledge.
del Rio-Chanona, R. M., P. Mealy, A. Pichler, F. Lafond, and J. D. Farmer. 2020. “Supply and demand shocks in the COVID-19 pandemic: An industry and occupation perspective.” Supplement, Oxford Rev. Econ. Policy 36 (S1): S94–S137. https://doi.org/10.1093/oxrep/graa033.
Fernandes, N. 2020. Economic effects of coronavirus outbreak (COVID-19) on the world economy. Barcelona, Spain: IESE Business School.
Gamil, Y., and A. Alhagar. 2020. “The impact of pandemic crisis on the survival of construction industry:A case of COVID-19.” Mediterr. J. Soc. Sci. 11 (4): 122. https://doi.org/10.36941/mjss-2020-0047.
Hook, J. 2020. “Engineering and construction in a post-COVID world: Weathering the storm.” Accessed November 6, 2022. https://www.pwc.com/gx/en/issues/crisis-solutions/COVID-19/engineering-construction-post-COVID-world.html.
JCT (Joint Contracts Tribunal). 2016. Formula rules 2016. London: Thomson Reuters.
JCT (Joint Contracts Tribunal). 2017. Formula rules 2016. London: Thomson Reuters.
King, S. S., R. A. Rahman, M. A. Fauzi, and A. T. Haron. 2021. “Mechanisms for addressing the impact of COVID-19 on infrastructure projects.” In Vol. 682 of Proc., IOP Conf. Series: Earth and Environmental Science, 012047. Bristol, UK: IOP Publishing.
Kirkham, R. 2014. Ferry and Brandon’s cost planning of buildings. Hoboken, NJ: Wiley.
Martin, J. 2016. “Inflation indices: Crossrail’s procurement strategy.” Accessed November 14, 2022. https://www.isurv.com/info/390/features/9750/inflation_indices_crossrail_s_procurement_strategy.
Moon, T., and D. H. Shin. 2017. “Forecasting construction cost index using interrupted time-series.” KSCE J. Civ. Eng. 22 (Aug): 1626–1633. https://doi.org/10.1007/s12205-017-0452-x.
NBS. 2018. “National construction contracts and law report 2018.” Accessed September 16, 2021. https://www.thenbs.com/knowledge/national-construction-contracts-and-law-report-2018.
NEC (New Engineering Contract). 2017. NEC4: Engineering and construction contract. London: NEC.
Ogunnusi, M., M. Hamma-Adama, H. Salman, and T. Kouider. 2020. “COVID-19 pandemic: The effects and prospects in the construction industry.” Supplement, Int. J. Real Estate Stud. 14 (S2): 120–128.
Ogunnusi, M., T. Omotayo, M. Hamma-Adama, B. O. Awuzie, and T. Egbelakin. 2021. “Lessons learned from the impact of COVID-19 on the global construction industry.” J. Eng. Des. Technol. 20 (1): 299–320. https://doi.org/10.1108/JEDT-05-2021-0286.
Olatunji, O. A. 2010. “The impact of oil price regimes on construction cost in Nigeria.” Construct. Manage. Econ. 28 (7): 747–759. https://doi.org/10.1080/01446191003725162.
Olatunji, O. A., A. O. Orundami, and O. Ogundare. 2018. “Causal relationship between material price fluctuation and project’s outturn costs.” Built Environ. Project Asset Manage. 8 (4): 358–371. https://doi.org/10.1108/BEPAM-12-2017-0119.
ONS (Office for National Statistics). 2017. “Consumer price indices, a brief guide: 2017.” Accessed September 16, 2021. https://www.ons.gov.uk/economy/inflationandpriceindices/articles/consumerpriceindicesabriefguide/2017.
Pamidimukkala, A., and S. Kermanshachi. 2021. “Impact of COVID-19 on field and office workforce in construction industry.” Project Leadersh. Soc. 2 (Dec): 100018. https://doi.org/10.1016/j.plas.2021.100018.
Price, D. 2019. “CN100 2019: The top 100 UK contractors.” Accessed November 27, 2022. https://www.constructionnews.co.uk/financial/cn100-2019-top-100-uk-contractors-05-09-2019/.
RICS (Royal Institution of Chartered Surveyors). 2016. RICS professional standards and guidance, UK—Fluctuations. London: RICS.
RICS (Royal Institution of Chartered Surveyors). 2020. “New tender price index calculation method developed for BCIS.” Accessed November 14, 2022. https://www.rics.org/uk/products/data-products/insights/new-tender-price-index-bcis/.
Shaw, M. 2020. “AGC Survey: 28% of members report halted or delayed projects due to COVID-19.” Engineering News Record. Accessed March 17, 2020. https://www.enr.com/articles/48976-agc-survey-28-percent-of-members-report-halted-or-delayed-projects-due-to-covid-19.
Suresh, S., S. Renukappa, and M. Stride. 2020. “The impact of COVID-19 on the UK construction industry.” Accessed January 25, 2021. https://wlv.openrepository.com/bitstream/handle/2436/623423/Stride_et_al_The_impact_of_Covid-19_on_the_UK_construction_industry_2020.pdf?sequence=3%26isAllowed=y.
Uchehara, I., M. Hamma-Adama, K. A. Obiri, N. Jafarifar, and D. Moore. 2020. “Impacts and risk management of COVID-19 pandemic on real estate supply chain.” Int. J. Real Estate Stud. 14 (S1).
US Bureau of Labor Statistics. 2020. The handbook of methods. Washington, DC: US Bureau of Labor Statistics.
Winch, G. M., D. Cao, E. Maytorena-Sanchez, J. Pinto, N. Sergeeva, and S. Zhang. 2021. “Operation warp speed: Projects responding to the COVID-19 pandemic.” Project Leadersh. Soc. 2 (Dec): 100019. https://doi.org/10.1016/j.plas.2021.100019.
Yin, R. K. 2009. Case study research: Design and methods. Thousand Oaks, CA: SAGE.

Information & Authors

Information

Published In

Go to Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
Volume 16Issue 3August 2024

History

Received: Jul 24, 2023
Accepted: Jan 5, 2024
Published online: May 3, 2024
Published in print: Aug 1, 2024
Discussion open until: Oct 3, 2024

Permissions

Request permissions for this article.

Authors

Affiliations

Thomas Gibbens
Quantity Surveyor, Essex County Council, County Hall Market Rd., Chelmsford CM1 1QH, UK.
Senior Lecturer, Faculty of Science and Engineering, Anglia Ruskin Univ., Bishop Hall Lane, Chelmsford CM1 1SQ, UK (corresponding author). ORCID: https://orcid.org/0000-0001-8889-8019. Email: [email protected]
Postgraduate Researcher, Faculty of Science and Engineering, Anglia Ruskin Univ., Bishop Hall Lane, Chelmsford CM1 1SQ, UK. Email: [email protected]
Senior Lecturer, Faculty of Science and Engineering, Anglia Ruskin Univ., Bishop Hall Lane, Chelmsford CM1 1SQ, UK. Email: [email protected]

Metrics & Citations

Metrics

Citations

Download citation

If you have the appropriate software installed, you can download article citation data to the citation manager of your choice. Simply select your manager software from the list below and click Download.

View Options

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Get Access

Access content

Please select your options to get access

Log in/Register Log in via your institution (Shibboleth)
ASCE Members: Please log in to see member pricing

Purchase

Save for later Information on ASCE Library Cards
ASCE Library Cards let you download journal articles, proceedings papers, and available book chapters across the entire ASCE Library platform. ASCE Library Cards remain active for 24 months or until all downloads are used. Note: This content will be debited as one download at time of checkout.

Terms of Use: ASCE Library Cards are for individual, personal use only. Reselling, republishing, or forwarding the materials to libraries or reading rooms is prohibited.
ASCE Library Card (5 downloads)
$105.00
Add to cart
ASCE Library Card (20 downloads)
$280.00
Add to cart
Buy Single Article
$35.00
Add to cart

Media

Figures

Other

Tables

Share

Share

Copy the content Link

Share with email

Email a colleague

Share